Letting of 7/27/2005 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 713-53-0107
Parish: TANGIPAHOA
Routes:
Description: BRIDGES ON BRIAR PATCH CEMETERY,STRAUGHNS NURSERY,NORTHHAYES
Type Const: grading, drainage structures, class ii base course, superpave asph conc pavement,
pvmt widening, conc slab span bridges and related work.
 
RankLicenseBidderAmount
100939 FORDICE CONSTRUCTION CO. $520,954.60
202109 CHAMBERS CONSTRUCTION CO., INC. $579,244.80
300481 COASTAL BRIDGE CO., L.L.C. $623,425.40
414422 T. L. WALLACE CONSTRUCTION, INC. $635,960.70
534567 JAMES CONSTRUCTION GROUP LLC $930,540.20
 
Item Number Item Description Quantity Unit of Measure - 1 -
FORDICE CONSTRUCTION CO.
- 2 -
CHAMBERS CONSTRUCTION CO., INC.
- 3 -
COASTAL BRIDGE CO., L.L.C.
- 4 -
T. L. WALLACE CONSTRUCTION, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 25,000.00 25,000.00 20,000.00 20,000.00 19,000.00 19,000.00 80,000.00 80,000.00
202-02-A-01 removal of bridge(sta. 105+00, 19.4' wide x 50.1' long
timber bridge)
1      EACH 5,000.00 5,000.00 8,000.00 8,000.00 6,000.00 6,000.00 5,000.00 5,000.00
202-02-A-02 removal of bridge(sta. 105+00, 21.0' wide x 36.06'
long timber bridge)
1      EACH 5,000.00 5,000.00 4,000.00 4,000.00 6,000.00 6,000.00 5,000.00 5,000.00
202-02-A-03 removal of bridge(sta. 105+00, 24.49' wide x 39.06'
long timber bridge)
1      EACH 5,000.00 5,000.00 6,000.00 6,000.00 6,000.00 6,000.00 5,000.00 5,000.00
202-02-G removal of surfacing & stabilized base 410.2    SQYD 6.50 2,666.30 12.00 4,922.40 7.00 2,871.40 7.00 2,871.40
203-06 excavation & embankment lump      LUMP 25,000.00 25,000.00 30,000.00 30,000.00 21,000.00 21,000.00 25,000.00 25,000.00
204-02 temporary hay or straw bales 250      EACH 10.50 2,625.00 10.00 2,500.00 10.00 2,500.00 10.00 2,500.00
204-03 temporary slope drains 350      LNFT 5.00 1,750.00 1.00 350.00 2.00 700.00 6.00 2,100.00
204-05-A temporary sediment check dams (hay) 12      EACH 225.00 2,700.00 25.00 300.00 200.00 2,400.00 200.00 2,400.00
204-06 temporary silt fencing 640      LNFT 4.00 2,560.00 3.00 1,920.00 2.00 1,280.00 3.00 1,920.00
302-01 class ii base course 110.1    CUYD 90.00 9,909.00 120.00 13,212.00 90.00 9,909.00 115.00 12,661.50
401-02 aggregate surface course (adjusted vehicular
measurement)
22      CUYD 65.00 1,430.00 85.00 1,870.00 65.00 1,430.00 190.00 4,180.00
502-01 superpave asphaltic concrete 257.0    TON 160.00 41,120.00 160.00 41,120.00 135.00 34,695.00 135.00 34,695.00
701-05-G side drain pipe (18") 91      LNFT 42.50 3,867.50 30.00 2,730.00 45.00 4,095.00 40.00 3,640.00
701-05-G-01 side drain pipe (18")(erosion) 365      LNFT 26.00 9,490.00 30.00 10,950.00 40.00 14,600.00 30.00 10,950.00
701-05-I-01 side drain pipe (24")(erosion) 397      LNFT 31.50 12,505.50 38.00 15,086.00 60.00 23,820.00 35.00 13,895.00
701-06-D-01 side drain pipe arch (24" equiv.)(erosion) 122      LNFT 45.00 5,490.00 42.00 5,124.00 60.00 7,320.00 45.00 5,490.00
704-08-B guard rail transitions (double thrie beam) 200.0    LNFT 43.00 8,600.00 60.00 12,000.00 50.00 10,000.00 45.00 9,000.00
704-09 guard rail anchor sections (turndown) 200.0    LNFT 32.00 6,400.00 35.00 7,000.00 40.00 8,000.00 35.00 7,000.00
705-01 barbed wire fence 600      LNFT 8.50 5,100.00 8.00 4,800.00 8.00 4,800.00 5.00 3,000.00
711-01-C riprap (30 lb, 14" thick) 522      SQYD 32.00 16,704.00 60.00 31,320.00 45.00 23,490.00 45.00 23,490.00
711-04 geotextile fabric 522      SQYD 2.00 1,044.00 2.00 1,044.00 3.00 1,566.00 2.00 1,044.00
713-01 temporary signs & barricades lump      LUMP 15,000.00 15,000.00 10,000.00 10,000.00 18,000.00 18,000.00 14,000.00 14,000.00
724-02 pavement widening 252.9    SQYD 65.00 16,438.50 100.00 25,290.00 80.00 20,232.00 80.00 20,232.00
726-01 bedding material 117.8    CUYD 55.00 6,479.00 60.00 7,068.00 55.00 6,479.00 55.00 6,479.00
727-01 mobilization lump      LUMP 25,000.00 25,000.00 26,900.00 26,900.00 78,000.00 78,000.00 60,000.00 60,000.00
729-16-B object marker assembly (type 2) 4      EACH 80.00 320.00 70.00 280.00 70.00 280.00 60.00 240.00
729-16-C object marker assembly (type 3) 16      EACH 80.00 1,280.00 85.00 1,360.00 80.00 1,280.00 70.00 1,120.00
740-01 construction layout lump      LUMP 10,000.00 10,000.00 5,000.00 5,000.00 5,000.00 5,000.00 14,000.00 14,000.00
744-01 traffic control management lump      LUMP 10,000.00 10,000.00 10,000.00 10,000.00 5,000.00 5,000.00 10,000.00 10,000.00
804-01-B precast concrete piles (14") 1,404      LNFT 30.00 42,120.00 40.00 56,160.00 42.00 58,968.00 31.00 43,524.00
804-12 loading permanent piles 2      EACH FREE FREE 100.00 200.00 100.00 200.00 1.00 2.00
805-01-B class a concrete (box culvert headwalls) 20.58   CUYD 700.00 14,406.00 500.00 10,290.00 700.00 14,406.00 660.00 13,582.80
805-10-A bridge superstructure & substructure (24' clr. rdwy;
90 degree crossing)
6      SPAN 15,500.00 93,000.00 20,000.00 120,000.00 19,400.00 116,400.00 18,000.00 108,000.00
805-12-H reinforced concrete box culverts (7'x 4') 188.0    LNFT 350.00 65,800.00 325.00 61,100.00 350.00 65,800.00 330.00 62,040.00
806-01 deformed reinforcing steel 2,458      LB 1.10 2,703.80 1.00 2,458.00 1.00 2,458.00 1.00 2,458.00
813-01 concrete approach slabs 111.12   SQYD 175.00 19,446.00 170.00 18,890.40 175.00 19,446.00 175.00 19,446.00
                       
