Bid Tabulations
Letting of
07/28/2010
LA DOTD Headquarters
| Lead Project: 053-03-0037 | |
| Parish: Natchitoches | |
| Routes: LA 1 | |
| Description: OLD RIVER BRIDGE AT MONTROSE | |
| Type Const: GRADING, CLASS II BASE COURSE, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONTINUOUS SPAN QUADBEAM BRIDGE AND RELATED WORK. | |
| Estimated Construction Cost: $2,863,255.80 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $2,456,528.57 |
| 2 | 39462 | JB James Construction LLC | $3,158,753.60 |
| 3 | 01012 | Cecil D. Gassiott, LLC | $3,428,362.41 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - JB James Construction LLC |
- 3 - Cecil D. Gassiott, LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 25,000.00 | 25,000.00 | 300,000.00 | 300,000.00 | 58,000.00 | 58,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 30,000.00 | 30,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-02000 | Removal of Asphalt Drives | 106 | SQYD | 7.00 | 742.00 | 6.00 | 636.00 | 50.00 | 5,300.00 |
| 0004 | 202-02-02020 | Removal of Asphalt Pavement | 4,929 | SQYD | 5.20 | 25,630.80 | 4.00 | 19,716.00 | 6.00 | 29,574.00 |
| 0005 | 202-02-04000 | Removal of Bridge STA. 23+03.08; 370'X23' CONCRETE DECK BRIDGE | 1 | EACH | 120,000.00 | 120,000.00 | 110,000.00 | 110,000.00 | 150,000.00 | 150,000.00 |
| 0006 | 202-02-14500 | Removal of Guard Rail | 640 | LNFT | 8.00 | 5,120.00 | 5.00 | 3,200.00 | 25.00 | 16,000.00 |
| 0007 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 3,493.4 | SQYD | 5.00 | 17,467.00 | 7.50 | 26,200.50 | 20.00 | 69,868.00 |
| 0008 | 203-01-00100 | General Excavation | 1,035 | CUYD | 9.50 | 9,832.50 | 15.00 | 15,525.00 | 10.00 | 10,350.00 |
| 0009 | 203-02-00100 | Drainage Excavation | 3,337 | CUYD | 7.00 | 23,359.00 | 12.00 | 40,044.00 | 25.00 | 83,425.00 |
| 0010 | 203-03-00100 | Embankment | 6,280 | CUYD | 16.00 | 100,480.00 | 21.00 | 131,880.00 | 14.00 | 87,920.00 |
| 0011 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 250.00 | 2,000.00 | 150.00 | 1,200.00 | 200.00 | 1,600.00 |
| 0012 | 204-06-00100 | Temporary Silt Fencing | 3,225 | LNFT | 2.00 | 6,450.00 | 1.60 | 5,160.00 | 2.50 | 8,062.50 |
| 0013 | 302-02-04120 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete) | 6,710 | SQYD | 21.50 | 144,265.00 | 24.00 | 161,040.00 | 23.00 | 154,330.00 |
| 0014 | 304-05-00100 | Lime Treatment (Type E) | 81.18 | TON | 300.00 | 24,354.00 | 300.00 | 24,354.00 | 200.00 | 16,236.00 |
| 0015 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 26 | CUYD | 60.00 | 1,560.00 | 100.00 | 2,600.00 | 75.00 | 1,950.00 |
| 0016 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 400 | CUYD | 20.00 | 8,000.00 | 65.00 | 26,000.00 | 25.00 | 10,000.00 |
| 0017 | 502-01-00100 | Superpave Asphaltic Concrete | 1,762 | TON | 88.00 | 155,056.00 | 130.00 | 229,060.00 | 130.00 | 229,060.00 |
| 0018 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 490.2 | TON | 115.00 | 56,373.00 | 170.00 | 83,334.00 | 180.00 | 88,236.00 |
| 0019 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 112 | LNFT | 145.00 | 16,240.00 | 100.00 | 11,200.00 | 200.00 | 22,400.00 |
| 0020 | 704-03-00100 | Blocked Out Guard Rail | 312.5 | LNFT | 25.00 | 7,812.50 | 18.00 | 5,625.00 | 18.50 | 5,781.25 |
| 0021 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 80.00 | 8,000.00 | 55.00 | 5,500.00 | 60.00 | 6,000.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,000.00 | 8,000.00 | 2,100.00 | 8,400.00 |
| 0023 | 705-01-00100 | Barbed Wire Fence | 100 | LNFT | 12.00 | 1,200.00 | 15.00 | 1,500.00 | 20.00 | 2,000.00 |
| 0024 | 712-04-00100 | Flexible Revetment | 572 | SQYD | 60.00 | 34,320.00 | 55.00 | 31,460.00 | 80.00 | 45,760.00 |
| 0025 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 |
| 0026 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 16 | LNFT | 1.00 | 16.00 | 0.60 | 9.60 | 0.65 | 10.40 |
| 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.537 | MILE | 440.00 | 236.28 | 300.00 | 161.10 | 325.00 | 174.53 |
| 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.537 | MILE | 590.00 | 316.83 | 400.00 | 214.80 | 325.00 | 174.53 |
