Letting of 7/27/2005 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 025-01-0043
Parish: VERNON, SABINE
Routes: US 171
Description: HORNBECK-FLORIEN (SOUTHBOUND LANES)
Type Const: grading, class i & ii bc, lime trmt, subgrade layer, drain struct,superpave acp,
pccp, concrete slab span bridges, and related work
 
RankLicenseBidderAmount
139462 DENTON-JAMES LLC $20,119,608.66
212487 DIAMOND B CONSTRUCTION CO., L.L.C. $20,703,295.21
312312 GILCHRIST CONSTRUCTION CO. LLC $21,826,155.30
408815 W. E. MCDONALD & SON, LLC. $24,238,872.52
 
Item Number Item Description Quantity Unit of Measure - 1 -
DENTON-JAMES LLC
- 2 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 3 -
GILCHRIST CONSTRUCTION CO. LLC
- 4 -
W. E. MCDONALD & SON, LLC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 900,000.00 900,000.00 375,000.00 375,000.00 200,000.00 200,000.00 125,000.00 125,000.00
202-01 removal of structures & obstructions lump      LUMP 184,000.00 184,000.00 50,000.00 50,000.00 100,000.00 100,000.00 132,000.00 132,000.00
202-02-A-01 removal of bridges (sta. 217+50, 27.7'x100', concrete
slab bridge)
1      EACH 18,000.00 18,000.00 30,000.00 30,000.00 20,000.00 20,000.00 15,000.00 15,000.00
202-02-A-02 removal of bridges (sta. 357+39.5, 27.8'x81', concrete
slab bridge)
1      EACH 16,000.00 16,000.00 30,000.00 30,000.00 12,000.00 12,000.00 15,000.00 15,000.00
202-02-A-03 removal of bridges (sta. 363+00, 27.6'x222.1',
concrete slab bridge)
1      EACH 28,000.00 28,000.00 40,000.00 40,000.00 25,000.00 25,000.00 15,000.00 15,000.00
202-02-A-04 removal of bridges (sta. 376+00, 27.6'x262.1',
concrete slab bridge)
1      EACH 32,000.00 32,000.00 40,000.00 40,000.00 25,000.00 25,000.00 15,000.00 15,000.00
202-02-B-01 removal of concrete box culverts (sta. 124+79,
3'x3'x56' r. c. box)
1      EACH 2,000.00 2,000.00 6,000.00 6,000.00 1,800.00 1,800.00 7,500.00 7,500.00
202-02-B-02 removal of concrete box culverts (sta. 146+90,
2-4'x4'x55.5' r. c. box)
1      EACH 4,000.00 4,000.00 8,000.00 8,000.00 3,000.00 3,000.00 7,500.00 7,500.00
202-02-B-03 removal of concrete box culverts (sta. 184+46,
4'x4'x77' r. c. box)
1      EACH 3,500.00 3,500.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-04 removal of concrete box culverts (sta. 190+73,
4-5'x5'x75.7' r. c. box)
1      EACH 8,000.00 8,000.00 16,000.00 16,000.00 6,000.00 6,000.00 7,500.00 7,500.00
202-02-B-05 removal of concrete box culverts (sta. 204+90,
4'x5'x76' r. c. box)
1      EACH 3,000.00 3,000.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-06 removal of concrete box culverts (sta. 233+48,
3'x3'x63.5' r. c. box)
1      EACH 2,000.00 2,000.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-07 removal of concrete box culverts (sta. 240+00,
4'x4'x53.7' r. c. box)
1      EACH 2,500.00 2,500.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-08 removal of concrete box culverts (sta. 249+45,
4'x4'x55' r. c. box)
1      EACH 2,500.00 2,500.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-09 removal of concrete box culverts (sta. 255+57,
3-4'x4'x55.3' r. c. box)
1      EACH 5,000.00 5,000.00 11,000.00 11,000.00 6,000.00 6,000.00 7,500.00 7,500.00
202-02-B-10 removal of concrete box culverts (sta. 324+11,
2'x3'x64' r. c. box)
1      EACH 2,000.00 2,000.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-11 removal of concrete box culverts (sta. 451+43.5,
