| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - COASTAL BRIDGE CO., L.L.C. |
- 2 - BARRIERE CONSTRUCTION CO., LLC |
- 3 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
BARBER BROS. CONTRACTING CO., L.L.C |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
91   |
LNFT |
10.00 |
910.00 |
10.00 |
910.00 |
10.00 |
910.00 |
15.00 |
1,365.00 |
| 203-08 |
borrow (vehicular measurement)
|
300   |
CUYD |
15.00 |
4,500.00 |
20.00 |
6,000.00 |
20.00 |
6,000.00 |
20.00 |
6,000.00 |
| 204-06 |
temporary silt fencing
|
300   |
LNFT |
4.00 |
1,200.00 |
3.00 |
900.00 |
3.00 |
900.00 |
4.00 |
1,200.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
5,131   |
CUYD |
1.00 |
5,131.00 |
50.00 |
256,550.00 |
25.00 |
128,275.00 |
26.00 |
133,406.00 |
| 502-01 |
superpave asphaltic concrete
|
23,354.6 |
TON |
55.50 |
1,296,180.30 |
58.00 |
1,354,566.80 |
51.50 |
1,202,761.90 |
58.00 |
1,354,566.80 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,036.0 |
TON |
1.00 |
2,036.00 |
58.00 |
118,088.00 |
75.00 |
152,700.00 |
80.00 |
162,880.00 |
| 509-01 |
cold planing asphaltic pavement (2" average depth)
|
121,323   |
SQYD |
3.70 |
448,895.10 |
1.50 |
181,984.50 |
2.40 |
291,175.20 |
2.25 |
272,976.75 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 3,033   |
CUYD |
1.00 |
- 3,033.00 |
10.00 |
- 30,330.00 |
0.01 |
- 30.33 |
0.00 |
0.00 |
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
952   |
LNFT |
75.00 |
71,400.00 |
130.00 |
123,760.00 |
200.00 |
190,400.00 |
130.00 |
123,760.00 |
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
105.0 |
LNFT |
44.00 |
4,620.00 |
46.00 |
4,830.00 |
45.00 |
4,725.00 |
55.00 |
5,775.00 |
| 704-03 |
blocked out guard rail
|
89.0 |
LNFT |
18.00 |
1,602.00 |
20.00 |
1,780.00 |
20.00 |
1,780.00 |
25.00 |
2,225.00 |
| 704-11-B |
guard rail end treatment (tangent)
|
2   |
EACH |
3,000.00 |
6,000.00 |
3,100.00 |
6,200.00 |
3,000.00 |
6,000.00 |
3,500.00 |
7,000.00 |
| 706-01-A |
concrete walk (4" thick)
|
50.0 |
SQYD |
50.00 |
2,500.00 |
60.00 |
3,000.00 |
50.00 |
2,500.00 |
40.00 |
2,000.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
15,000.00 |
15,000.00 |
60,000.00 |
60,000.00 |
150,000.00 |
150,000.00 |
50,000.00 |
50,000.00 |
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
28.200 |
MILE |
300.00 |
8,460.00 |
120.00 |
3,384.00 |
500.00 |
14,100.00 |
450.00 |
12,690.00 |
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
20.589 |
MILE |
300.00 |
6,176.70 |
10.00 |
205.89 |
100.00 |
2,058.90 |
350.00 |
7,206.15 |
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
111.565 |
MILE |
1.00 |
111.56 |
10.00 |
1,115.65 |
10.00 |
1,115.65 |
700.00 |
78,095.50 |
| 724-01-B |
pavement patching (12" minimum thickness)
|
212   |
SQYD |
80.00 |
16,960.00 |
100.00 |
21,200.00 |
90.00 |
19,080.00 |
75.00 |
15,900.00 |
| 726-01 |
bedding material
|
352.6 |
CUYD |
0.01 |
3.52 |
50.00 |
17,630.00 |
FREE |
FREE |
50.00 |
17,630.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
210,000.00 |
210,000.00 |
240,000.00 |
240,000.00 |
201,000.00 |
201,000.00 |
100,000.00 |
100,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
60   |
EACH |
60.00 |
3,600.00 |
55.00 |
3,300.00 |
50.00 |
3,000.00 |
60.00 |
3,600.00 |
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
75.00 |
150.00 |
80.00 |
160.00 |
75.00 |
150.00 |
85.00 |
170.00 |
| 731-02 |
reflectorized raised pavement markers
|
1,242   |
EACH |
5.10 |
6,334.20 |
5.50 |
6,831.00 |
6.00 |
7,452.00 |
6.00 |
7,452.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
24.655 |
MILE |
2,150.00 |
53,008.25 |
2,200.00 |
54,241.00 |
2,500.00 |
61,637.50 |
2,500.00 |
61,637.50 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
6.863 |
MILE |
900.00 |
6,176.70 |
920.00 |
6,313.96 |
1,000.00 |
6,863.00 |
1,200.00 |
8,235.60 |
| 735-01 |
mailboxes
|
87   |
EACH |
1.00 |
87.00 |
5.00 |
435.00 |
5.00 |
435.00 |
6.00 |
522.00 |
| 735-02 |
mailbox supports (single)
|
81   |
EACH |
125.00 |
10,125.00 |
115.00 |
9,315.00 |
125.00 |
10,125.00 |
130.00 |
10,530.00 |
| 735-03 |
mailbox supports (double)
|
3   |
EACH |
225.00 |
675.00 |
170.00 |
510.00 |
200.00 |
600.00 |
200.00 |
600.00 |
| 739-01 |
hydro-seeding
|
11.39 |
ACRE |
900.00 |
10,251.00 |
900.00 |
10,251.00 |
1,000.00 |
11,390.00 |
1,000.00 |
11,390.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
7,500.00 |
7,500.00 |
10,000.00 |
10,000.00 |
99,000.00 |
99,000.00 |
10,000.00 |
10,000.00 |
| 744-01 |
traffic control management
|
lump |
LUMP |
15,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
101,000.00 |
101,000.00 |
50,000.00 |
50,000.00 |
| S-001 |
cleaning existing ditches
|
2,200   |
LNFT |
6.00 |
13,200.00 |
5.00 |
11,000.00 |
5.00 |
11,000.00 |
6.00 |
13,200.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,224,760.33 |
|
2,499,131.80 |
|
2,688,103.82 |
|
IRREGULAR |
|