 CONTRACTOR TOTAL       520,954.60   579,244.80   623,425.40   635,960.70
 
Item Number Item Description Quantity Unit of Measure - 5 -
JAMES CONSTRUCTION GROUP LLC

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 30,000.00 30,000.00            
202-02-A-01 removal of bridge(sta. 105+00, 19.4' wide x 50.1' long
timber bridge)
1      EACH 12,000.00 12,000.00            
202-02-A-02 removal of bridge(sta. 105+00, 21.0' wide x 36.06'
long timber bridge)
1      EACH 12,000.00 12,000.00            
202-02-A-03 removal of bridge(sta. 105+00, 24.49' wide x 39.06'
long timber bridge)
1      EACH 12,000.00 12,000.00            
202-02-G removal of surfacing & stabilized base 410.2    SQYD 15.00 6,153.00            
203-06 excavation & embankment lump      LUMP 50,000.00 50,000.00            
204-02 temporary hay or straw bales 250      EACH 7.00 1,750.00            
204-03 temporary slope drains 350      LNFT 1.50 525.00            
204-05-A temporary sediment check dams (hay) 12      EACH 150.00 1,800.00            
204-06 temporary silt fencing 640      LNFT 1.35 864.00            
302-01 class ii base course 110.1    CUYD 80.00 8,808.00            
401-02 aggregate surface course (adjusted vehicular
measurement)
22      CUYD 70.00 1,540.00            
502-01 superpave asphaltic concrete 257.0    TON 150.00 38,550.00            
701-05-G side drain pipe (18") 91      LNFT 60.00 5,460.00            
701-05-G-01 side drain pipe (18")(erosion) 365      LNFT 70.00 25,550.00            
701-05-I-01 side drain pipe (24")(erosion) 397      LNFT 80.00 31,760.00            
701-06-D-01 side drain pipe arch (24" equiv.)(erosion) 122      LNFT 100.00 12,200.00            
704-08-B guard rail transitions (double thrie beam) 200.0    LNFT 45.00 9,000.00            
704-09 guard rail anchor sections (turndown) 200.0    LNFT 25.00 5,000.00            
705-01 barbed wire fence 600      LNFT 7.00 4,200.00            
711-01-C riprap (30 lb, 14" thick) 522      SQYD 55.00 28,710.00            
711-04 geotextile fabric 522      SQYD 3.00 1,566.00            
713-01 temporary signs & barricades lump      LUMP 16,000.00 16,000.00            
724-02 pavement widening 252.9    SQYD 80.00 20,232.00            
726-01 bedding material 117.8    CUYD 85.00 10,013.00            
727-01 mobilization lump      LUMP 100,000.00 100,000.00            
729-16-B object marker assembly (type 2) 4      EACH 50.00 200.00            
729-16-C object marker assembly (type 3) 16      EACH 80.00 1,280.00            
740-01 construction layout lump      LUMP 20,000.00 20,000.00            
744-01 traffic control management lump      LUMP 5,000.00 5,000.00            
804-01-B precast concrete piles (14") 1,404      LNFT 90.00 126,360.00            
804-12 loading permanent piles 2      EACH 3,500.00 7,000.00            
805-01-B class a concrete (box culvert headwalls) 20.58   CUYD 1,500.00 30,870.00            
805-10-A bridge superstructure & substructure (24' clr. rdwy;
90 degree crossing)
6      SPAN 25,000.00 150,000.00            
805-12-H reinforced concrete box culverts (7'x 4') 188.0    LNFT 600.00 112,800.00            
806-01 deformed reinforcing steel 2,458      LB 1.00 2,458.00            
813-01 concrete approach slabs 111.12   SQYD 260.00 28,891.20            
                       
 CONTRACTOR TOTAL       930,540.20            