| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BEST-YET BUILDERS, LLC |
- 2 - BENTON & BROWN, LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
20,000.00 |
20,000.00 |
40,000.00 |
40,000.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
1,846   |
SQYD |
7.00 |
12,922.00 |
19.00 |
35,074.00 |
|
|
|
|
| 202-02-K |
removal of chain link fence
|
1,542   |
LNFT |
2.00 |
3,084.00 |
3.00 |
4,626.00 |
|
|
|
|
| 202-02-L |
removal of sand clay gravel base
|
8,543.0 |
SQYD |
3.00 |
25,629.00 |
2.00 |
17,086.00 |
|
|
|
|
| 203-01 |
general excavation
|
7,192   |
CUYD |
5.00 |
35,960.00 |
10.00 |
71,920.00 |
|
|
|
|
| 203-04 |
embankment
|
2,642   |
CUYD |
8.00 |
21,136.00 |
20.00 |
52,840.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
500   |
LNFT |
2.00 |
1,000.00 |
4.00 |
2,000.00 |
|
|
|
|
| 302-02-B |
class ii base course (8 1/2" thick)
|
839.7 |
SQYD |
15.50 |
13,015.35 |
16.00 |
13,435.20 |
|
|
|
|
| 302-02-D-01 |
class ii base course on embankment layer (12" thick)
(stone, recycled pccp or asphalt) |
14,286.9 |
SQYD |
18.00 |
257,164.20 |
20.00 |
285,738.00 |
|
|
|
|
| 304-05 |
lime treatment (type e)
|
249.38 |
TON |
412.71 |
102,921.62 |
370.00 |
92,270.60 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
1,294.8 |
CUYD |
1.00 |
1,294.80 |
34.00 |
44,023.20 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
5,186.3 |
TON |
80.00 |
414,904.00 |
80.00 |
414,904.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
332.3 |
TON |
90.00 |
29,907.00 |
80.00 |
26,584.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
11,423   |
SQYD |
1.25 |
14,278.75 |
3.00 |
34,269.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,535   |
CUYD |
0.10 |
- 153.50 |
1.00 |
- 1,535.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp/pp)
|
299   |
LNFT |
50.00 |
14,950.00 |
62.00 |
18,538.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp/pp)
|
118   |
LNFT |
60.00 |
7,080.00 |
90.00 |
10,620.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp/pp)
|
220   |
LNFT |
65.00 |
14,300.00 |
110.00 |
24,200.00 |
|
|
|
|
| 701-03-M |
storm drain pipe (36" rcp/pp)
|
195   |
LNFT |
100.00 |
19,500.00 |
133.00 |
25,935.00 |
|
|
|
|
| 701-03-N |
storm drain pipe (42" rcp/pp)
|
750   |
LNFT |
140.00 |
105,000.00 |
130.00 |
97,500.00 |
|
|
|
|
| 701-03-S |
storm drain pipe (72" rcp/pp)
|
804   |
LNFT |
400.00 |
321,600.00 |
530.00 |
426,120.00 |
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
31   |
LNFT |
100.00 |
3,100.00 |
150.00 |
4,650.00 |
|
|
|
|
| 702-02-B |
manholes (r-cb-11)
|
8   |
EACH |
2,500.00 |
20,000.00 |
5,100.00 |
40,800.00 |
|
|
|
|
| 702-02-E |
manholes (r-cb-32)
|
4   |
EACH |
4,500.00 |
18,000.00 |
8,400.00 |
33,600.00 |
|
|
|
|
| 702-02-I |
manholes (r-cb-20)
|
2   |
EACH |
3,000.00 |
6,000.00 |
4,400.00 |
8,800.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
4   |
EACH |
3,500.00 |
14,000.00 |
2,100.00 |
8,400.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
7   |
EACH |
3,500.00 |
24,500.00 |
3,100.00 |
21,700.00 |
|
|
|
|
| 702-03-E |
catch basins (cb-03)
|
6   |
EACH |
3,000.00 |
18,000.00 |
2,400.00 |
14,400.00 |
|
|
|
|
| 702-03-G |
catch basins (cb-09)
|
4   |
EACH |
4,000.00 |
16,000.00 |
4,800.00 |
19,200.00 |
|
|
|
|
| 705-06-D |
chain link fence (7-foot height)
|
1,521   |
LNFT |
16.00 |
24,336.00 |
21.00 |
31,941.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
2,767.7 |
SQYD |
45.00 |
124,546.50 |
50.00 |
138,385.00 |
|
|
|
|
| 706-02-D |
concrete drive (9" thick)
|
278.5 |
SQYD |
65.00 |
18,102.50 |
57.00 |
15,874.50 |
|
|
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
240.7 |
SQYD |
40.00 |
9,628.00 |
48.00 |
11,553.60 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
6,989.8 |
LNFT |
30.00 |
209,694.00 |
24.00 |
167,755.20 |
|
|
|
|
| 710-01 |
flowable fill
|
33   |
CUYD |
75.00 |
2,475.00 |
154.00 |
5,082.00 |
|
|
|
|
| 711-01-D |
riprap (55 lb, 36" thick)
|
67   |
SQYD |
75.00 |
5,025.00 |
180.00 |
12,060.00 |
|
|
|
|
| 712-01-A |
concrete cast-in-place revetment (4" thick)
|
156   |
SQYD |
40.00 |
6,240.00 |
50.00 |
7,800.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
50,000.00 |
50,000.00 |
240,000.00 |
240,000.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
1.547 |
MILE |
1.00 |
1.55 |
340.00 |
525.98 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
2.648 |
MILE |
1.00 |
2.65 |
800.00 |
2,118.40 |
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
197   |
SQYD |
3.00 |
591.00 |
2.00 |
394.00 |
|
|
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
10,000.00 |
10,000.00 |
3,000.00 |
3,000.00 |
|
|
|
|
| 725-02 |
temporary detour roads
|
140.2 |
SQYD |
38.97 |
5,463.59 |
28.00 |
3,925.60 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
150,000.00 |
150,000.00 |
240,000.00 |
240,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
560   |
EACH |
5.10 |
2,856.00 |
6.00 |
3,360.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
100   |
LNFT |
2.90 |
290.00 |
3.00 |
300.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
3.654 |
MILE |
2,160.00 |
7,892.64 |
2,800.00 |
10,231.20 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.210 |
MILE |
960.00 |
1,161.60 |
1,100.00 |
1,331.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
10   |
EACH |
155.00 |
1,550.00 |
165.00 |
1,650.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
0.885 |
MILE |
4,820.00 |
4,265.70 |
6,800.00 |
6,018.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
7.00 |
ACRE |
1,200.00 |
8,400.00 |
1,700.00 |
11,900.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
50,000.00 |
50,000.00 |
65,000.00 |
65,000.00 |
|
|
|
|
| 742-01-A |
sanitary sewer pipe (8" pvc)
|
768   |
LNFT |
20.00 |
15,360.00 |
48.00 |
36,864.00 |
|
|
|
|
| 742-01-B |
sanitary sewer pipe (8" dip)
|
43   |
LNFT |
40.00 |
1,720.00 |
77.00 |
3,311.00 |
|
|
|
|
| 742-01-C |
sanitary sewer pipe (12" pvc)
|
421   |
LNFT |
35.00 |
14,735.00 |
60.00 |
25,260.00 |
|
|
|
|
| 742-02 |
adjusting sanitary sewer house connections
|
6   |
EACH |
600.00 |
3,600.00 |
785.00 |
4,710.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
25,000.00 |
25,000.00 |
54,000.00 |
54,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,308,029.95 |
|
2,992,048.48 |
|
|
|
|
|