| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GUINN BROTHERS, LLC. |
- 2 - W. E. MCDONALD & SON, LLC. |
- 3 - F. MILLER & SONS, LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
2,000.00 |
2,000.00 |
10,000.00 |
10,000.00 |
9,500.00 |
9,500.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
5,300.00 |
5,300.00 |
|
|
| 202-02-A-01 |
removal of bridge(stat.505+88,25.67' wide x 133'long
concrete slab span bridge w/timber piles) |
1   |
EACH |
14,000.00 |
14,000.00 |
8,000.00 |
8,000.00 |
14,400.00 |
14,400.00 |
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
5,000.00 |
5,000.00 |
7,500.00 |
7,500.00 |
5,800.00 |
5,800.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
30   |
EACH |
FREE |
FREE |
1.00 |
30.00 |
10.00 |
300.00 |
|
|
| 204-03 |
temporary slope drains
|
200   |
LNFT |
FREE |
FREE |
1.00 |
200.00 |
9.00 |
1,800.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
FREE |
FREE |
1.00 |
4.00 |
130.00 |
520.00 |
|
|
| 204-06 |
temporary silt fencing
|
400   |
LNFT |
FREE |
FREE |
2.00 |
800.00 |
2.00 |
800.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
21   |
CUYD |
100.00 |
2,100.00 |
100.00 |
2,100.00 |
120.00 |
2,520.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
87.7 |
TON |
200.00 |
17,540.00 |
300.00 |
26,310.00 |
170.00 |
14,909.00 |
|
|
| 704-03 |
blocked out guard rail
|
12.5 |
LNFT |
35.00 |
437.50 |
25.00 |
312.50 |
25.00 |
312.50 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
25.0 |
LNFT |
68.00 |
1,700.00 |
65.00 |
1,625.00 |
56.00 |
1,400.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,500.00 |
10,000.00 |
2,500.00 |
10,000.00 |
2,300.00 |
9,200.00 |
|
|
| 711-01-D |
riprap (55 lb,18" thick)
|
311   |
SQYD |
65.00 |
20,215.00 |
95.00 |
29,545.00 |
100.00 |
31,100.00 |
|
|
| 711-04 |
geotextile fabric
|
311   |
SQYD |
5.00 |
1,555.00 |
3.00 |
933.00 |
3.00 |
933.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
12,000.00 |
12,000.00 |
15,000.00 |
15,000.00 |
31,200.00 |
31,200.00 |
|
|
| 724-02 |
pavement widening
|
48.2 |
SQYD |
195.00 |
9,399.00 |
175.00 |
8,435.00 |
210.00 |
10,122.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
32,000.00 |
32,000.00 |
50,000.00 |
50,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
85.00 |
340.00 |
75.00 |
300.00 |
66.00 |
264.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
8,000.00 |
8,000.00 |
7,500.00 |
7,500.00 |
21,200.00 |
21,200.00 |
|
|
| 804-01-C-01 |
precast concrete piles (16")(hpc)
|
2,040   |
LNFT |
58.00 |
118,320.00 |
60.00 |
122,400.00 |
44.80 |
91,392.00 |
|
|
| 804-12 |
loading permanent piles
|
1   |
EACH |
1.00 |
1.00 |
1.00 |
1.00 |
100.00 |
100.00 |
|
|
| 805-10-A |
bridge superstructure & substructure (28'-90 degree
crossing, precast special bents)(hpc) |
7   |
SPAN |
23,000.00 |
161,000.00 |
26,000.00 |
182,000.00 |
26,000.00 |
182,000.00 |
|
|
| S-101 |
concrete approach slabs (without asphalt)(28'-
90 degree crossing)(hpc) |
2   |
EACH |
10,000.00 |
20,000.00 |
12,500.00 |
25,000.00 |
12,200.00 |
24,400.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
443,607.50 |
|
494,995.50 |
|
509,472.50 |
|
|
|