Letting of 5/10/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 006-01-0022
Parish: JEFFERSON
Routes: US 90
Description: HUEY P. LONG BRIDGE WIDENING (RAILROAD MODIFICATIONS)
Type Const: replace existing steel railroad deck girders and steel tower bents with concrete
straddle bents and steel deck girders and related work.
Estimated Construction Cost: $17,305,812.37
 
RankLicenseBidderConstruction Bid
1 02179 BOH BROS. CONSTRUCTION CO., LLC. $12,123,324.02
2 12370 HILL BROS. CONST & ENGINEERING INC. $16,337,568.55
3 28665 KIEWIT SOUTHERN CO. $17,417,597.50
4 00271 MASSMAN CONSTRUCTION CO. $17,456,404.30
5 07779 ROSIEK CONSTRUCTION CO INC $20,516,783.05
 
Item Number Item Description Quantity Unit of Measure - 1 -
BOH BROS. CONSTRUCTION CO., LLC.
- 2 -
HILL BROS. CONST & ENGINEERING INC.
- 3 -
KIEWIT SOUTHERN CO.
- 4 -
MASSMAN CONSTRUCTION CO.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
302-02-D class ii base course (12" thick) 99.3    SQYD 72.00 7,149.60 150.00 14,895.00 200.00 19,860.00 40.00 3,972.00
502-01 superpave asphaltic concrete 45.7    TON 350.00 15,995.00 400.00 18,280.00 200.00 9,140.00 150.00 6,855.00
704-01-C guard rail (double thrie beam)(3'-1 1/2" post spacing) 37.5    LNFT 63.00 2,362.50 56.00 2,100.00 50.00 1,875.00 50.00 1,875.00
704-03 blocked out guard rail 29.0    LNFT 23.00 667.00 20.00 580.00 18.00 522.00 18.00 522.00
704-06-A guard rail anchor sections (trailing end)(single thrie
beam)
6.3    LNFT 85.00 535.50 80.00 504.00 70.00 441.00 70.00 441.00
704-11-A guard rail end treatment (flared) 1      EACH 2,700.00 2,700.00 2,600.00 2,600.00 2,300.00 2,300.00 2,300.00 2,300.00
713-01 temporary signs & barricades lump      LUMP 25,000.00 25,000.00 20,000.00 20,000.00 20,000.00 20,000.00 16,000.00 16,000.00
713-02 temporary pavement markings lump      LUMP 3,200.00 3,200.00 2,800.00 2,800.00 2,500.00 2,500.00 6,000.00 6,000.00
713-08 temporary precast concrete barrier (contractor
furnished)
13      EACH 825.00 10,725.00 1,600.00 20,800.00 1,500.00 19,500.00 2,000.00 26,000.00
727-01 mobilization lump      LUMP 1,000,000.00 1,000,000.00 800,000.00 800,000.00 1,700,000.00 1,700,000.00 1,700,000.00 1,700,000.00
731-02 reflectorized raised pavement markers 11      EACH 8.00 88.00 8.00 88.00 7.00 77.00 7.00 77.00
732-01-A plastic pavement striping (4" width) 414      LNFT 0.63 260.82 0.70 289.80 0.50 207.00 0.50 207.00
732-01-C plastic pavement striping (8" width) 33      LNFT 1.25 41.25 2.50 82.50 1.00 33.00 1.00 33.00
740-01 construction layout lump      LUMP 101,000.00 101,000.00 200,000.00 200,000.00 300,000.00 300,000.00 50,000.00 50,000.00
744-01 traffic control management lump      LUMP 20,000.00 20,000.00 100,000.00 100,000.00 40,000.00 40,000.00 100,000.00 100,000.00
802-01 structural excavation 2,785.1    CUYD 50.00 139,255.00 500.00 1,392,550.00 400.00 1,114,040.00 700.00 1,949,570.00
804-03-H steel piles (hp 14x102) 28,756      LNFT 56.00 1,610,336.00 85.00 2,444,260.00 65.00 1,869,140.00 90.00 2,588,040.00
804-07 steel test piles 4      EACH 11,500.00 46,000.00 10,500.00 42,000.00 100,000.00 400,000.00 33,000.00 132,000.00
804-09 loading test piles 4      EACH 32,000.00 128,000.00 6,000.00 24,000.00 40,000.00 160,000.00 75,000.00 300,000.00
804-10 reloading test piles 1      EACH 500.00 500.00 6,000.00 6,000.00 10,000.00 10,000.00 10,000.00 10,000.00
804-11 redriving test piles 1      EACH 750.00 750.00 3,000.00 3,000.00 5,000.00 5,000.00 8,000.00 8,000.00
804-12 loading permanent piles 1      EACH 25,000.00 25,000.00 6,000.00 6,000.00 10,000.00 10,000.00 50,000.00 50,000.00
804-17 dynamic monitoring 4      EACH 2,600.00 10,400.00 4,000.00 16,000.00 2,000.00 8,000.00 2,000.00 8,000.00
805-02-D class a(m) concrete (footings) 1,254.44   CUYD 310.00 388,876.40 450.00 564,498.00 1,200.00 1,505,328.00 500.00 627,220.00
805-02-F class a(m) concrete (bents) 2,156.00   CUYD 515.00 1,110,340.00 750.00 1,617,000.00 1,700.00 3,665,200.00 1,100.00 2,371,600.00
806-01 deformed reinforcing steel 756,993      LB 1.15 870,541.95 1.25 946,241.25 1.50 1,135,489.50 1.10 832,692.30
807-06 structural metalwork lump      LUMP 5,700,000.00 5,700,000.00 6,200,000.00 6,200,000.00 3,930,945.00 3,930,945.00 5,152,000.00 5,152,000.00
S-001 removal of eastbank railroad structure lump      LUMP 206,000.00 206,000.00 230,000.00 230,000.00 500,000.00 500,000.00 600,000.00 600,000.00
S-002 removal of westbank railroad structure lump      LUMP 55,000.00 55,000.00 600,000.00 600,000.00 200,000.00 200,000.00 300,000.00 300,000.00
S-003 removal of gas station lump      LUMP 53,000.00 53,000.00 70,000.00 70,000.00 300,000.00 300,000.00 50,000.00 50,000.00
S-004 removal of eastbank power poles and power lines lump      LUMP 15,000.00 15,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00
S-101 railroad deck lump      LUMP 420,000.00 420,000.00 600,000.00 600,000.00 300,000.00 300,000.00 324,000.00 324,000.00
S-102 construction site survey lump      LUMP 51,000.00 51,000.00 125,000.00 125,000.00 20,000.00 20,000.00 150,000.00 150,000.00
S-103 vibration monitoring lump      LUMP 46,000.00 46,000.00 250,000.00 250,000.00 150,000.00 150,000.00 75,000.00 75,000.00
S-104 dynamic analysis 4      each 14,400.00 57,600.00 2,000.00 8,000.00 2,000.00 8,000.00 1,000.00 4,000.00
                       
