Lead Project: 451-02-0083
Parish: BOSSIER
Routes: I-20
Description: PAVEMENT MARKING REPLACEMENT WEST AND EASTBOUND LANES
Type Const: pavement striping and related work.
Estimated Construction Cost: $428,900.00
 
RankLicenseBidderConstruction Bid
1 24518 HIGHWAY GRAPHICS INC. $298,430.00
2 23811 UNITED RENTALS HWY TECHNOLOGIES INC $357,800.00
3 06799 PAV'T-MARK. CO, DIV OF GULF IND INC $425,476.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
HIGHWAY GRAPHICS INC.
- 2 -
UNITED RENTALS HWY TECHNOLOGIES INC
- 3 -
PAV'T-MARK. CO, DIV OF GULF IND INC

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
713-01 temporary signs & barricades lump      LUMP 5,000.00 5,000.00 15,000.00 15,000.00 40,000.00 40,000.00    
727-01 mobilization lump      LUMP 5,000.00 5,000.00 30,000.00 30,000.00 50,000.00 50,000.00    
731-02 reflectorized raised pavement markers 4,000      EACH 4.00 16,000.00 5.50 22,000.00 5.20 20,800.00    
732-02-A plastic pavement striping (solid line) (4" width) 44.000  MILE 2,350.00 103,400.00 2,300.00 101,200.00 2,365.00 104,060.00    
732-02-C plastic pavement striping (solid line) (8" width) 1.500  MILE 7,000.00 10,500.00 5,000.00 7,500.00 4,730.00 7,095.00    
732-03-A-01 plastic pvmt striping (broken line)(4"width)preformed
marking tape) (type v)
22.700  MILE 3,900.00 88,530.00 5,000.00 113,500.00 3,630.00 82,401.00    
732-04-F-01 plastic pavement legends & symbols (exit only)
(performed marking tape) (type v)
2      EACH 1,500.00 3,000.00 1,000.00 2,000.00 760.00 1,520.00    
732-05 removal of existing markings 22.000  MILE 3,000.00 66,000.00 2,800.00 61,600.00 4,300.00 94,600.00    
744-01 traffic control management lump      LUMP 1,000.00 1,000.00 5,000.00 5,000.00 25,000.00 25,000.00    
                       
 CONTRACTOR TOTAL       298,430.00   357,800.00   425,476.00    