| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - MADDEN CONTRACTING CO., INC. |
- 2 - BENTON & BROWN, LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-08 |
borrow (vehicular measurement)
|
4,000   |
CUYD |
10.00 |
40,000.00 |
10.00 |
40,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
15,315.4 |
TON |
56.15 |
859,959.71 |
55.00 |
842,347.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
775.0 |
TON |
40.00 |
31,000.00 |
55.00 |
42,625.00 |
|
|
|
|
| 701-10-G |
reinforced concrete pipe (extension)(18")
|
12   |
LNFT |
150.00 |
1,800.00 |
75.00 |
900.00 |
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
6   |
LNFT |
180.00 |
1,080.00 |
85.00 |
510.00 |
|
|
|
|
| 701-10-K |
reinforced concrete pipe (extension)(30")
|
36   |
LNFT |
205.00 |
7,380.00 |
100.00 |
3,600.00 |
|
|
|
|
| 701-10-M |
reinforced concrete pipe (extension)(36")
|
128   |
LNFT |
230.00 |
29,440.00 |
120.00 |
15,360.00 |
|
|
|
|
| 701-15 |
concrete collar
|
29   |
EACH |
650.00 |
18,850.00 |
645.00 |
18,705.00 |
|
|
|
|
| 711-01-D |
riprap (55 lb)(12" thick)
|
144   |
SQYD |
55.00 |
7,920.00 |
50.00 |
7,200.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
144   |
SQYD |
2.50 |
360.00 |
1.50 |
216.00 |
|
|
|
|
| 712-02 |
sacked concrete revetment
|
300   |
SQYD |
70.00 |
21,000.00 |
55.00 |
16,500.00 |
|
|
|
|
| 712-03 |
stone revetment
|
97   |
SQYD |
48.00 |
4,656.00 |
25.00 |
2,425.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
45,000.00 |
45,000.00 |
70,000.00 |
70,000.00 |
|
|
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
300   |
LNFT |
0.10 |
30.00 |
0.50 |
150.00 |
|
|
|
|
| 713-03-D |
temporary pavement markings (12" width)
|
150   |
LNFT |
0.10 |
15.00 |
0.75 |
112.50 |
|
|
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
210   |
LNFT |
0.10 |
21.00 |
4.00 |
840.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
5.019 |
MILE |
325.00 |
1,631.17 |
360.00 |
1,806.84 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.362 |
MILE |
1.00 |
2.36 |
1.00 |
2.36 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
16.672 |
MILE |
1.00 |
16.67 |
1.00 |
16.67 |
|
|
|
|
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
2   |
EACH |
1.00 |
2.00 |
200.00 |
400.00 |
|
|
|
|
| 716-01-B |
mulch (fiber)
|
5.41 |
ACRE |
600.00 |
3,246.00 |
750.00 |
4,057.50 |
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
630   |
SQYD |
51.00 |
32,130.00 |
38.00 |
23,940.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
45,000.00 |
45,000.00 |
70,000.00 |
70,000.00 |
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
7   |
EACH |
65.00 |
455.00 |
80.00 |
560.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
760   |
EACH |
4.50 |
3,420.00 |
5.00 |
3,800.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
300   |
LNFT |
1.00 |
300.00 |
1.00 |
300.00 |
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
150   |
LNFT |
1.50 |
225.00 |
1.50 |
225.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
210   |
LNFT |
3.00 |
630.00 |
4.00 |
840.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
19.025 |
MILE |
1,850.00 |
35,196.25 |
2,500.00 |
47,562.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.419 |
MILE |
800.00 |
1,935.20 |
800.00 |
1,935.20 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
2   |
EACH |
400.00 |
800.00 |
500.00 |
1,000.00 |
|
|
|
|
| 735-01 |
mailboxes
|
22   |
EACH |
1.00 |
22.00 |
50.00 |
1,100.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
2   |
EACH |
175.00 |
350.00 |
140.00 |
280.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
10   |
EACH |
180.00 |
1,800.00 |
170.00 |
1,700.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
5.41 |
ACRE |
1,100.00 |
5,951.00 |
1,600.00 |
8,656.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
16,000.00 |
16,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
10,000.00 |
10,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,221,624.36 |
|
1,250,672.57 |
|
|
|
|
|