3'x3'x46.5' r. c. box)
1      EACH 2,000.00 2,000.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-B-12 removal of concrete box culverts (sta. 457+71,
2'x6'x46.6' r. c. box)
1      EACH 3,000.00 3,000.00 6,000.00 6,000.00 1,500.00 1,500.00 7,500.00 7,500.00
202-02-C removal of portland cement concrete pavement 68,760      SQYD 5.50 378,180.00 6.00 412,560.00 3.25 223,470.00 5.00 343,800.00
202-02-D removal of concrete walks & drives 1,566      SQYD 8.00 12,528.00 5.00 7,830.00 4.00 6,264.00 25.00 39,150.00
202-02-F removal of concrete combination curb & gutter 670.0    LNFT 3.00 2,010.00 7.00 4,690.00 8.00 5,360.00 20.00 13,400.00
202-02-G removal of surfacing & stabilized base 1,380.9    SQYD 7.00 9,666.30 8.00 11,047.20 5.00 6,904.50 6.00 8,285.40
202-02-H removal of guard rail 1,428      LNFT 2.00 2,856.00 4.00 5,712.00 6.00 8,568.00 4.00 5,712.00
202-02-I removal of asphalt widening 23,409      SQYD 3.00 70,227.00 2.00 46,818.00 3.25 76,079.25 1.50 35,113.50
202-02-J removal of temporary junction box 2      EACH 500.00 1,000.00 5,000.00 10,000.00 2,000.00 4,000.00 2,000.00 4,000.00
202-02-K removal of temporary guardrail 250      LNFT 2.00 500.00 6.00 1,500.00 5.00 1,250.00 4.00 1,000.00
202-02-L removal of temporary detour roads 2,059.0    LNFT 20.00 41,180.00 8.00 16,472.00 15.00 30,885.00 33.00 67,947.00
202-02-M removal of stone check dams 43      EACH 250.00 10,750.00 500.00 21,500.00 50.00 2,150.00 250.00 10,750.00
202-02-N removal of temporary striping (type i removable tape) 4.500  MILE 5,300.00 23,850.00 5,500.00 24,750.00 5,500.00 24,750.00 5,280.00 23,760.00
203-01 general excavation 427,430      CUYD 2.60 1,111,318.00 4.63 1,979,000.90 3.75 1,602,862.50 3.00 1,282,290.00
203-02 drainage excavation 5,813      CUYD 6.00 34,878.00 10.00 58,130.00 6.00 34,878.00 12.00 69,756.00
203-03 muck excavation 12,801      CUYD 6.00 76,806.00 7.00 89,607.00 8.00 102,408.00 12.00 153,612.00
203-04 embankment 398,996      CUYD 3.80 1,516,184.80 4.00 1,595,984.00 6.75 2,693,223.00 6.00 2,393,976.00
203-05 nonplastic embankment 165      CUYD 120.00 19,800.00 125.00 20,625.00 80.00 13,200.00 88.00 14,520.00
204-01 temporary sandbagging 8.0    CUYD 500.00 4,000.00 275.00 2,200.00 300.00 2,400.00 250.00 2,000.00
204-02 temporary hay or straw bales 1,330      EACH 5.00 6,650.00 25.00 33,250.00 20.00 26,600.00 5.00 6,650.00
204-03 temporary slope drains 656      LNFT 10.00 6,560.00 16.00 10,496.00 20.00 13,120.00 15.00 9,840.00
204-04 temporary sediment basins 2      EACH 500.00 1,000.00 750.00 1,500.00 500.00 1,000.00 1,000.00 2,000.00
204-05-A temporary sediment check dams (hay) 75      EACH 70.00 5,250.00 150.00 11,250.00 150.00 11,250.00 70.00 5,250.00
204-05-B temporary sediment check dams (stone) 198      EACH 600.00 118,800.00 500.00 99,000.00 500.00 99,000.00 250.00 49,500.00
204-06 temporary silt fencing 26,248      LNFT 1.50 39,372.00 3.00 78,744.00 1.50 39,372.00 2.00 52,496.00
204-07 temporary stone construction entrance 9      EACH 1,500.00 13,500.00 1,800.00 16,200.00 200.00 1,800.00 1,000.00 9,000.00
301-01 class i base course 6,184.1    CUYD 75.00 463,807.50 63.00 389,598.30 75.00 463,807.50 80.00 494,728.00
302-01 class ii base course 30,379.3    CUYD 70.00 2,126,551.00 62.00 1,883,516.60 75.00 2,278,447.50 79.00 2,399,964.70
