| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - T.L. CONSTRUCTION INC |
- 2 - C W & W CONTRACTORS, INC. |
- 3 - QUALITY DESIGN & CONSTRUCTION, INC. |
- 4 - GUINN BROTHERS, LLC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
12,000.00 |
12,000.00 |
15,000.00 |
15,000.00 |
16,789.10 |
16,789.10 |
15,000.00 |
15,000.00 |
| 202-02-A-01 |
removal of bridge(sta. 105+00,20.8' wide x 57.8' long
timber bridge with wingwalls) |
1   |
EACH |
10,000.00 |
10,000.00 |
7,500.00 |
7,500.00 |
7,687.10 |
7,687.10 |
8,000.00 |
8,000.00 |
| 203-06 |
excavation & embankment
|
lump |
LUMP |
35,000.00 |
35,000.00 |
16,000.00 |
16,000.00 |
31,682.40 |
31,682.40 |
35,000.00 |
35,000.00 |
| 204-02 |
temporary hay or straw bales
|
5   |
EACH |
15.00 |
75.00 |
10.00 |
50.00 |
13.20 |
66.00 |
10.00 |
50.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
150.00 |
600.00 |
125.00 |
500.00 |
181.50 |
726.00 |
100.00 |
400.00 |
| 204-06 |
temporary silt fencing
|
225   |
LNFT |
3.00 |
675.00 |
3.00 |
675.00 |
3.10 |
697.50 |
3.00 |
675.00 |
| 302-01 |
class ii base course
|
76.6 |
CUYD |
50.00 |
3,830.00 |
80.00 |
6,128.00 |
95.04 |
7,280.06 |
110.00 |
8,426.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
11   |
CUYD |
60.00 |
660.00 |
80.00 |
880.00 |
64.60 |
710.60 |
110.00 |
1,210.00 |
| 502-01 |
superpave asphaltic concrete
|
59.2 |
TON |
300.00 |
17,760.00 |
200.00 |
11,840.00 |
309.00 |
18,292.80 |
250.00 |
14,800.00 |
| 701-05-G |
side drain pipe (18")
|
48   |
LNFT |
57.00 |
2,736.00 |
45.00 |
2,160.00 |
43.40 |
2,083.20 |
100.00 |
4,800.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,000.00 |
6,000.00 |
5,000.00 |
5,000.00 |
26,988.70 |
26,988.70 |
10,000.00 |
10,000.00 |
| 720-01-A |
erosion control system, slope protection (type a)
|
465   |
SQYD |
2.10 |
976.50 |
2.00 |
930.00 |
2.80 |
1,302.00 |
3.50 |
1,627.50 |
| 726-01 |
bedding material
|
129.2 |
CUYD |
40.00 |
5,168.00 |
100.00 |
12,920.00 |
153.30 |
19,806.36 |
100.00 |
12,920.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
16,995.00 |
16,995.00 |
65,000.00 |
65,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
4   |
EACH |
100.00 |
400.00 |
100.00 |
400.00 |
78.10 |
312.40 |
100.00 |
400.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
3,500.00 |
3,500.00 |
5,000.00 |
5,000.00 |
10,483.20 |
10,483.20 |
5,000.00 |
5,000.00 |
| 805-01-B |
class a concrete (box culvert headwalls)
|
53.96 |
CUYD |
900.00 |
48,564.00 |
1,000.00 |
53,960.00 |
995.20 |
53,700.99 |
1,500.00 |
80,940.00 |
| 805-12-V |
reinforced concrete box culverts (9'x 9')
|
123.0 |
LNFT |
710.00 |
87,330.00 |
1,100.00 |
135,300.00 |
983.70 |
120,995.10 |
1,250.00 |
153,750.00 |
| 806-01 |
deformed reinforcing steel
|
4,199   |
LB |
1.00 |
4,199.00 |
2.00 |
8,398.00 |
2.60 |
10,917.40 |
5.00 |
20,995.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
249,473.50 |
|
297,641.00 |
|
347,515.91 |
|
438,993.50 |
|