| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
2,000.00 |
2,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 202-02-H |
removal of guard rail
|
496   |
LNFT |
5.00 |
2,480.00 |
4.00 |
1,984.00 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
70   |
CUYD |
15.00 |
1,050.00 |
20.00 |
1,400.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,267   |
CUYD |
12.00 |
15,204.00 |
34.00 |
43,078.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
13,730.1 |
TON |
55.00 |
755,155.50 |
53.75 |
737,992.87 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
554.8 |
TON |
90.00 |
49,932.00 |
84.00 |
46,603.20 |
|
|
|
|
| 507-01-A |
asphaltic surface treatment (1 application)
|
53,792   |
SQYD |
1.50 |
80,688.00 |
1.50 |
80,688.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
91,091   |
SQYD |
1.00 |
91,091.00 |
1.50 |
136,636.50 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,293   |
CUYD |
1.00 |
- 2,293.00 |
0.10 |
- 229.30 |
|
|
|
|
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
16   |
LNFT |
185.00 |
2,960.00 |
162.00 |
2,592.00 |
|
|
|
|
| 701-15 |
concrete collar
|
1   |
EACH |
900.00 |
900.00 |
1,300.00 |
1,300.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
900.0 |
LNFT |
27.00 |
24,300.00 |
28.00 |
25,200.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
137.5 |
LNFT |
17.00 |
2,337.50 |
17.00 |
2,337.50 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
50.00 |
5,000.00 |
53.00 |
5,300.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
1,900.00 |
7,600.00 |
2,000.00 |
8,000.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,000.00 |
6,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
14.708 |
MILE |
400.00 |
5,883.20 |
135.00 |
1,985.58 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
4.287 |
MILE |
300.00 |
1,286.10 |
270.00 |
1,157.49 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
50.933 |
MILE |
250.00 |
12,733.25 |
540.00 |
27,503.82 |
|
|
|
|
| 717-01 |
seeding
|
30   |
LB |
7.50 |
225.00 |
8.00 |
240.00 |
|
|
|
|
| 718-01 |
fertilizer
|
1,000   |
LB |
5.50 |
5,500.00 |
0.54 |
540.00 |
|
|
|
|
| 721-01 |
asphalt mulch
|
2,420   |
GAL |
2.50 |
6,050.00 |
2.17 |
5,251.40 |
|
|
|
|
| 724-01-C |
pavement patching (8.5" minimum thickness)
|
200   |
SQYD |
50.00 |
10,000.00 |
90.00 |
18,000.00 |
|
|
|
|
| 724-01-D |
pavement patching (17" minimum thickness)
|
1,400   |
SQYD |
90.00 |
126,000.00 |
100.00 |
140,000.00 |
|
|
|
|
| 724-03 |
pavement joint repair
|
200.0 |
TON |
170.00 |
34,000.00 |
200.00 |
40,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
4.2 |
CUYD |
80.00 |
336.00 |
70.00 |
294.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
100,000.00 |
100,000.00 |
30,000.00 |
30,000.00 |
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
2   |
EACH |
55.00 |
110.00 |
54.00 |
108.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
65.00 |
260.00 |
67.00 |
268.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
866   |
EACH |
5.00 |
4,330.00 |
5.00 |
4,330.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
22.620 |
MILE |
2,000.00 |
45,240.00 |
2,100.00 |
47,502.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.972 |
MILE |
750.00 |
1,479.00 |
750.00 |
1,479.00 |
|
|
|
|
| 735-01 |
mailboxes
|
22   |
EACH |
25.00 |
550.00 |
12.00 |
264.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
18   |
EACH |
150.00 |
2,700.00 |
150.00 |
2,700.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
3   |
EACH |
200.00 |
600.00 |
200.00 |
600.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
6,000.00 |
6,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
36,000.00 |
36,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| S-001 |
sawcuts in asphaltic concrete lifts
|
123,000   |
LNFT |
0.50 |
61,500.00 |
0.60 |
73,800.00 |
|
|
|
|
| S-002 |
sawing and sealing longitudinal joints in asphaltic
concrete overlay |
50,912   |
LNFT |
0.80 |
40,729.60 |
1.00 |
50,912.00 |
|
|
|
|
| S-003 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
25,686   |
LNFT |
0.80 |
20,548.80 |
1.15 |
29,538.90 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,570,465.95 |
|
1,600,356.96 |
|
|
|
|
|