304-01 lime 694.58   TON 120.00 83,349.60 120.15 83,453.78 130.00 90,295.40 150.00 104,187.00
304-02-D lime treatment (type b) (12" thick) 49,000      SQYD 1.50 73,500.00 3.20 156,800.00 2.00 98,000.00 4.00 196,000.00
305-01-A subgrade layer (8" thick) 119,700      SQYD 5.00 598,500.00 6.01 719,397.00 7.00 837,900.00 6.25 748,125.00
305-01-B subgrade layer (12" thick) 22,344      SQYD 8.00 178,752.00 7.15 159,759.60 9.75 217,854.00 7.25 161,994.00
401-02 aggregate surface course (adjusted vehicular
measurement)
5,686      CUYD 50.00 284,300.00 12.00 68,232.00 30.00 170,580.00 30.00 170,580.00
402-01 traffic maintenance aggregate (vehicular measurement) 2,000.0    CUYD 65.00 130,000.00 25.00 50,000.00 30.00 60,000.00 15.00 30,000.00
502-01 superpave asphaltic concrete 42,701.3    TON 58.00 2,476,675.40 50.00 2,135,065.00 55.00 2,348,571.50 58.00 2,476,675.40
502-01-A superpave asphaltic concrete, paved drives and
turnouts
1,262.4    TON 100.00 126,240.00 100.00 126,240.00 85.00 107,304.00 101.00 127,502.40
601-01-M portland cement concrete pavement (11" thick) 7,478.5    SQYD 56.00 418,796.00 64.00 478,624.00 60.00 448,710.00 61.00 456,188.50
601-02-M portland cement concrete pavement (11" thick)
(crossovers & turnouts)
11,925.6    SQYD 62.00 739,387.20 68.00 810,940.80 65.00 775,164.00 65.00 775,164.00
601-03-M portland cement concrete shoulder (11" thick) 3,032.1    SQYD 60.00 181,926.00 68.00 206,182.80 60.00 181,926.00 65.00 197,086.50
601-04 portland cement concrete pavement coring 25      EACH 100.00 2,500.00 110.00 2,750.00 100.00 2,500.00 101.00 2,525.00
701-01-I cross drain pipe (24" rcp/pcp) 543      LNFT 60.00 32,580.00 64.00 34,752.00 55.00 29,865.00 45.00 24,435.00
701-01-K cross drain pipe (30" rcp/pcp) 1,234      LNFT 65.00 80,210.00 67.00 82,678.00 75.00 92,550.00 58.00 71,572.00
701-01-M cross drain pipe (36" rcp/pcp) 218      LNFT 90.00 19,620.00 95.00 20,710.00 110.00 23,980.00 79.00 17,222.00
701-01-N cross drain pipe (42" rcp/pcp) 208      LNFT 100.00 20,800.00 105.00 21,840.00 140.00 29,120.00 100.00 20,800.00
701-01-O-01 cross drain pipe (48" rcp/pcp)(class iv) 309      LNFT 130.00 40,170.00 132.00 40,788.00 180.00 55,620.00 165.00 50,985.00
701-01-O-02 cross drain pipe (48" rcp/pcp)(class v) 224      LNFT 150.00 33,600.00 153.00 34,272.00 200.00 44,800.00 200.00 44,800.00
701-01-P cross drain pipe (54" rcp/pcp) 520      LNFT 145.00 75,400.00 165.00 85,800.00 185.00 96,200.00 325.00 169,000.00
701-01-S cross drain pipe (72" rcp/pcp) 288      LNFT 280.00 80,640.00 286.00 82,368.00 350.00 100,800.00 600.00 172,800.00
701-01-W cross drain pipe (96" rcp/pcp) 240      LNFT 430.00 103,200.00 466.00 111,840.00 550.00 132,000.00 900.00 216,000.00
701-01-W-01 cross drain pipe (96" rcp/pcp)(class iv) 488      LNFT 480.00 234,240.00 487.00 237,656.00 580.00 283,040.00 900.00 439,200.00
701-02-F cross drain pipe arch (36" equiv. rcpa) 264      LNFT 90.00 23,760.00 96.00 25,344.00 120.00 31,680.00 92.00 24,288.00
701-02-J cross drain pipe arch (60" equiv. rcpa) 712      LNFT 230.00 163,760.00 233.00 165,896.00 240.00 170,880.00 225.00 160,200.00
701-03-F storm drain pipe (15" rcp/pcp) 932      LNFT 42.00 39,144.00 45.00 41,940.00 45.00 41,940.00 41.00 38,212.00
701-03-G storm drain pipe (18" rcp/pcp) 172      LNFT 44.00 7,568.00 48.00 8,256.00 60.00 10,320.00 48.00 8,256.00
