| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARBER BROS. CONTRACTING CO., L.L.C |
- 2 - COASTAL BRIDGE CO., L.L.C. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
122,000.00 |
122,000.00 |
400,000.00 |
400,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
100,000.00 |
100,000.00 |
75,000.00 |
75,000.00 |
|
|
|
|
| 202-02-C |
removal of pcc pavement
|
58   |
SQYD |
100.00 |
5,800.00 |
50.00 |
2,900.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
7,569   |
SQYD |
50.00 |
378,450.00 |
12.00 |
90,828.00 |
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
5,050.9 |
LNFT |
15.00 |
75,763.50 |
10.00 |
50,509.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
28,361.0 |
SQYD |
12.00 |
340,332.00 |
36.50 |
1,035,176.50 |
|
|
|
|
| 202-02-H |
removal of guard rail
|
340   |
LNFT |
10.00 |
3,400.00 |
15.00 |
5,100.00 |
|
|
|
|
| 202-02-I |
removal of signal equipment and related items
|
lump |
LUMP |
15,000.00 |
15,000.00 |
8,000.00 |
8,000.00 |
|
|
|
|
| 202-02-J |
removal of concrete headwalls (various sizes)
|
9   |
EACH |
2,000.00 |
18,000.00 |
1,000.00 |
9,000.00 |
|
|
|
|
| 203-01 |
general excavation
|
25,507   |
CUYD |
12.00 |
306,084.00 |
13.00 |
331,591.00 |
|
|
|
|
| 203-03 |
muck excavation
|
299   |
CUYD |
20.00 |
5,980.00 |
15.00 |
4,485.00 |
|
|
|
|
| 203-04 |
embankment
|
9,810   |
CUYD |
20.00 |
196,200.00 |
17.00 |
166,770.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
16   |
EACH |
350.00 |
5,600.00 |
105.00 |
1,680.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
23,905   |
LNFT |
2.50 |
59,762.50 |
1.55 |
37,052.75 |
|
|
|
|
| 302-02-E |
class ii base course (8" thick)
|
43,448.1 |
SQYD |
25.00 |
1,086,202.50 |
30.00 |
1,303,443.00 |
|
|
|
|
| 302-02-F |
class ii base course (13" thick)
|
16,129.7 |
SQYD |
36.00 |
580,669.20 |
35.00 |
564,539.50 |
|
|
|
|
| 304-01 |
lime
|
15.63 |
TON |
150.00 |
2,344.50 |
1,000.00 |
15,630.00 |
|
|
|
|
| 304-04-D |
lime treatment (type d, slurry) (12" thick)
|
29,760   |
SQYD |
2.50 |
74,400.00 |
1.00 |
29,760.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
800.0 |
CUYD |
150.00 |
120,000.00 |
70.00 |
56,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
35,844.9 |
TON |
60.00 |
2,150,694.00 |
68.00 |
2,437,453.20 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
1,729.8 |
TON |
100.00 |
172,980.00 |
100.00 |
172,980.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
85,333   |
SQYD |
3.00 |
255,999.00 |
3.10 |
264,532.30 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 4,741   |
CUYD |
FREE |
FREE |
10.00 |
- 47,410.00 |
|
|
|
|
| 601-01-G |
portland cement concrete pavement(8" thick)
|
58   |
SQYD |
100.00 |
5,800.00 |
85.00 |
4,930.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24")
|
55   |
LNFT |
65.00 |
3,575.00 |
55.00 |
3,025.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp/pcp)
|
87   |
