Bid Tabulations
Letting of
03/31/2010
LA DOTD Headquarters
| Lead Project: 058-01-0027 | |
| Parish: St. Tammany | |
| Routes: LA 433, LA 1090, LA 41 | |
| Description: District 62 Emergency Repair Project | |
| Type Const: | |
| Estimated Construction Cost: $4,165,464.95 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06487 | Huey Stockstill, Inc. | $4,298,532.78 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $4,381,250.41 |
| 3 | 06276 | Barriere Construction Co., LLC. | $4,445,957.10 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $5,316,894.52 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Huey Stockstill, Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Barriere Construction Co., LLC. |
- 4 - Boh Bros. Construction Co., LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,700 | SQYD | 14.00 | 23,800.00 | 13.00 | 22,100.00 | 13.00 | 22,100.00 | 10.00 | 17,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 250 | LNFT | 1.00 | 250.00 | 1.00 | 250.00 | 5.00 | 1,250.00 | 1.00 | 250.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) Sta. 142+50,Sta. 164+80, Sta. 171+25, Sta. 187+35, Sta. 203+40, Sta. 218+35, Sta. 221+60, Sta. 281+50 & Sta. 294+50 | 186 | LNFT | 19.00 | 3,534.00 | 16.00 | 2,976.00 | 100.00 | 18,600.00 | 40.00 | 7,440.00 |
| 0004 | 202-02-38300 | Removal of Sign and U-Channel Post | 48 | EACH | 44.00 | 2,112.00 | 16.00 | 768.00 | 16.00 | 768.00 | 15.00 | 720.00 |
| 0005 | 203-04-00300 | Nonplastic Embankment (Stone) Sta. 246+50 | 10.5 | CUYD | 60.00 | 630.00 | 137.00 | 1,438.50 | 280.00 | 2,940.00 | 200.00 | 2,100.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,961 | CUYD | 8.00 | 23,688.00 | 20.00 | 59,220.00 | 12.00 | 35,532.00 | 15.00 | 44,415.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 96 | EACH | 8.00 | 768.00 | 20.00 | 1,920.00 | 13.00 | 1,248.00 | 12.00 | 1,152.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 45,626 | LNFT | 0.40 | 18,250.40 | 2.45 | 111,783.70 | 1.40 | 63,876.40 | 1.10 | 50,188.60 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,569.8 | CUYD | 10.00 | 35,698.00 | 52.00 | 185,629.60 | 20.00 | 71,396.00 | 30.00 | 107,094.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 35,987.4 | TON | 58.45 | 2,103,463.53 | 69.00 | 2,483,130.60 | 69.00 | 2,483,130.60 | 88.00 | 3,166,891.20 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 3,291 | TON | 80.00 | 263,280.00 | 120.00 | 394,920.00 | 100.00 | 329,100.00 | 100.00 | 329,100.00 |
| 0012 | 509-01-00100 | Cold Planing Asphaltic Pavement | 118,158 | SQYD | 1.10 | 129,973.80 | 1.40 | 165,421.20 | 1.50 | 177,237.00 | 3.00 | 354,474.00 |
| 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,923 | CUYD | 0.00 | 0.00 | 10.00 | -49,230.00 | 5.00 | -24,615.00 | 12.00 | -59,076.00 |
| 0014 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,150 | SQYD | 80.00 | 172,000.00 | 93.50 | 201,025.00 | 72.00 | 154,800.00 | 100.00 | 215,000.00 |
| 0015 | 510-02-00100 | Pavement Widening | 3,729 | SQYD | 66.00 | 246,114.00 | 51.00 | 190,179.00 | 40.00 | 149,160.00 | 65.00 | 242,385.00 |
| 0016 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 5,155 | LNFT | 1.00 | 5,155.00 | 2.75 | 14,176.25 | 1.80 | 9,279.00 | 2.50 | 12,887.50 |
| 0017 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 6,220 | LNFT | 1.50 | 9,330.00 | 2.75 | 17,105.00 | 1.95 | 12,129.00 | 2.50 | 15,550.00 |
| 0018 | 602-03-00100 | Cleaning and Sealing Random cracks | 200 | LNFT | 1.50 | 300.00 | 3.50 | 700.00 | 4.40 | 880.00 | 3.00 | 600.00 |