701-05-G side drain pipe (18") 1,082      LNFT 40.00 43,280.00 42.00 45,444.00 45.00 48,690.00 39.00 42,198.00
701-05-I side drain pipe (24") 706      LNFT 50.00 35,300.00 53.00 37,418.00 75.00 52,950.00 48.00 33,888.00
701-05-K side drain pipe (30") 112      LNFT 75.00 8,400.00 80.00 8,960.00 100.00 11,200.00 55.00 6,160.00
701-15 concrete collar 2      EACH 1,000.00 2,000.00 1,100.00 2,200.00 1,500.00 3,000.00 1,200.00 2,400.00
702-03-A catch basins (cb-01) 14      EACH 2,400.00 33,600.00 3,400.00 47,600.00 3,500.00 49,000.00 2,000.00 28,000.00
702-03-B catch basins (cb-02) 5      EACH 4,000.00 20,000.00 4,300.00 21,500.00 4,500.00 22,500.00 3,000.00 15,000.00
702-03-I catch basins (cb-62) 2      EACH 4,000.00 8,000.00 5,800.00 11,600.00 5,000.00 10,000.00 5,000.00 10,000.00
703-02 shoulder outlet underdrains 264      EACH 350.00 92,400.00 10.00 2,640.00 350.00 92,400.00 515.00 135,960.00
703-03-A perforated pipe underdrains (4") 64,951      LNFT 6.50 422,181.50 0.50 32,475.50 4.75 308,517.25 9.55 620,282.05
703-03-B perforated pipe underdrains (6") 2,331      LNFT 10.00 23,310.00 0.50 1,165.50 15.00 34,965.00 12.55 29,254.05
703-04 nonperforated pipe underdrains 244      LNFT 14.00 3,416.00 27.00 6,588.00 16.00 3,904.00 1.50 366.00
704-03 blocked out guard rail 693.8    LNFT 15.00 10,407.00 16.00 11,100.80 17.00 11,794.60 16.50 11,447.70
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 38.00 3,800.00 40.00 4,000.00 41.00 4,100.00 40.00 4,000.00
704-11-A guard rail end treatment (flared) 4      EACH 1,500.00 6,000.00 1,600.00 6,400.00 2,100.00 8,400.00 2,000.00 8,000.00
705-09 rebuilt fence 598      LNFT 15.00 8,970.00 16.00 9,568.00 8.00 4,784.00 20.00 11,960.00
706-01-A concrete walk (4" thick) 380.5    SQYD 35.00 13,317.50 45.00 17,122.50 34.00 12,937.00 45.00 17,122.50
706-02-C concrete drive (6" thick) 3,482.9    SQYD 40.00 139,316.00 48.00 167,179.20 38.00 132,350.20 55.00 191,559.50
707-01 concrete curb 915.9    LNFT 3.00 2,747.70 9.00 8,243.10 12.00 10,990.80 8.50 7,785.15
708-01 right-of-way monument 253      EACH 120.00 30,360.00 110.00 27,830.00 300.00 75,900.00 150.00 37,950.00
708-02 right-of-way monument witness post 253      EACH 120.00 30,360.00 110.00 27,830.00 300.00 75,900.00 150.00 37,950.00
711-02-C riprap (30 lb) 590      CUYD 90.00 53,100.00 90.00 53,100.00 80.00 47,200.00 105.00 61,950.00
712-01-A concrete cast-in-place revetment (4" thick) 4,921      SQYD 37.00 182,077.00 67.00 329,707.00 33.00 162,393.00 70.00 344,470.00
712-04 flexible revetment 11,781      SQYD 40.00 471,240.00 42.00 494,802.00 50.00 589,050.00 45.00 530,145.00
713-01 temporary signs & barricades lump      LUMP 140,000.00 140,000.00 100,000.00 100,000.00 100,000.00 100,000.00 375,000.00 375,000.00
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
1.000  MILE 500.00 500.00 175.00 175.00 550.00 550.00 250.00 250.00
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
2.000  MILE 300.00 600.00 280.00 560.00 300.00 600.00 264.00 528.00
713-05-A temporary pavement markings (solid line)(4" width) 2.000  MILE 700.00 1,400.00 670.00 1,340.00 650.00 1,300.00 633.00 1,266.00
713-05-A-01 temporary pavement markings (solid line)(4" width)
(type i removable)
1.500  MILE 12,000.00 18,000.00 12,500.00 18,750.00 12,000.00 18,000.00 11,880.00 17,820.00
716-01-A mulch (vegetative) 193.13   ACRE 600.00 115,878.00 635.00 122,637.55 650.00 125,534.50 600.00 115,878.00
