Letting of 1/25/2006 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 261-03-0017
Parish: TANGIPAHOA
Routes: LA 22 9 td>
Description: LIVINGSTON LINE - WEST JCT. U.S. 51 BUS.
Type Const: grading, cold planing asphaltic concrete,pavement patching, superpave asphaltic
concrete pavement overlay and related work
 
RankLicenseBidderAmount
106276 BARRIERE CONSTRUCTION CO., LLC. $1,887,936.60
212487 DIAMOND B CONSTRUCTION CO., L.L.C. $1,999,854.86
300849 F.G. SULLIVAN, JR. CONTRACTOR LLC $2,417,629.90
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARRIERE CONSTRUCTION CO., LLC.
- 2 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 3 -
F.G. SULLIVAN, JR. CONTRACTOR LLC

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-C removal of portland cement concrete pavement 500      SQYD 12.00 6,000.00 12.00 6,000.00 7.00 3,500.00    
202-02-H removal of guard rail 1,481      LNFT 4.50 6,664.50 5.00 7,405.00 5.00 7,405.00    
203-08 borrow (vehicular measurement) 1,000      CUYD 16.00 16,000.00 26.00 26,000.00 15.00 15,000.00    
502-01 superpave asphaltic concrete 20,676.9    TON 58.00 1,199,260.20 56.00 1,157,906.40 60.00 1,240,614.00    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
984.0    TON 85.00 83,640.00 100.00 98,400.00 115.00 113,160.00    
509-01 cold planing asphaltic pavement 81,725      SQYD 2.00 163,450.00 1.20 98,070.00 3.00 245,175.00    
509-02 contractor retained reclaimed asphaltic pavement - 2,270      CUYD 5.00 - 11,350.00 0.10 - 227.00 0.01 - 22.70    
602-02-A cleaning and resealing existing longitudinal pavement
joints
3,802      LNFT 1.70 6,463.40 1.50 5,703.00 2.00 7,604.00    
602-02-B cleaning and resealing existing transverse pavement
joints
2,148      LNFT 1.70 3,651.60 1.80 3,866.40 2.00 4,296.00    
602-03 cleaning and sealing random cracks 300      LNFT 4.00 1,200.00 4.00 1,200.00 3.00 900.00    
701-02-D/E cross drain pipe arch (24" equiv. rcpa or 30" equiv.
cmpa)
140      LNFT 150.00 21,000.00 100.00 14,000.00 100.00 14,000.00    
704-01-C guard rail (double thrie beam)(3'-1 1/2" post spacing) 81.3    LNFT 47.00 3,821.10 55.00 4,471.50 45.00 3,658.50    
704-03 blocked out guard rail 318.8    LNFT 18.00 5,738.40 20.00 6,376.00 18.00 5,738.40    
704-06-A guard rail anchor sections (trailing end)(single thrie
beam)
12.5    LNFT 87.00 1,087.50 104.00 1,300.00 80.00 1,000.00    
704-07-A guard rail bridge attachments (single thrie beam) 37.5    LNFT 37.00 1,387.50 42.00 1,575.00 35.00 1,312.50    
704-08-B guard rail transitions (double thrie beam) 350.0    LNFT 52.00 18,200.00 61.00 21,350.00 55.00 19,250.00    
704-10 guard rail anchor block 12      EACH 1,200.00 14,400.00 1,400.00 16,800.00 2,000.00 24,000.00    
704-11-A guard rail end treatment (flared) 3      EACH 1,800.00 5,400.00 2,100.00 6,300.00 2,000.00 6,000.00    
704-11-B guard rail end treatment (tangent) 12      EACH 2,200.00 26,400.00 2,600.00 31,200.00 2,000.00 24,000.00    
706-03-B incidental concrete paving (5" thick) 232.2    SQYD 56.00 13,003.20 160.00 37,152.00 50.00 11,610.00    
711-01-C riprap (30 lb, 18" thick) 13      SQYD 100.00 1,300.00 80.00 1,040.00 60.00 780.00    
711-04 geotextile fabric 13      SQYD 8.00 104.00 5.00 65.00 3.00 39.00    
713-01 temporary signs & barricades lump      LUMP 12,000.00 12,000.00 15,000.00 15,000.00 125,000.00 125,000.00    