 CONTRACTOR TOTAL       12,123,324.02   16,337,568.55   17,417,597.50   17,456,404.30
 
Item Number Item Description Quantity Unit of Measure - 5 -
ROSIEK CONSTRUCTION CO INC

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
302-02-D class ii base course (12" thick) 99.3    SQYD 35.00 3,475.50            
502-01 superpave asphaltic concrete 45.7    TON 800.00 36,560.00            
704-01-C guard rail (double thrie beam)(3'-1 1/2" post spacing) 37.5    LNFT 50.00 1,875.00            
704-03 blocked out guard rail 29.0    LNFT 20.00 580.00            
704-06-A guard rail anchor sections (trailing end)(single thrie
beam)
6.3    LNFT 100.00 630.00            
704-11-A guard rail end treatment (flared) 1      EACH 2,500.00 2,500.00            
713-01 temporary signs & barricades lump      LUMP 20,000.00 20,000.00            
713-02 temporary pavement markings lump      LUMP 2,500.00 2,500.00            
713-08 temporary precast concrete barrier (contractor
furnished)
13      EACH 1,100.00 14,300.00            
727-01 mobilization lump      LUMP 2,050,000.00 2,050,000.00            
731-02 reflectorized raised pavement markers 11      EACH 7.00 77.00            
732-01-A plastic pavement striping (4" width) 414      LNFT 1.00 414.00            
732-01-C plastic pavement striping (8" width) 33      LNFT 1.10 36.30            
740-01 construction layout lump      LUMP 300,000.00 300,000.00            
744-01 traffic control management lump      LUMP 200,000.00 200,000.00            
802-01 structural excavation 2,785.1    CUYD 100.00 278,510.00            
804-03-H steel piles (hp 14x102) 28,756      LNFT 100.00 2,875,600.00            
804-07 steel test piles 4      EACH 15,000.00 60,000.00            
804-09 loading test piles 4      EACH 50,000.00 200,000.00            
804-10 reloading test piles 1      EACH 25,000.00 25,000.00            
804-11 redriving test piles 1      EACH 6,000.00 6,000.00            
804-12 loading permanent piles 1      EACH 60,000.00 60,000.00            
804-17 dynamic monitoring 4      EACH 8,000.00 32,000.00            
805-02-D class a(m) concrete (footings) 1,254.44   CUYD 1,100.00 1,379,884.00            
805-02-F class a(m) concrete (bents) 2,156.00   CUYD 1,100.00 2,371,600.00            
806-01 deformed reinforcing steel 756,993      LB 1.25 946,241.25            
807-06 structural metalwork lump      LUMP 6,921,000.00 6,921,000.00            
S-001 removal of eastbank railroad structure lump      LUMP 1,400,000.00 1,400,000.00            
S-002 removal of westbank railroad structure lump      LUMP 250,000.00 250,000.00            
S-003 removal of gas station lump      LUMP 150,000.00 150,000.00            
S-004 removal of eastbank power poles and power lines lump      LUMP 8,000.00 8,000.00            
S-101 railroad deck lump      LUMP 700,000.00 700,000.00            
S-102 construction site survey lump      LUMP 150,000.00 150,000.00            
S-103 vibration monitoring lump      LUMP 60,000.00 60,000.00            
S-104 dynamic analysis 4      each 2,500.00 10,000.00            
                       
 CONTRACTOR TOTAL       20,516,783.05            