LNFT |
90.00 |
7,830.00 |
79.00 |
6,873.00 |
|
|
|
|
| 701-03-M |
storm drain pipe (36" rcp/pcp)
|
1,124   |
LNFT |
60.00 |
67,440.00 |
50.00 |
56,200.00 |
|
|
|
|
| 701-03-N |
storm drain pipe (42")
|
20   |
LNFT |
120.00 |
2,400.00 |
100.00 |
2,000.00 |
|
|
|
|
| 701-04-G |
storm drain pipe arch (42" equivalent)
|
870   |
LNFT |
150.00 |
130,500.00 |
135.00 |
117,450.00 |
|
|
|
|
| 701-05-G |
side drain pipe (18")
|
184   |
LNFT |
60.00 |
11,040.00 |
45.00 |
8,280.00 |
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
52   |
LNFT |
200.00 |
10,400.00 |
125.00 |
6,500.00 |
|
|
|
|
| 701-10-K |
reinforced concrete pipe (extension)(30")
|
20   |
LNFT |
250.00 |
5,000.00 |
150.00 |
3,000.00 |
|
|
|
|
| 701-15 |
concrete collar
|
7   |
EACH |
600.00 |
4,200.00 |
500.00 |
3,500.00 |
|
|
|
|
| 702-02-C |
r-cb-11 modified
|
10   |
EACH |
7,500.00 |
75,000.00 |
7,000.00 |
70,000.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
5   |
EACH |
3,500.00 |
17,500.00 |
3,000.00 |
15,000.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
1   |
EACH |
1,500.00 |
1,500.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
1   |
EACH |
2,500.00 |
2,500.00 |
2,000.00 |
2,000.00 |
|
|
|
|
| 702-07-A |
cross drain safety end (type 1)
|
3   |
EACH |
4,500.00 |
13,500.00 |
3,700.00 |
11,100.00 |
|
|
|
|
| 702-08-A |
side drain safety end (type 1)
|
41   |
EACH |
2,400.00 |
98,400.00 |
1,800.00 |
73,800.00 |
|
|
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
116.7 |
LNFT |
60.00 |
7,002.00 |
45.00 |
5,251.50 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
75.8 |
LNFT |
35.00 |
2,653.00 |
18.00 |
1,364.40 |
|
|
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
25.0 |
LNFT |
100.00 |
2,500.00 |
75.00 |
1,875.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,500.00 |
10,000.00 |
2,600.00 |
10,400.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
4,153.3 |
SQYD |
65.00 |
269,964.50 |
60.00 |
249,198.00 |
|
|
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
551.8 |
SQYD |
60.00 |
33,108.00 |
45.00 |
24,831.00 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
10,234.0 |
LNFT |
42.00 |
429,828.00 |
35.00 |
358,190.00 |
|
|
|
|
| 712-02 |
sacked concrete revetment
|
74   |
SQYD |
100.00 |
7,400.00 |
75.00 |
5,550.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
500,000.00 |
500,000.00 |
120,000.00 |
120,000.00 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
9.940 |
MILE |
350.00 |
3,479.00 |
800.00 |
7,952.00 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
15.108 |
MILE |
600.00 |
9,064.80 |
495.00 |
7,478.46 |
|
|
|
|
| 713-05-C |
temporary pavement markings (solid line)(8" width)
|
1.470 |
MILE |
2,500.00 |
3,675.00 |
995.00 |
1,462.65 |
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
41   |
EACH |
60.00 |
2,460.00 |
50.00 |
2,050.00 |
|
|
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
