Bid Tabulations
Letting of
06/02/2010
LA DOTD Headquarters
| Lead Project: 055-06-0081 | |
| Parish: Vermilion | |
| Routes: LA 14, LA 82 | |
| Description: DISTRICT 03 EMERGENCY REPAIR PROJECT - FUNCTIONAL OVERLAYS | |
| Type Const: PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $2,636,324.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 33663 | Glenn Lege Construction Inc | $2,416,319.37 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,800,609.82 |
| 3 | 51821 | Elliott Construction, LLC | $3,352,544.31 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Glenn Lege Construction Inc |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Elliott Construction, LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4,732 | CUYD | 21.80 | 103,157.60 | 77.00 | 364,364.00 | 75.00 | 354,900.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 19,522.9 | TON | 79.50 | 1,552,070.55 | 81.00 | 1,581,354.90 | 99.95 | 1,951,313.86 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,626 | TON | 100.00 | 162,600.00 | 148.00 | 240,648.00 | 128.00 | 208,128.00 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 500 | SQYD | 85.00 | 42,500.00 | 72.00 | 36,000.00 | 138.00 | 69,000.00 |
| 0005 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 300 | SQYD | 127.50 | 38,250.00 | 114.00 | 34,200.00 | 143.00 | 42,900.00 |
| 0006 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 44,971 | LNFT | 1.40 | 62,959.40 | 1.40 | 62,959.40 | 1.35 | 60,710.85 |
| 0007 | 602-03-00100 | Cleaning and Sealing Random cracks | 500 | LNFT | 3.30 | 1,650.00 | 3.10 | 1,550.00 | 3.24 | 1,620.00 |
| 0008 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 57 | EACH | 400.00 | 22,800.00 | 365.00 | 20,805.00 | 150.00 | 8,550.00 |
| 0009 | 702-04-00200 | Adjusting Catch Basins | 7 | EACH | 1,000.00 | 7,000.00 | 4,300.00 | 30,100.00 | 2,200.00 | 15,400.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 65,000.00 | 65,000.00 | 17,000.00 | 17,000.00 | 125,000.00 | 125,000.00 |
| 0011 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,517 | LNFT | 0.25 | 379.25 | 0.25 | 379.25 | 0.24 | 364.08 |
| 0012 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 345 | LNFT | 0.85 | 293.25 | 0.80 | 276.00 | 0.81 | 279.45 |
| 0013 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.271 | MILE | 650.00 | 6,676.15 | 145.00 | 1,489.30 | 377.96 | 3,882.03 |
| 0014 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.215 | MILE | 520.00 | 4,791.80 | 305.00 | 2,810.58 | 513.00 | 4,727.30 |
| 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 34.609 | MILE | 600.00 | 20,765.40 | 610.00 | 21,111.49 | 594.00 | 20,557.75 |
| 0016 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 44 | EACH | 50.00 | 2,200.00 | 55.00 | 2,420.00 | 48.60 | 2,138.40 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 83,200.00 | 83,200.00 | 100,000.00 | 100,000.00 |
| 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,091 | EACH | 5.75 | 17,773.25 | 5.00 | 15,455.00 | 5.67 | 17,525.97 |
| 0019 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 585 | LNFT | 0.55 | 321.75 | 0.50 | 292.50 | 0.54 | 315.90 |
| 0020 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,517 | LNFT | 1.50 | 2,275.50 | 1.10 | 1,668.70 | 1.46 | 2,214.82 |
| 0021 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,119 | LNFT | 5.00 | 5,595.00 | 3.10 | 3,468.90 | 4.86 | 5,438.34 |
| 0022 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 222 | LNFT | 5.50 | 1,221.00 | 5.10 | 1,132.20 | 5.40 | 1,198.80 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 34.609 | MILE | 2,730.00 | 94,482.57 | 2,500.00 | 86,522.50 | 2,700.00 | 93,444.30 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.215 | MILE | 930.00 | 8,569.95 | 710.00 | 6,542.65 | 918.00 | 8,459.37 |
| 0025 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 49 | EACH | 235.00 | 11,515.00 | 210.00 | 10,290.00 | 232.20 | 11,377.80 |
| 0026 | 732-04-08040 | Plastic Pavement Legends and Symbols (Handicap Parking) | 2 | EACH | 275.00 | 550.00 | 210.00 | 420.00 | 270.00 | 540.00 |
| 0027 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 12 | EACH | 250.00 | 3,000.00 | 210.00 | 2,520.00 | 243.00 | 2,916.00 |
| 0028 | 732-04-16000 | Plastic Pavement Legends and Symbols (Pedestrian Crossing) | 3 | EACH | 330.00 | 990.00 | 510.00 | 1,530.00 | 324.00 | 972.00 |
| 0029 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 440.00 | 880.00 | 410.00 | 820.00 | 432.00 | 864.00 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,000.00 | 7,000.00 | 6,500.00 | 6,500.00 | 11,500.00 | 11,500.00 |
| 0031 | 741-11-00100 | Adjusting Water Valve | 30 | EACH | 150.00 | 4,500.00 | 235.00 | 7,050.00 | 50.00 | 1,500.00 |
| 0032 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 23,732 | LNFT | 1.10 | 26,105.20 | 1.10 | 26,105.20 | 1.08 | 25,630.56 |
| 0033 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 21,239 | LNFT | 1.20 | 25,486.80 | 1.20 | 25,486.80 | 1.19 | 25,274.41 |
| 0034 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 44,971 | LNFT | 0.95 | 42,722.45 | 0.95 | 42,722.45 | 0.92 | 41,373.32 |
| 0035 | NS-500-00280 | Surface Preparation | 1 | LUMP | 13,000.00 | 13,000.00 | 51,200.00 | 51,200.00 | 125,000.00 | 125,000.00 |
| 0036 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 3,240 | INLF | 1.25 | 4,050.00 | 1.50 | 4,860.00 | 1.30 | 4,212.00 |
| 0037 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,550 | INLF | 1.25 | 3,187.50 | 2.10 | 5,355.00 | 1.30 | 3,315.00 |
| CONTRACTOR TOTAL | 2,416,319.37 | 2,800,609.82 | 3,352,544.31 | |||||||