| 0019 | 602-05-01160 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9" Thick) | 190 | SQYD | 150.00 | 28,500.00 | 150.00 | 28,500.00 | 155.00 | 29,450.00 | 150.00 | 28,500.00 |
| 0020 | 602-05-02160 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9" Thick) | 60 | SQYD | 150.00 | 9,000.00 | 150.00 | 9,000.00 | 155.00 | 9,300.00 | 150.00 | 9,000.00 |
| 0021 | 602-05-03160 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) | 206 | SQYD | 150.00 | 30,900.00 | 150.00 | 30,900.00 | 150.00 | 30,900.00 | 150.00 | 30,900.00 |
| 0022 | 701-02-02000 | Cross Drain Pipe Arch (24" Equiv. RCPA or 30" Equiv. CMPA) | 236 | LNFT | 130.00 | 30,680.00 | 125.00 | 29,500.00 | 180.00 | 42,480.00 | 180.00 | 42,480.00 |
| 0023 | 701-02-02080 | Cross Drain Pipe Arch (36" Equiv. RCPA or 42" Equiv. CMPA) | 40 | LNFT | 150.00 | 6,000.00 | 160.00 | 6,400.00 | 250.00 | 10,000.00 | 240.00 | 9,600.00 |
| 0024 | 701-02-02120 | Cross Drain Pipe Arch (42" Equiv. RCPA or 48" Equiv. CMPA) | 120 | LNFT | 180.00 | 21,600.00 | 195.00 | 23,400.00 | 250.00 | 30,000.00 | 290.00 | 34,800.00 |
| 0025 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 29 | LNFT | 130.00 | 3,770.00 | 149.00 | 4,321.00 | 155.00 | 4,495.00 | 190.00 | 5,510.00 |
| 0026 | 701-12-01100 | Corrugated Metal Pipe (Extension) (36") | 4 | LNFT | 200.00 | 800.00 | 240.00 | 960.00 | 250.00 | 1,000.00 | 250.00 | 1,000.00 |
| 0027 | 701-15-00100 | Concrete Collar | 7 | EACH | 900.00 | 6,300.00 | 1,400.00 | 9,800.00 | 1,485.00 | 10,395.00 | 3,400.00 | 23,800.00 |
| 0028 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 100 | LNFT | 20.00 | 2,000.00 | 21.00 | 2,100.00 | 16.00 | 1,600.00 | 20.00 | 2,000.00 |
| 0029 | 704-03-00100 | Blocked Out Guard Rail | 100 | LNFT | 26.00 | 2,600.00 | 27.00 | 2,700.00 | 21.00 | 2,100.00 | 26.00 | 2,600.00 |
| 0030 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 20.00 | 1,000.00 | 21.00 | 1,050.00 | 27.00 | 1,350.00 | 20.00 | 1,000.00 |
| 0031 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,000.00 | 8,000.00 | 2,100.00 | 8,400.00 | 2,600.00 | 10,400.00 | 2,000.00 | 8,000.00 |
| 0032 | 711-02-00300 | Riprap (30 lb) | 50 | CUYD | 75.00 | 3,750.00 | 130.00 | 6,500.00 | 110.00 | 5,500.00 | 160.00 | 8,000.00 |
| 0033 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 273,300.00 | 273,300.00 | 22,000.00 | 22,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0034 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 500 | LNFT | 0.10 | 50.00 | 0.30 | 150.00 | 0.50 | 250.00 | 0.10 | 50.00 |
| 0035 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 796 | LNFT | 0.20 | 159.20 | 1.00 | 796.00 | 1.00 | 796.00 | 0.20 | 159.20 |
| 0036 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.941 | MILE | 200.00 | 3,588.20 | 165.00 | 2,960.27 | 500.00 | 8,970.50 | 10.00 | 179.41 |
| 0037 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.218 | MILE | 100.00 | 921.80 | 260.00 | 2,396.68 | 500.00 | 4,609.00 | 15.00 | 138.27 |
| 0038 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 66.032 | MILE | 200.00 | 13,206.40 | 530.00 | 34,996.96 | 500.00 | 33,016.00 | 20.00 | 1,320.64 |
| 0039 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 4 | EACH | 20.00 | 80.00 | 50.00 | 200.00 | 1.00 | 4.00 | 25.00 | 100.00 |
| 0040 | 713-05-00200 | Temporary Pavement Legends & Symbols (Double Arrow) | 4 | EACH | 20.00 | 80.00 | 50.00 | 200.00 | 1.00 | 4.00 | 30.00 | 120.00 |
| 0041 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 8 | EACH | 20.00 | 160.00 | 50.00 | 400.00 | 1.00 | 8.00 | 25.00 | 200.00 |