713-03-C temporary pavement markings (8" width) 1,710      LNFT 0.50 855.00 0.24 410.40 0.25 427.50    
713-03-D temporary pavement markings (12" width) 108      LNFT 0.70 75.60 0.37 39.96 0.40 43.20    
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
16.860  MILE 150.00 2,529.00 150.00 2,529.00 500.00 8,430.00    
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
12.600  MILE 10.00 126.00 300.00 3,780.00 100.00 1,260.00    
713-05-A temporary pavement markings (solid line)(4" width) 44.160  MILE 20.00 883.20 100.00 4,416.00 100.00 4,416.00    
713-06-A temporary pavement legends and symbols (arrow) 3      EACH 54.00 162.00 60.00 180.00 25.00 75.00    
713-06-C temporary pavement legends and symbols (only) 3      EACH 54.00 162.00 60.00 180.00 25.00 75.00    
724-01-A pavement patching (6" minimum thickness) 350      SQYD 36.00 12,600.00 70.00 24,500.00 45.00 15,750.00    
724-01-B-01 pavement patching (12" minimum thickness)asphaltic
concrete
650      SQYD 56.00 36,400.00 75.00 48,750.00 95.00 61,750.00    
724-01-B-02 pavement patching (12" minimum thickness) pcc 500      SQYD 65.00 32,500.00 134.00 67,000.00 125.00 62,500.00    
724-02 pavement widening 278.1    SQYD 50.00 13,905.00 145.00 40,324.50 75.00 20,857.50    
726-01 bedding material 23.1    CUYD 70.00 1,617.00 67.00 1,547.70 60.00 1,386.00    
727-01 mobilization lump      LUMP 40,000.00 40,000.00 114,000.00 114,000.00 139,000.00 139,000.00    
729-16-C object marker assembly (type 3) 52      EACH 75.00 3,900.00 86.00 4,472.00 80.00 4,160.00    
731-02 reflectorized raised pavement markers 1,068      EACH 5.30 5,660.40 5.00 5,340.00 6.00 6,408.00    
732-01-C plastic pavement striping (8" width) 1,800      LNFT 2.00 3,600.00 1.00 1,800.00 1.00 1,800.00    
732-01-D plastic pavement striping (12" width) 36      LNFT 6.00 216.00 1.50 54.00 2.00 72.00    
732-01-E plastic pavement striping (24" width) 520      LNFT 8.00 4,160.00 3.00 1,560.00 4.00 2,080.00    
732-02-A plastic pavement striping (solid line) (4" width) 16.720  MILE 2,200.00 36,784.00 2,300.00 38,456.00 2,500.00 41,800.00    
732-03-A plastic pavement striping (broken line)(4" width) 5.200  MILE 900.00 4,680.00 850.00 4,420.00 1,000.00 5,200.00    
732-04-A plastic pavement legends & symbols (arrow) 5      EACH 200.00 1,000.00 200.00 1,000.00 200.00 1,000.00    
732-04-C plastic pavement legends & symbols (only) 5      EACH 200.00 1,000.00 200.00 1,000.00 200.00 1,000.00    
732-05 removal of existing markings 2.000  MILE 5,000.00 10,000.00 6,100.00 12,200.00 6,000.00 12,000.00    
735-01 mailboxes 119      EACH 10.00 1,190.00 20.00 2,380.00 5.00 595.00    
735-02 mailbox supports (single) 119      EACH 150.00 17,850.00 150.00 17,850.00 135.00 16,065.00    
739-01 hydro-seeding 6.81   ACRE 1,000.00 6,810.00 1,200.00 8,172.00 1,000.00 6,810.00    
740-01 construction layout lump      LUMP 12,000.00 12,000.00 10,000.00 10,000.00 51,000.00 51,000.00    
744-01 traffic control management lump      LUMP 30,000.00 30,000.00 10,000.00 10,000.00 70,000.00 70,000.00    
S-001 u-channel post installation 93      EACH 50.00 4,650.00 80.00 7,440.00 50.00 4,650.00    
S-002 cleaning existing ditches 400      LNFT 7.00 2,800.00 10.00 4,000.00 6.00 2,400.00    
S-003 special anchor section 1      EACH 1,000.00 1,000.00 1,100.00 1,100.00 600.00 600.00    
                       
 CONTRACTOR TOTAL       1,887,936.60   1,999,854.86   2,417,629.90    