| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - HARD ROCK CONSTRUCTION CO. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
1,830   |
LNFT |
7.00 |
12,810.00 |
5.00 |
9,150.00 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
250   |
CUYD |
60.00 |
15,000.00 |
55.00 |
13,750.00 |
|
|
|
|
| 302-02-C |
class ii base course (10" thick)
|
342.7 |
SQYD |
40.00 |
13,708.00 |
35.00 |
11,994.50 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
3,821   |
CUYD |
78.00 |
298,038.00 |
78.00 |
298,038.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts, and
miscellaneous |
619.2 |
TON |
175.00 |
108,360.00 |
130.00 |
80,496.00 |
|
|
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
108,847   |
LNFT |
1.30 |
141,501.10 |
1.00 |
108,847.00 |
|
|
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
168,242   |
LNFT |
0.80 |
134,593.60 |
1.00 |
168,242.00 |
|
|
|
|
| 602-03 |
cleaning and sealing random cracks
|
671   |
LNFT |
3.25 |
2,180.75 |
2.00 |
1,342.00 |
|
|
|
|
| 602-05-I-01 |
full depth patching of jointed conc pvmt (9" thick)
(16.0 sq yds & under) |
1,963.5 |
SQYD |
160.00 |
314,160.00 |
150.00 |
294,525.00 |
|
|
|
|
| 602-05-I-02 |
full depth patching of jointed conc pvmt (9" thick)
(16.1 - 48.0 sq yds) |
1,220.0 |
SQYD |
135.00 |
164,700.00 |
150.00 |
183,000.00 |
|
|
|
|
| 602-05-I-03 |
full depth patching of jointed conc pvmt (9" thick)
(48.1 sq yds & over) |
243.4 |
SQYD |
120.00 |
29,208.00 |
150.00 |
36,510.00 |
|
|
|
|
| 602-10 |
longitudinal shoulder joints
|
18,850   |
LNFT |
1.50 |
28,275.00 |
1.00 |
18,850.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
480.0 |
LNFT |
32.00 |
15,360.00 |
36.00 |
17,280.00 |
|
|
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
487.6 |
LNFT |
46.00 |
22,429.60 |
48.00 |
23,404.80 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
587.8 |
LNFT |
18.00 |
10,580.40 |
20.00 |
11,756.00 |
|
|
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
25.2 |
LNFT |
105.00 |
2,646.00 |
70.00 |
1,764.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
55.00 |
5,500.00 |
50.00 |
5,000.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
8   |
EACH |
2,200.00 |
17,600.00 |
2,000.00 |
16,000.00 |
|
|
|
|
| 704-11-C |
guard rail end treatment (bi-directional)
|
2   |
EACH |
4,900.00 |
9,800.00 |
7,000.00 |
14,000.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
135,000.00 |
135,000.00 |
110,000.00 |
110,000.00 |
|
|
|
|
| 713-05-A-01 |
temporary pavement markings (solid line)(4" width)
(type 1 removable) |
8.000 |
MILE |
14,000.00 |
112,000.00 |
14,000.00 |
112,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
96,000.00 |
96,000.00 |
200,000.00 |
200,000.00 |
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
20   |
EACH |
55.00 |
1,100.00 |
70.00 |
1,400.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
10   |
EACH |
85.00 |
850.00 |
70.00 |
700.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
5,132   |
EACH |
6.00 |
30,792.00 |
5.00 |
25,660.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
702   |
LNFT |
1.00 |
702.00 |
1.00 |
702.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
632   |
LNFT |
3.00 |
1,896.00 |
3.00 |
1,896.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
18.845 |
MILE |
2,500.00 |
47,112.50 |
2,500.00 |
47,112.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
16.180 |
MILE |
730.00 |
11,811.40 |
700.00 |
11,326.00 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
4   |
EACH |
500.00 |
2,000.00 |
500.00 |
2,000.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
16.440 |
MILE |
5,000.00 |
82,200.00 |
5,000.00 |
82,200.00 |
|
|
|
|
| 735-01 |
mailboxes
|
88   |
EACH |
5.00 |
440.00 |
1.00 |
88.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
49   |
EACH |
160.00 |
7,840.00 |
150.00 |
7,350.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
9   |
EACH |
250.00 |
2,250.00 |
200.00 |
1,800.00 |
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
11   |
EACH |
300.00 |
3,300.00 |
400.00 |
4,400.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
30,000.00 |
30,000.00 |
50,000.00 |
50,000.00 |
|
|
|
|
| S-001 |
temporary traffic signal (solar powered)
|
lump |
LUMP |
90,000.00 |
90,000.00 |
72,000.00 |
72,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,011,744.35 |
|
2,069,583.80 |
|
|
|
|
|