Bid Tabulations
Letting of
12/16/2009
LA DOTD Headquarters
| Lead Project: 057-06-0025 | |
| Parish: Lafayette, Evangeline | |
| Routes: LA 13, LA 3168 | |
| Description: DISTRICT WIDE ASPHALTIC SURFACE TREATMENT (CM) | |
| Type Const: ASPHALTIC SURFACE TREATMENT AND RELATED WORK. | |
| Estimated Construction Cost: $499,097.85 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 35378 | P.R. Parker Company Inc | $455,740.73 |
| 2 | 14422 | T. L. Wallace Construction, Inc. | $485,368.75 |
| 3 | 30339 | Missouri Petroleum Products Co. LLC | $528,991.80 |
| 4 | 01552 | W. R. Core, LLC. | $562,862.35 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - P.R. Parker Company Inc |
- 2 - T. L. Wallace Construction, Inc. |
- 3 - Missouri Petroleum Products Co. LLC |
- 4 - W. R. Core, LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 75,579 | GAL | 2.98 | 225,225.42 | 3.30 | 249,410.70 | 2.95 | 222,958.05 | 3.20 | 241,852.80 |
| 0002 | 507-02-00200 | Aggregate (S2) | 111,145 | SQYD | 0.75 | 83,358.75 | 0.95 | 105,587.75 | 1.01 | 112,256.45 | 1.25 | 138,931.25 |
| 0003 | 507-02-00300 | Aggregate (S3) | 111,145 | SQYD | 0.62 | 68,909.90 | 0.65 | 72,244.25 | 1.01 | 112,256.45 | 1.05 | 116,702.25 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,400.00 | 7,400.00 | 7,500.00 | 7,500.00 | 4,137.00 | 4,137.00 | 4,500.00 | 4,500.00 |
| 0005 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,980 | EACH | 2.00 | 3,960.00 | 1.50 | 2,970.00 | 1.00 | 1,980.00 | 1.50 | 2,970.00 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 45,000.00 | 45,000.00 | 10,250.00 | 10,250.00 | 52,000.00 | 52,000.00 | 20,000.00 | 20,000.00 |
| 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,005 | EACH | 5.10 | 5,125.50 | 4.50 | 4,522.50 | 5.25 | 5,276.25 | 4.50 | 4,522.50 |
| 0008 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 400.00 | 400.00 | 2,500.00 | 2,500.00 | 400.00 | 400.00 | 2,500.00 | 2,500.00 |
| 0009 | 737-01-00100 | Painted Traffic Striping (Solid Line) (4" Width) | 16.277 | MILE | 792.00 | 12,891.38 | 1,400.00 | 22,787.80 | 850.00 | 13,835.45 | 1,400.00 | 22,787.80 |
| 0010 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 7.347 | MILE | 325.00 | 2,387.78 | 750.00 | 5,510.25 | 450.00 | 3,306.15 | 750.00 | 5,510.25 |
| 0011 | 737-03-00300 | Painted Traffic Striping (Solid Line) (8" Width) | 90 | LNFT | 0.30 | 27.00 | 0.45 | 40.50 | 0.40 | 36.00 | 0.45 | 40.50 |
| 0012 | 737-03-00500 | Painted Traffic Striping (Solid Line) (24" Width) | 50 | LNFT | 1.10 | 55.00 | 0.90 | 45.00 | 1.00 | 50.00 | 0.90 | 45.00 |
| 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 500.00 | 500.00 | 2,500.00 | 2,500.00 |
| CONTRACTOR TOTAL | 455,740.73 | 485,368.75 | 528,991.80 | 562,862.35 | ||||||||