| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
15,000.00 |
15,000.00 |
50,000.00 |
50,000.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
7,546.0 |
SQYD |
4.00 |
30,184.00 |
5.00 |
37,730.00 |
|
|
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
30,000.00 |
30,000.00 |
72,000.00 |
72,000.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
6   |
EACH |
100.00 |
600.00 |
75.00 |
450.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
80   |
LNFT |
5.00 |
400.00 |
3.00 |
240.00 |
|
|
|
|
| 302-02-A-01 |
class ii base course (6" thick)(stone)
|
10,919.8 |
SQYD |
13.00 |
141,957.40 |
13.50 |
147,417.30 |
|
|
|
|
| 302-02-B-01 |
class ii base course (8 1/2" thick)(soil cement)
|
10,919.8 |
SQYD |
9.00 |
98,278.20 |
13.50 |
147,417.30 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
700   |
CUYD |
68.00 |
47,600.00 |
45.00 |
31,500.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
5,660.9 |
TON |
60.00 |
339,654.00 |
60.00 |
339,654.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
176.5 |
TON |
122.00 |
21,533.00 |
140.00 |
24,710.00 |
|
|
|
|
| 702-08-B |
side drain safety end (type 2)
|
2   |
EACH |
7,800.00 |
15,600.00 |
2,500.00 |
5,000.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,000.00 |
6,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (4" width)
|
170   |
LNFT |
0.11 |
18.70 |
0.30 |
51.00 |
|
|
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
950   |
LNFT |
0.22 |
209.00 |
0.50 |
475.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
0.275 |
MILE |
300.00 |
82.50 |
550.00 |
151.25 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
3.087 |
MILE |
600.00 |
1,852.20 |
400.00 |
1,234.80 |
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
4   |
EACH |
100.00 |
400.00 |
80.00 |
320.00 |
|
|
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
3,000.00 |
3,000.00 |
7,500.00 |
7,500.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
48,000.00 |
48,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,000   |
EACH |
5.00 |
5,000.00 |
6.00 |
6,000.00 |
|
|
|
|
| 732-01-A |
plastic pavement striping (4" width)
|
170   |
LNFT |
0.45 |
76.50 |
0.50 |
85.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
950   |
LNFT |
1.12 |
1,064.00 |
1.00 |
950.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
2,232   |
LNFT |
3.36 |
7,499.52 |
3.00 |
6,696.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
3.087 |
MILE |
2,100.00 |
6,482.70 |
2,500.00 |
7,717.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.275 |
MILE |
800.00 |
220.00 |
750.00 |
206.25 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
140.00 |
560.00 |
150.00 |
600.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
1.12 |
ACRE |
1,700.00 |
1,904.00 |
1,750.00 |
1,960.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
1,000.00 |
1,000.00 |
20,000.00 |
20,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
816,175.72 |
|
978,065.40 |
|
|
|
|
|