41   |
EACH |
200.00 |
8,200.00 |
50.00 |
2,050.00 |
|
|
|
|
| 717-01 |
seeding
|
253   |
LB |
12.00 |
3,036.00 |
7.50 |
1,897.50 |
|
|
|
|
| 718-01 |
fertilizer
|
10,116   |
LB |
0.50 |
5,058.00 |
0.25 |
2,529.00 |
|
|
|
|
| 719-01-A |
plants ('drake' elm (ulmus parvifolia))(20/25 gallon)
|
17   |
EACH |
300.00 |
5,100.00 |
250.00 |
4,250.00 |
|
|
|
|
| 719-01-B |
plants (elaegnus (elaegnus pungens))(3 gallon)
|
99   |
EACH |
30.00 |
2,970.00 |
25.00 |
2,475.00 |
|
|
|
|
| 719-01-C |
plants (crepe myrtle 'natchez'(lagerstroemia indica))
(30 gallon) |
40   |
EACH |
220.00 |
8,800.00 |
180.00 |
7,200.00 |
|
|
|
|
| 719-01-D |
plants (bald cypress(taxodium distichum))(30 gallon)
|
49   |
EACH |
260.00 |
12,740.00 |
225.00 |
11,025.00 |
|
|
|
|
| 719-02 |
top dressing mulch (6" depth)
|
1,419   |
SQYD |
7.50 |
10,642.50 |
6.00 |
8,514.00 |
|
|
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
37   |
SQYD |
10.00 |
370.00 |
5.00 |
185.00 |
|
|
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
28   |
SQYD |
10.00 |
280.00 |
5.00 |
140.00 |
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
1,000   |
SQYD |
100.00 |
100,000.00 |
90.00 |
90,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
385.5 |
CUYD |
40.00 |
15,420.00 |
30.00 |
11,565.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
1,000,000.00 |
1,000,000.00 |
1,200,000.00 |
1,200,000.00 |
|
|
|
|
| 729-01 |
sign (type a)
|
319.0 |
SQFT |
35.00 |
11,165.00 |
35.00 |
11,165.00 |
|
|
|
|
| 729-06 |
sign (overhead mounted)
|
624.5 |
SQFT |
65.00 |
40,592.50 |
40.00 |
24,980.00 |
|
|
|
|
| 729-11 |
mounting (overhead cantilever)(ground mounted)
|
4   |
EACH |
30,000.00 |
120,000.00 |
25,000.00 |
100,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
60.00 |
480.00 |
50.00 |
400.00 |
|
|
|
|
| 729-20 |
footings for overhead mountings (type)
|
4   |
EACH |
25,000.00 |
100,000.00 |
18,000.00 |
72,000.00 |
|
|
|
|
| 729-21 |
u-channel post
|
10   |
EACH |
65.00 |
650.00 |
60.00 |
600.00 |
|
|
|
|
| 729-21-A |
u-channel post(5')
|
29   |
EACH |
45.00 |
1,305.00 |
40.00 |
1,160.00 |
|
|
|
|
| 730-15 |
relocate light poles (20'-30', single arm)
|
18   |
EACH |
3,200.00 |
57,600.00 |
2,525.00 |
45,450.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
2,633   |
EACH |
7.00 |
18,431.00 |
5.00 |
13,165.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
1,462   |
LNFT |
3.50 |
5,117.00 |
2.75 |
4,020.50 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
11.453 |
MILE |
2,400.00 |
27,487.20 |
2,000.00 |
22,906.00 |
|
|
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
1.469 |
MILE |
12,000.00 |
17,628.00 |
6,000.00 |
8,814.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
9.943 |
MILE |
1,200.00 |
11,931.60 |
700.00 |
6,960.10 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
81   |
EACH |
200.00 |
16,200.00 |
