| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-C |
removal of portland cement concrete pavement
|
500   |
SQYD |
12.00 |
6,000.00 |
12.00 |
6,000.00 |
7.00 |
3,500.00 |
|
|
| 202-02-H |
removal of guard rail
|
1,481   |
LNFT |
4.50 |
6,664.50 |
5.00 |
7,405.00 |
5.00 |
7,405.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
1,000   |
CUYD |
16.00 |
16,000.00 |
26.00 |
26,000.00 |
15.00 |
15,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
20,676.9 |
TON |
58.00 |
1,199,260.20 |
56.00 |
1,157,906.40 |
60.00 |
1,240,614.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
984.0 |
TON |
85.00 |
83,640.00 |
100.00 |
98,400.00 |
115.00 |
113,160.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
81,725   |
SQYD |
2.00 |
163,450.00 |
1.20 |
98,070.00 |
3.00 |
245,175.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,270   |
CUYD |
5.00 |
- 11,350.00 |
0.10 |
- 227.00 |
0.01 |
- 22.70 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
3,802   |
LNFT |
1.70 |
6,463.40 |
1.50 |
5,703.00 |
2.00 |
7,604.00 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
2,148   |
LNFT |
1.70 |
3,651.60 |
1.80 |
3,866.40 |
2.00 |
4,296.00 |
|
|
| 602-03 |
cleaning and sealing random cracks
|
300   |
LNFT |
4.00 |
1,200.00 |
4.00 |
1,200.00 |
3.00 |
900.00 |
|
|
| 701-02-D/E |
cross drain pipe arch (24" equiv. rcpa or 30" equiv.
cmpa) |
140   |
LNFT |
150.00 |
21,000.00 |
100.00 |
14,000.00 |
100.00 |
14,000.00 |
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
81.3 |
LNFT |
47.00 |
3,821.10 |
55.00 |
4,471.50 |
45.00 |
3,658.50 |
|
|
| 704-03 |
blocked out guard rail
|
318.8 |
LNFT |
18.00 |
5,738.40 |
20.00 |
6,376.00 |
18.00 |
5,738.40 |
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
12.5 |
LNFT |
87.00 |
1,087.50 |
104.00 |
1,300.00 |
80.00 |
1,000.00 |
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
37.5 |
LNFT |
37.00 |
1,387.50 |
42.00 |
1,575.00 |
35.00 |
1,312.50 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
350.0 |
LNFT |
52.00 |
18,200.00 |
61.00 |
21,350.00 |
55.00 |
19,250.00 |
|
|
| 704-10 |
guard rail anchor block
|
12   |
EACH |
1,200.00 |
14,400.00 |
1,400.00 |
16,800.00 |
2,000.00 |
24,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
3   |
EACH |
1,800.00 |
5,400.00 |
2,100.00 |
6,300.00 |
2,000.00 |
6,000.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
12   |
EACH |
2,200.00 |
26,400.00 |
2,600.00 |
31,200.00 |
2,000.00 |
24,000.00 |
|
|
| 706-03-B |
incidental concrete paving (5" thick)
|
232.2 |
SQYD |
56.00 |
13,003.20 |
160.00 |
37,152.00 |
50.00 |
11,610.00 |
|
|
| 711-01-C |
riprap (30 lb, 18" thick)
|
13   |
SQYD |
100.00 |
1,300.00 |
80.00 |
1,040.00 |
60.00 |
780.00 |
|
|
| 711-04 |
geotextile fabric
|
13   |
SQYD |
8.00 |
104.00 |
5.00 |
65.00 |
3.00 |
39.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
12,000.00 |
12,000.00 |
15,000.00 |
15,000.00 |
125,000.00 |
125,000.00 |
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
1,710   |
LNFT |
0.50 |
855.00 |
0.24 |
410.40 |
0.25 |
427.50 |
|
|
| 713-03-D |
temporary pavement markings (12" width)
|
108   |
LNFT |
0.70 |
75.60 |
0.37 |
39.96 |
0.40 |
43.20 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
16.860 |
MILE |
150.00 |
2,529.00 |
150.00 |
2,529.00 |
500.00 |
8,430.00 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
12.600 |
MILE |
10.00 |
126.00 |
300.00 |
3,780.00 |
100.00 |
