Letting of 2/22/2006 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 713-49-0105
Parish: ST LANDRY
Routes:
Description: SPANISH TRAIL ROAD BRIDGE
Type Const: clearing and grubbing, drainage structures, precast prestressed concrete girder
spans bridge, and related work.
Estimated Construction Cost: $213,959.50
 
RankLicenseBidderConstruction Bid
1 08815 W. E. MCDONALD & SON, LLC. $301,037.60
2 00060 F. MILLER & SONS, LLC $329,162.80
3 09090 GUINN BROTHERS, LLC. $342,919.20
4 18546 C W & W CONTRACTORS, INC. $409,188.80
 
Item Number Item Description Quantity Unit of Measure - 1 -
W. E. MCDONALD & SON, LLC.
- 2 -
F. MILLER & SONS, LLC
- 3 -
GUINN BROTHERS, LLC.
- 4 -
C W & W CONTRACTORS, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      lump 25,000.00 25,000.00 9,400.00 9,400.00 20,000.00 20,000.00 30,000.00 30,000.00
202-02-A-01 removal of bridge(sta. 10+000;15.544m x 5.486m timber
bridge)
1      ea 10,000.00 10,000.00 6,000.00 6,000.00 10,000.00 10,000.00 12,500.00 12,500.00
203-06 excavation & embankment lump      lump 10,000.00 10,000.00 28,000.00 28,000.00 15,000.00 15,000.00 20,000.00 20,000.00
204-02 temporary hay or straw bales 20      ea 25.00 500.00 12.00 240.00 10.00 200.00 10.00 200.00
204-03 temporary slope drains 10      ln m 50.00 500.00 30.00 300.00 10.00 100.00 35.00 350.00
204-05-A temporary sediment check dams (hay) 4      ea 200.00 800.00 130.00 520.00 100.00 400.00 125.00 500.00
204-06 temporary silt fencing 320      ln m 12.00 3,840.00 6.00 1,920.00 5.00 1,600.00 10.00 3,200.00
403-01 aggregate roadway surfacing (vehicular measurement) 75.0    cu m 200.00 15,000.00 95.00 7,125.00 95.00 7,125.00 105.00 7,875.00
701-05-G-01 side drain pipe (450 mm)(erosion) 87.0    ln m 95.00 8,265.00 96.00 8,352.00 138.00 12,006.00 90.00 7,830.00
701-05-I side drain pipe (600 mm) 18.0    ln m 135.00 2,430.00 158.00 2,844.00 215.00 3,870.00 125.00 2,250.00
701-05-I-01 side drain pipe (600 mm)(erosion) 16.0    ln m 145.00 2,320.00 158.00 2,528.00 215.00 3,440.00 125.00 2,000.00
702-03-A catch basins (cb-01) 1      ea 3,800.00 3,800.00 4,000.00 4,000.00 4,300.00 4,300.00 3,500.00 3,500.00
704-08-B guard rail transitions (double thrie beam) 30.48   ln m 172.00 5,242.56 580.00 17,678.40 195.00 5,943.60 215.00 6,553.20
704-09 guard rail anchor sections (turndown) 30.48   ln m 73.00 2,225.04 260.00 7,924.80 95.00 2,895.60 95.00 2,895.60
705-01 barbed wire fence 32      ln m 18.00 576.00 45.00 1,440.00 35.00 1,120.00 30.00 960.00
705-05 double swinging driveway gates 1      dbgt 750.00 750.00 1,200.00 1,200.00 1,500.00 1,500.00 1,500.00 1,500.00
712-04 flexible revetment 300      sq m 54.00 16,200.00 60.00 18,000.00 85.00 25,500.00 100.00 30,000.00
713-01 temporary signs & barricades lump      lump 10,000.00 10,000.00 8,800.00 8,800.00 12,000.00 12,000.00 15,000.00 15,000.00
726-01 bedding material 2.5    cu m 200.00 500.00 220.00 550.00 350.00 875.00 250.00 625.00
727-01 mobilization lump      lump 25,000.00 25,000.00 30,000.00 30,000.00 50,000.00 50,000.00 63,000.00 63,000.00
729-16-C object marker assembly (type 3) 8      ea 70.00 560.00 70.00 560.00 95.00 760.00 100.00 800.00
740-01 construction layout lump      lump 5,000.00 5,000.00 6,400.00 6,400.00 8,000.00 8,000.00 10,000.00 10,000.00
804-01-B precast concrete piles (350 mm) 250.2    ln m 140.00 35,028.00 153.00 38,280.60 165.00 41,283.00 250.00 62,550.00
804-12 loading permanent piles 1      ea 1.00 1.00 100.00 100.00 1.00 1.00 100.00 100.00
805-10-A bridge superstructure & substructure(90 degree
crossing,7.3m roadway; precast)
5      span 23,500.00 117,500.00 25,400.00 127,000.00 23,000.00 115,000.00 25,000.00 125,000.00
                       
 CONTRACTOR TOTAL       301,037.60   329,162.80   342,919.20   409,188.80