150.00 |
12,150.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
81   |
EACH |
300.00 |
24,300.00 |
175.00 |
14,175.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
1.200 |
MILE |
15,000.00 |
18,000.00 |
6,000.00 |
7,200.00 |
|
|
|
|
| 736-01 |
trenching and backfilling
|
4,324   |
LNFT |
3.50 |
15,134.00 |
3.50 |
15,134.00 |
|
|
|
|
| 736-03-A |
jacked or bored conduit (1" p.e.c. shedule 80)
|
7,475   |
LNFT |
12.00 |
89,700.00 |
8.00 |
59,800.00 |
|
|
|
|
| 736-03-B |
jacked or bored conduit (2" p.e.c. shedule 80)
|
17,903   |
LNFT |
12.50 |
223,787.50 |
8.50 |
152,175.50 |
|
|
|
|
| 736-04 |
signal support (35',galvanized steel strain pole, with
luminaire) |
33   |
EACH |
7,000.00 |
231,000.00 |
6,000.00 |
198,000.00 |
|
|
|
|
| 736-04-B |
signal support (40' galvanized steel strain pole with
luminaire) |
1   |
EACH |
8,000.00 |
8,000.00 |
10,500.00 |
10,500.00 |
|
|
|
|
| 736-05-A |
signal heads (3-section, r,y,g)(led)
|
82   |
EACH |
900.00 |
73,800.00 |
850.00 |
69,700.00 |
|
|
|
|
| 736-05-B |
signal heads (3-section, r,lty,ltg)(led)
|
20   |
EACH |
800.00 |
16,000.00 |
800.00 |
16,000.00 |
|
|
|
|
| 736-05-C |
signal heads (3-section, r,rty,rtg)(led)
|
3   |
EACH |
800.00 |
2,400.00 |
800.00 |
2,400.00 |
|
|
|
|
| 736-05-D |
signal heads (5-section, r,lty,y,ltg,g,)(led)
|
2   |
EACH |
1,500.00 |
3,000.00 |
1,200.00 |
2,400.00 |
|
|
|
|
| 736-05-E |
signal heads (5-section, r,rty,y,rtg,g)(led)
|
5   |
EACH |
1,500.00 |
7,500.00 |
1,200.00 |
6,000.00 |
|
|
|
|
| 736-05-F |
signal heads (3-section, r,y,g)(led)(optically
programmed) |
2   |
EACH |
3,500.00 |
7,000.00 |
2,625.00 |
5,250.00 |
|
|
|
|
| 736-05-G |
signal heads (4-section, r,y,ltg,g)(optically
programmed) |
1   |
EACH |
4,000.00 |
4,000.00 |
3,500.00 |
3,500.00 |
|
|
|
|
| 736-06-A |
signal service (pole mounted for controller and/or
street lights) |
16   |
EACH |
1,500.00 |
24,000.00 |
800.00 |
12,800.00 |
|
|
|
|
| 736-06-B |
signal service (pedestal mounted for controller)
|
7   |
EACH |
2,000.00 |
14,000.00 |
1,100.00 |
7,700.00 |
|
|
|
|
| 736-08-A |
signal controller (ts2 controller cabinet with nema
ts-2,type 1 controller with ethernet port on new controller) |
8   |
EACH |
22,000.00 |
176,000.00 |
18,500.00 |
148,000.00 |
|
|
|
|
| 736-08-B |
signal controller(ts2 controller cabinet with nema
ts-2,type 1 controller w/ethernet port on exisitng controoler base |
2   |
EACH |
25,000.00 |
50,000.00 |
17,500.00 |
35,000.00 |
|
|
|
|
| 736-09 |
loop detector
|
2,935   |
LNFT |
12.00 |
35,220.00 |
10.00 |
29,350.00 |
|
|
|
|
| 736-10-A |
junction box (type "e")
|
58   |
EACH |
400.00 |
23,200.00 |
375.00 |
21,750.00 |
|
|
|
|
| 736-10-B |
junction box (type "f")
|
65   |
EACH |
600.00 |
39,000.00 |
450.00 |
29,250.00 |
|
|
|
|
| 736-10-C |
junction box (type "h")
|
8   |
EACH |
900.00 |
7,200.00 |
850.00 |
6,800.00 |
|
|
|
|
| 736-10-D |