| 0042 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 40.00 | 160.00 | 200.00 | 800.00 | 1.00 | 4.00 | 50.00 | 200.00 |
| 0043 | 716-01-00100 | Mulch (Vegetative) | 9.6 | TON | 175.00 | 1,680.00 | 425.00 | 4,080.00 | 475.00 | 4,560.00 | 450.00 | 4,320.00 |
| 0044 | 717-01-00100 | Seeding | 143 | LB | 35.00 | 5,005.00 | 8.00 | 1,144.00 | 8.50 | 1,215.50 | 10.00 | 1,430.00 |
| 0045 | 718-01-00100 | Fertilizer | 4,781 | LB | 0.35 | 1,673.35 | 0.50 | 2,390.50 | 0.30 | 1,434.30 | 1.25 | 5,976.25 |
| 0046 | 726-01-00100 | Bedding Material | 176.3 | CUYD | 62.00 | 10,930.60 | 74.00 | 13,046.20 | 70.00 | 12,341.00 | 100.00 | 17,630.00 |
| 0047 | 727-01-00100 | Mobilization | 1 | LUMP | 430,000.00 | 430,000.00 | 118,000.00 | 118,000.00 | 440,000.00 | 440,000.00 | 330,000.00 | 330,000.00 |
| 0048 | 729-16-00300 | Object Marker Assembly (Type 3) | 48 | EACH | 69.00 | 3,312.00 | 69.00 | 3,312.00 | 70.00 | 3,360.00 | 70.00 | 3,360.00 |
| 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,527 | EACH | 6.00 | 9,162.00 | 5.00 | 7,635.00 | 5.50 | 8,398.50 | 5.50 | 8,398.50 |
| 0050 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 277 | LNFT | 1.50 | 415.50 | 1.00 | 277.00 | 1.50 | 415.50 | 1.40 | 387.80 |
| 0051 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 398 | LNFT | 5.00 | 1,990.00 | 3.20 | 1,273.60 | 4.75 | 1,890.50 | 4.50 | 1,791.00 |
| 0052 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 35.147 | MILE | 2,700.00 | 94,896.90 | 2,600.00 | 91,382.20 | 2,600.00 | 91,382.20 | 2,500.00 | 87,867.50 |
| 0053 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.609 | MILE | 900.00 | 4,148.10 | 850.00 | 3,917.65 | 900.00 | 4,148.10 | 850.00 | 3,917.65 |
| 0054 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 260.00 | 520.00 | 210.00 | 420.00 | 265.00 | 530.00 | 250.00 | 500.00 |
| 0055 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 230.00 | 460.00 | 210.00 | 420.00 | 235.00 | 470.00 | 220.00 | 440.00 |
| 0056 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 240.00 | 960.00 | 260.00 | 1,040.00 | 240.00 | 960.00 | 225.00 | 900.00 |
| 0057 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 430.00 | 860.00 | 420.00 | 840.00 | 440.00 | 880.00 | 400.00 | 800.00 |
| 0058 | 735-01-00100 | Mailboxes | 117 | EACH | 6.00 | 702.00 | 1.00 | 117.00 | 2.00 | 234.00 | 1.00 | 117.00 |
| 0059 | 735-02-00100 | Mailbox Supports (Single) | 109 | EACH | 125.00 | 13,625.00 | 100.00 | 10,900.00 | 105.00 | 11,445.00 | 100.00 | 10,900.00 |
| 0060 | 735-04-00100 | Mailbox Supports (Multiple) | 6 | EACH | 400.00 | 2,400.00 | 300.00 | 1,800.00 | 300.00 | 1,800.00 | 300.00 | 1,800.00 |
| 0061 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 26,000.00 | 26,000.00 | 18,000.00 | 18,000.00 | 15,000.00 | 15,000.00 |
| 0062 | NS-200-00020 | Cleaning Existing Ditches | 500 | LNFT | 4.00 | 2,000.00 | 6.25 | 3,125.00 | 5.00 | 2,500.00 | 10.00 | 5,000.00 |
| 0063 | NS-500-00280 | Surface Preparation | 1 | LUMP | 100,000.00 | 100,000.00 | 22,000.00 | 22,000.00 | 7,500.00 | 7,500.00 | 15,000.00 | 15,000.00 |
| 0064 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 510 | INLF | 4.00 | 2,040.00 | 1.15 | 586.50 | 5.00 | 2,550.00 | 3.00 | 1,530.00 |
| 0065 | 202-02-36000 | Removal of Railroad Grade Crossing | 1 | EACH | 11,800.00 | 11,800.00 | 8,300.00 | 8,300.00 | 4,500.00 | 4,500.00 | 5,000.00 | 5,000.00 |
| 0066 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 5,000.00 | 15,000.00 | 9,100.00 | 27,300.00 | 10,000.00 | 30,000.00 | 9,000.00 | 27,000.00 |
| CONTRACTOR TOTAL | 4,298,532.78 | 4,381,250.41 | 4,445,957.10 | 5,316,894.52 | ||||||||