| 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.101 | MILE | 685.00 | 754.19 | 500.00 | 550.50 | 400.00 | 440.40 |
| 0030 | 716-01-00100 | Mulch (Vegetative) | 6.8 | TON | 560.00 | 3,808.00 | 700.00 | 4,760.00 | 700.00 | 4,760.00 |
| 0031 | 717-01-00100 | Seeding | 360 | LB | 8.75 | 3,150.00 | 7.00 | 2,520.00 | 10.00 | 3,600.00 |
| 0032 | 718-01-00100 | Fertilizer | 4,500 | LB | 0.55 | 2,475.00 | 0.60 | 2,700.00 | 0.65 | 2,925.00 |
| 0033 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 9,400.00 | 9,400.00 | 5,000.00 | 5,000.00 | 30,000.00 | 30,000.00 |
| 0034 | 726-01-00100 | Bedding Material | 46.9 | CUYD | 110.00 | 5,159.00 | 70.00 | 3,283.00 | 125.00 | 5,862.50 |
| 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 240,000.00 | 240,000.00 | 310,000.00 | 310,000.00 | 300,000.00 | 300,000.00 |
| 0036 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 55.00 | 110.00 | 65.00 | 130.00 | 75.00 | 150.00 |
| 0037 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | 75.00 | 300.00 | 85.00 | 340.00 |
| 0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | 32 | EACH | 6.50 | 208.00 | 10.00 | 320.00 | 9.00 | 288.00 |
| 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 16 | LNFT | 5.50 | 88.00 | 6.00 | 96.00 | 6.50 | 104.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.55 | MILE | 3,100.00 | 1,705.00 | 8,000.00 | 4,400.00 | 8,500.00 | 4,675.00 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.242 | MILE | 1,000.00 | 242.00 | 2,000.00 | 484.00 | 2,000.00 | 484.00 |
| 0042 | 735-01-00100 | Mailboxes | 3 | EACH | 6.89 | 20.67 | 1.00 | 3.00 | 10.00 | 30.00 |
| 0043 | 735-02-00100 | Mailbox Supports (Single) | 3 | EACH | 235.00 | 705.00 | 200.00 | 600.00 | 125.00 | 375.00 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0045 | 804-01-00700 | Precast Concrete Piles (30") | 2,532 | LNFT | 115.00 | 291,180.00 | 130.00 | 329,160.00 | 200.00 | 506,400.00 |
| 0046 | 804-05-00700 | Precast Concrete Test Piles (30") | 1 | EACH | 40,000.00 | 40,000.00 | 35,000.00 | 35,000.00 | 50,000.00 | 50,000.00 |
| 0047 | 804-09-00100 | Loading Test Piles | 1 | EACH | 40,000.00 | 40,000.00 | 35,000.00 | 35,000.00 | 28,000.00 | 28,000.00 |
| 0048 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 1,000.00 | 1,000.00 | 100.00 | 100.00 | 5,000.00 | 5,000.00 |
| 0049 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1,000.00 | 1,000.00 | 100.00 | 100.00 | 2,500.00 | 2,500.00 |
| 0050 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 100.00 | 100.00 | 100.00 | 100.00 | 20,000.00 | 20,000.00 |
| 0051 | 804-17-00100 | Dynamic Monitoring | 21 | EACH | 250.00 | 5,250.00 | 2,000.00 | 42,000.00 | 3,500.00 | 73,500.00 |
| 0052 | 805-01-00700 | Class A Concrete (Bents) | 166.86 | CUYD | 950.00 | 158,517.00 | 1,000.00 | 166,860.00 | 1,375.00 | 229,432.50 |
| 0053 | 805-04-00100 | Class AA(M) Concrete | 413.84 | CUYD | 750.00 | 310,380.00 | 720.00 | 297,964.80 | 1,000.00 | 413,840.00 |
| 0054 | 805-08-00800 | Precast-Prestressed Concrete Girder (Type Quad Beam) | 3,160 | LNFT | 62.00 | 195,920.00 | 68.00 | 214,880.00 | 69.50 | 219,620.00 |
| 0055 | 805-11-00100 | Strip Seal Joints | 200 | LNFT | 170.00 | 34,000.00 | 190.00 | 38,000.00 | 190.00 | 38,000.00 |
| 0056 | 806-01-00100 | Deformed Reinforcing Steel | 187,687 | LB | 0.60 | 112,612.20 | 0.90 | 168,918.30 | 0.80 | 150,149.60 |
| 0057 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 8,000.00 | 8,000.00 | 8,000.00 | 8,000.00 | 4,000.00 | 4,000.00 |
| 0058 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 800 | LNFT | 55.00 | 44,000.00 | 65.00 | 52,000.00 | 65.00 | 52,000.00 |
| 0059 | 813-01-00100 | Concrete Approach Slabs | 363.88 | SQYD | 220.00 | 80,053.60 | 200.00 | 72,776.00 | 215.00 | 78,234.20 |
| 0060 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 1,520 | INLF | 2.00 | 3,040.00 | 1.40 | 2,128.00 | 2.00 | 3,040.00 |
| 0061 | NS-800-00540 | Pile Dynamic Monitoring Instrumentation Accessories | 1 | LUMP | 8,500.00 | 8,500.00 | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 2,456,528.57 | 3,158,753.60 | 3,428,362.41 | |||||||