junction box (type "i")
|
20   |
EACH |
1,200.00 |
24,000.00 |
900.00 |
18,000.00 |
|
|
|
|
| 736-10-E |
junction box (type "j")
|
10   |
EACH |
1,400.00 |
14,000.00 |
1,200.00 |
12,000.00 |
|
|
|
|
| 736-11-A |
conduit (1/2" p.e.c. schedule 80)
|
654   |
LNFT |
5.00 |
3,270.00 |
5.00 |
3,270.00 |
|
|
|
|
| 736-11-B |
conduit (1" p.e.c. schedule 80)
|
2,924   |
LNFT |
4.00 |
11,696.00 |
2.00 |
5,848.00 |
|
|
|
|
| 736-11-C |
conduit (2" p.e.c. schedule 80)
|
560   |
LNFT |
5.00 |
2,800.00 |
4.00 |
2,240.00 |
|
|
|
|
| 736-11-D |
conduit (3" p.e.c. schedule 80)
|
340   |
LNFT |
7.00 |
2,380.00 |
6.00 |
2,040.00 |
|
|
|
|
| 736-12-A |
conductor (2c, loop lead-in)
|
7,235   |
LNFT |
2.00 |
14,470.00 |
1.25 |
9,043.75 |
|
|
|
|
| 736-12-B |
conductor (3c, power)
|
1,802   |
LNFT |
3.00 |
5,406.00 |
4.50 |
8,109.00 |
|
|
|
|
| 736-12-C |
conductor (3c, illuminated signs)
|
545   |
LNFT |
3.00 |
1,635.00 |
2.00 |
1,090.00 |
|
|
|
|
| 736-12-D |
conductor (3c, emergency preemtion)
|
455   |
LNFT |
3.00 |
1,365.00 |
2.50 |
1,137.50 |
|
|
|
|
| 736-12-E |
conductor (3c, luminaires)
|
3,467   |
LNFT |
5.00 |
17,335.00 |
4.50 |
15,601.50 |
|
|
|
|
| 736-12-F |
conductor (6c, signal)
|
460   |
LNFT |
4.00 |
1,840.00 |
2.00 |
920.00 |
|
|
|
|
| 736-12-G |
conductor (10c, signal)
|
815   |
LNFT |
4.00 |
3,260.00 |
2.50 |
2,037.50 |
|
|
|
|
| 736-12-H |
conductor (video)
|
90   |
LNFT |
6.00 |
540.00 |
4.00 |
360.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
150,000.00 |
150,000.00 |
155,000.00 |
155,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
120,000.00 |
120,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
71.17 |
CUYD |
1,000.00 |
71,170.00 |
900.00 |
64,053.00 |
|
|
|
|
| 805-12-A |
reinforced concrete box culverts (4'x 3')
|
20.0 |
LNFT |
600.00 |
12,000.00 |
500.00 |
10,000.00 |
|
|
|
|
| 805-12-E |
reinforced concrete box culverts (4'x 4')
|
20.0 |
LNFT |
800.00 |
16,000.00 |
550.00 |
11,000.00 |
|
|
|
|
| 805-12-G |
reinforced concrete box culverts (6'x 4')
|
55.0 |
LNFT |
1,000.00 |
55,000.00 |
600.00 |
33,000.00 |
|
|
|
|
| 805-12-S |
reinforced concrete box culverts (8'x 8')
|
141.0 |
LNFT |
1,200.00 |
169,200.00 |
950.00 |
133,950.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
5,716   |
LB |
2.50 |
14,290.00 |
1.30 |
7,430.80 |
|
|
|
|
| S-001 |
emergency vehicle preemption detectors
|
33   |
EACH |
750.00 |
24,750.00 |
565.00 |
18,645.00 |
|
|
|
|
| S-002 |
emergency vehicle preemption phase selector
|
11   |
EACH |
4,000.00 |
44,000.00 |
3,325.00 |
36,575.00 |
|
|
|
|
| S-003 |
emergency vehicle preemption auxillary panel
|
3   |
EACH |
1,500.00 |
4,500.00 |
220.00 |
660.00 |
|
|
|
|
| S-004 |
internally illuminiated street name signs (18" x
varies) |
32   |
EACH |
2,400.00 |
76,800.00 |
1,730.00 |
55,360.00 |
|
|
|
|
| S-005 |
internally illuminiated street name signs (22" x
varies) |