1,260.00 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
44.160 |
MILE |
20.00 |
883.20 |
100.00 |
4,416.00 |
100.00 |
4,416.00 |
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
3   |
EACH |
54.00 |
162.00 |
60.00 |
180.00 |
25.00 |
75.00 |
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
3   |
EACH |
54.00 |
162.00 |
60.00 |
180.00 |
25.00 |
75.00 |
|
|
| 724-01-A |
pavement patching (6" minimum thickness)
|
350   |
SQYD |
36.00 |
12,600.00 |
70.00 |
24,500.00 |
45.00 |
15,750.00 |
|
|
| 724-01-B-01 |
pavement patching (12" minimum thickness)asphaltic
concrete |
650   |
SQYD |
56.00 |
36,400.00 |
75.00 |
48,750.00 |
95.00 |
61,750.00 |
|
|
| 724-01-B-02 |
pavement patching (12" minimum thickness) pcc
|
500   |
SQYD |
65.00 |
32,500.00 |
134.00 |
67,000.00 |
125.00 |
62,500.00 |
|
|
| 724-02 |
pavement widening
|
278.1 |
SQYD |
50.00 |
13,905.00 |
145.00 |
40,324.50 |
75.00 |
20,857.50 |
|
|
| 726-01 |
bedding material
|
23.1 |
CUYD |
70.00 |
1,617.00 |
67.00 |
1,547.70 |
60.00 |
1,386.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
40,000.00 |
40,000.00 |
114,000.00 |
114,000.00 |
139,000.00 |
139,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
52   |
EACH |
75.00 |
3,900.00 |
86.00 |
4,472.00 |
80.00 |
4,160.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,068   |
EACH |
5.30 |
5,660.40 |
5.00 |
5,340.00 |
6.00 |
6,408.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,800   |
LNFT |
2.00 |
3,600.00 |
1.00 |
1,800.00 |
1.00 |
1,800.00 |
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
36   |
LNFT |
6.00 |
216.00 |
1.50 |
54.00 |
2.00 |
72.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
520   |
LNFT |
8.00 |
4,160.00 |
3.00 |
1,560.00 |
4.00 |
2,080.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
16.720 |
MILE |
2,200.00 |
36,784.00 |
2,300.00 |
38,456.00 |
2,500.00 |
41,800.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
5.200 |
MILE |
900.00 |
4,680.00 |
850.00 |
4,420.00 |
1,000.00 |
5,200.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
5   |
EACH |
200.00 |
1,000.00 |
200.00 |
1,000.00 |
200.00 |
1,000.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
5   |
EACH |
200.00 |
1,000.00 |
200.00 |
1,000.00 |
200.00 |
1,000.00 |
|
|
| 732-05 |
removal of existing markings
|
2.000 |
MILE |
5,000.00 |
10,000.00 |
6,100.00 |
12,200.00 |
6,000.00 |
12,000.00 |
|
|
| 735-01 |
mailboxes
|
119   |
EACH |
10.00 |
1,190.00 |
20.00 |
2,380.00 |
5.00 |
595.00 |
|
|
| 735-02 |
mailbox supports (single)
|
119   |
EACH |
150.00 |
17,850.00 |
150.00 |
17,850.00 |
135.00 |
16,065.00 |
|
|
| 739-01 |
hydro-seeding
|
6.81 |
ACRE |
1,000.00 |
6,810.00 |
1,200.00 |
8,172.00 |
1,000.00 |
6,810.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
12,000.00 |
12,000.00 |
10,000.00 |
10,000.00 |
51,000.00 |
51,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
30,000.00 |
30,000.00 |
10,000.00 |
10,000.00 |
70,000.00 |
70,000.00 |
|
|
| S-001 |
u-channel post installation
|
93   |
EACH |
50.00 |
4,650.00 |
80.00 |
7,440.00 |
50.00 |
4,650.00 |
|
|
| S-002 |
cleaning existing ditches
|
400   |
LNFT |
7.00 |
2,800.00 |
10.00 |
4,000.00 |
6.00 |
2,400.00 |
|
|
| S-003 |
special anchor section
|
1   |
EACH |
1,000.00 |
1,000.00 |
1,100.00 |
1,100.00 |
600.00 |
600.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,887,936.60 |
|
1,999,854.86 |
|
2,417,629.90 |
|
|
|