| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
- 2 - BARBER BROS. CONTRACTING CO., L.L.C |
- 3 - COASTAL BRIDGE CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
114   |
SQYD |
15.00 |
1,710.00 |
30.00 |
3,420.00 |
50.00 |
5,700.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
760   |
CUYD |
9.00 |
6,840.00 |
22.00 |
16,720.00 |
5.00 |
3,800.00 |
|
|
| 203-08-A |
borrow (vehicular meas.)(selected soils)
|
1,228   |
CUYD |
9.00 |
11,052.00 |
15.00 |
18,420.00 |
5.00 |
6,140.00 |
|
|
| 204-06 |
temporary silt fencing
|
5,280   |
LNFT |
1.25 |
6,600.00 |
1.00 |
5,280.00 |
0.10 |
528.00 |
|
|
| 304-01 |
lime
|
39.09 |
TON |
150.00 |
5,863.50 |
180.00 |
7,036.20 |
125.00 |
4,886.25 |
|
|
| 304-03-D |
lime treatment (type c) (12" thick)
|
552   |
SQYD |
6.00 |
3,312.00 |
4.50 |
2,484.00 |
12.50 |
6,900.00 |
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
1,105   |
SQYD |
6.00 |
6,630.00 |
6.50 |
7,182.50 |
6.00 |
6,630.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
907   |
CUYD |
6.00 |
5,442.00 |
20.00 |
18,140.00 |
40.00 |
36,280.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
8,106.7 |
TON |
50.00 |
405,335.00 |
60.00 |
486,402.00 |
65.00 |
526,935.50 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnout and
miscellaneous |
644.3 |
TON |
100.00 |
64,430.00 |
80.00 |
51,544.00 |
100.00 |
64,430.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
37,976   |
SQYD |
1.50 |
56,964.00 |
2.00 |
75,952.00 |
3.20 |
121,523.20 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 950   |
CUYD |
0.01 |
- 9.50 |
0.00 |
0.00 |
1.00 |
- 950.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
261.6 |
LNFT |
43.00 |
11,248.80 |
50.00 |
13,080.00 |
42.00 |
10,987.20 |
|
|
| 704-03 |
blocked out guard rail
|
393.9 |
LNFT |
16.00 |
6,302.40 |
20.00 |
7,878.00 |
15.00 |
5,908.50 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
6   |
EACH |
2,000.00 |
12,000.00 |
2,500.00 |
15,000.00 |
2,000.00 |
12,000.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
50.0 |
SQYD |
65.00 |
3,250.00 |
100.00 |
5,000.00 |
60.00 |
3,000.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
97,000.00 |
97,000.00 |
25,000.00 |
25,000.00 |
15,000.00 |
15,000.00 |
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
500   |
LNFT |
0.15 |
75.00 |
1.00 |
500.00 |
0.20 |
100.00 |
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
400   |
LNFT |
0.50 |
200.00 |
2.00 |
800.00 |
0.60 |
240.00 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
10.590 |
MILE |
500.00 |
5,295.00 |
350.00 |
3,706.50 |
400.00 |
4,236.00 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
5.034 |
MILE |
10.00 |
50.34 |
400.00 |
2,013.60 |
300.00 |
1,510.20 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
19.814 |
MILE |
100.00 |
1,981.40 |
630.00 |
12,482.82 |
1.00 |
19.81 |
|
|
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
2   |
EACH |
75.00 |
150.00 |
250.00 |
500.00 |
200.00 |
400.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
6,000.00 |
6,000.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
100,000.00 |
100,000.00 |
30,000.00 |
30,000.00 |
95,000.00 |
95,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
44   |
EACH |
50.00 |
2,200.00 |
60.00 |
2,640.00 |
45.00 |
1,980.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
70.00 |
560.00 |
75.00 |
600.00 |
65.00 |
520.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
468   |
EACH |
7.00 |
3,276.00 |
6.00 |
2,808.00 |
5.00 |
2,340.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
250   |
LNFT |
2.00 |
500.00 |
1.50 |
375.00 |
1.00 |
250.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
200   |
LNFT |
4.00 |
800.00 |
3.50 |
700.00 |
2.50 |
500.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
8.958 |
MILE |
2,500.00 |
22,395.00 |
2,800.00 |
25,082.40 |
2,400.00 |
21,499.20 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.678 |
MILE |
2,000.00 |
3,356.00 |
1,000.00 |
1,678.00 |
700.00 |
1,174.60 |
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
2   |
EACH |
1,000.00 |
2,000.00 |
500.00 |
1,000.00 |
400.00 |
800.00 |
|
|
| 735-01 |
mailboxes
|
85   |
EACH |
5.00 |
425.00 |
5.00 |
425.00 |
1.00 |
85.00 |
|
|
| 735-02 |
mailbox supports (single)
|
81   |
EACH |
120.00 |
9,720.00 |
150.00 |
12,150.00 |
95.00 |
7,695.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
200.00 |
400.00 |
200.00 |
400.00 |
135.00 |
270.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
50,000.00 |
50,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
50,000.00 |
50,000.00 |
25,000.00 |
25,000.00 |
20,000.00 |
20,000.00 |
|
|
| S-001 |
cement treated base course (12 in depth)
|
44,182   |
SQYD |
5.00 |
220,910.00 |
7.00 |
309,274.00 |
8.00 |
353,456.00 |
|
|
| S-002 |
special anchor section
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,500.00 |
3,000.00 |
900.00 |
1,800.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,190,263.94 |
|
1,218,674.02 |
|
1,374,574.46 |
|
|
|