8   |
EACH |
3,200.00 |
25,600.00 |
2,500.00 |
20,000.00 |
|
|
|
|
| S-006 |
conductor (fiber optic trunk cable 36 count single
mode) |
19,925   |
LNFT |
5.50 |
109,587.50 |
2.50 |
49,812.50 |
|
|
|
|
| S-007 |
conductor (fiber drop cable, 12 count single mode)
|
900   |
LNFT |
6.00 |
5,400.00 |
2.00 |
1,800.00 |
|
|
|
|
| S-008 |
sign ("buried fiber optics" 4" x 12")
|
29   |
EACH |
30.00 |
870.00 |
26.00 |
754.00 |
|
|
|
|
| S-009 |
splice closure
|
11   |
EACH |
2,000.00 |
22,000.00 |
1,800.00 |
19,800.00 |
|
|
|
|
| S-010 |
preterminated patch panel
|
12   |
EACH |
400.00 |
4,800.00 |
400.00 |
4,800.00 |
|
|
|
|
| S-011 |
patch cord
|
18   |
EACH |
60.00 |
1,080.00 |
300.00 |
5,400.00 |
|
|
|
|
| S-012 |
ethernet switch
|
11   |
EACH |
6,000.00 |
66,000.00 |
6,500.00 |
71,500.00 |
|
|
|
|
| S-013 |
video detection camera device and connection
|
37   |
EACH |
7,000.00 |
259,000.00 |
6,000.00 |
222,000.00 |
|
|
|
|
| S-014 |
video detection camera system
|
9   |
EACH |
3,000.00 |
27,000.00 |
3,000.00 |
27,000.00 |
|
|
|
|
| S-015 |
video surveillance camera
|
3   |
EACH |
12,000.00 |
36,000.00 |
10,000.00 |
30,000.00 |
|
|
|
|
| S-016 |
its 48 strand single mode cable
|
18,620   |
LNFT |
6.00 |
111,720.00 |
3.00 |
55,860.00 |
|
|
|
|
| S-017 |
strain pole extension
|
2   |
EACH |
2,000.00 |
4,000.00 |
1,500.00 |
3,000.00 |
|
|
|
|
| S-018 |
its 2" hdpe conduit - bored
|
35,340   |
LNFT |
12.00 |
424,080.00 |
11.00 |
388,740.00 |
|
|
|
|
| S-019 |
its underground handhole / pullbox
|
17   |
each |
2,000.00 |
34,000.00 |
2,000.00 |
34,000.00 |
|
|
|
|
| S-020 |
tie into existing florida blvd. system
|
lump |
LUMP |
90,000.00 |
90,000.00 |
65,000.00 |
65,000.00 |
|
|
|
|
| S-021 |
tie into existing i-12 system
|
lump |
LUMP |
220,000.00 |
220,000.00 |
95,000.00 |
95,000.00 |
|
|
|
|
| S-026 |
system integration and testing
|
lump |
lump |
30,000.00 |
30,000.00 |
11,000.00 |
11,000.00 |
|
|
|
|
| S-027 |
encoder/decoder system
|
lump |
lump |
40,000.00 |
40,000.00 |
31,000.00 |
31,000.00 |
|
|
|
|
| S-028 |
spare parts, tools, test equipment, documentation and
burn in |
lump |
lump |
35,000.00 |
35,000.00 |
45,000.00 |
45,000.00 |
|
|
|
|
| S-040 |
cb-opntop
|
1   |
each |
6,000.00 |
6,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| S-041 |
cb-opntop2
|
1   |
each |
8,000.00 |
8,000.00 |
5,500.00 |
5,500.00 |
|
|
|
|
| S-042 |
cleaning existing ditches
|
1,000   |
LNFT |
15.00 |
15,000.00 |
10.00 |
10,000.00 |
|
|
|
|
| S-043 |
saw cutting (full depth)
|
33,998   |
LNFT |
6.00 |
203,988.00 |
20.00 |
679,960.00 |
|
|
|
|
| S-044 |
tree trimming
|
8   |
EACH |
3,500.00 |
28,000.00 |
2,500.00 |
20,000.00 |
|
|
|
|
| S-045 |
paved gutter drain (pg-drain01)
|
43   |
EACH |
2,500.00 |
107,500.00 |
2,200.00 |
94,600.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
13,283,158.30 |
|
13,417,664.41 |
|
|
|
|
|