717-01 seeding 3,650      LB 7.00 25,550.00 8.00 29,200.00 10.00 36,500.00 7.00 25,550.00
718-01 fertilizer 81,096      LB 0.30 24,328.80 0.32 25,950.72 0.35 28,383.60 0.30 24,328.80
718-02 agricultural lime 24.8    TON 100.00 2,480.00 105.00 2,604.00 200.00 4,960.00 99.00 2,455.20
720-01-A erosion control system, slope protection (type a) 162,736      SQYD 1.00 162,736.00 1.05 170,872.80 1.50 244,104.00 0.99 161,108.64
720-01-C erosion control system, flexible channel liner (type c) 24,319      SQYD 1.30 31,614.70 1.32 32,101.08 1.70 41,342.30 1.25 30,398.75
720-01-D erosion control system, flexible channel liner (type d) 23,128      SQYD 1.30 30,066.40 1.32 30,528.96 1.70 39,317.60 1.25 28,910.00
720-01-E erosion control system, flexible channel liner (type e) 1,611      SQYD 2.00 3,222.00 2.07 3,334.77 2.20 3,544.20 1.95 3,141.45
720-01-F erosion control system, flexible channel liner (type f) 1,533      SQYD 2.00 3,066.00 2.07 3,173.31 2.50 3,832.50 1.95 2,989.35
722-02 project site laboratory (equipped) 1      EACH 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 35,000.00 35,000.00
724-01-B pavement patching (12" minimum thickness) 50      SQYD 85.00 4,250.00 115.00 5,750.00 150.00 7,500.00 75.00 3,750.00
726-01 bedding material 2,286.3    CUYD 50.00 114,315.00 53.00 121,173.90 60.00 137,178.00 65.00 148,609.50
727-01 mobilization lump      LUMP 2,000,000.00 2,000,000.00 2,000,000.00 2,000,000.00 2,000,000.00 2,000,000.00 2,100,000.00 2,100,000.00
729-16-C object marker assembly (type 3) 16      EACH 65.00 1,040.00 58.00 928.00 80.00 1,280.00 70.00 1,120.00
731-02 reflectorized raised pavement markers 2,308      EACH 5.00 11,540.00 5.00 11,540.00 5.00 11,540.00 4.90 11,309.20
732-01-A plastic pavement striping (4" width) 13,948      LNFT 0.40 5,579.20 0.42 5,858.16 0.45 6,276.60 0.40 5,579.20
732-01-C plastic pavement striping (8" width) 880      LNFT 0.80 704.00 0.85 748.00 0.90 792.00 0.80 704.00
732-01-E plastic pavement striping (24" width) 754      LNFT 2.40 1,809.60 2.54 1,915.16 2.50 1,885.00 2.40 1,809.60
732-02-A plastic pavement striping (solid line) (4" width) 25.838  MILE 2,000.00 51,676.00 2,100.00 54,259.80 2,100.00 54,259.80 1,990.00 51,417.62
732-03-A plastic pavement striping (broken line)(4" width) 14.131  MILE 700.00 9,891.70 700.00 9,891.70 700.00 9,891.70 660.00 9,326.46
732-04-A plastic pavement legends & symbols (arrow) 17      EACH 130.00 2,210.00 132.00 2,244.00 150.00 2,550.00 125.00 2,125.00
732-04-C plastic pavement legends & symbols (only) 5      EACH 140.00 700.00 143.00 715.00 160.00 800.00 135.00 675.00
732-05 removal of existing markings 2.000  MILE 4,500.00 9,000.00 4,800.00 9,600.00 5,000.00 10,000.00 4,500.00 9,000.00
735-01 mailboxes 45      EACH 1.00 45.00 12.00 540.00 50.00 2,250.00 1.00 45.00
735-02 mailbox supports (single) 37      EACH 140.00 5,180.00 130.00 4,810.00 150.00 5,550.00 200.00 7,400.00
735-03 mailbox supports (double) 2      EACH 200.00 400.00 300.00 600.00 200.00 400.00 300.00 600.00
735-04 mailbox supports (multiple) 1      EACH 400.00 400.00 600.00 600.00 400.00 400.00 500.00 500.00
740-01 construction layout lump      LUMP 250,000.00 250,000.00 250,000.00 250,000.00 200,000.00 200,000.00 400,000.00 400,000.00
804-01-C precast concrete piles (16") 3,655      LNFT 34.00 124,270.00 52.00 190,060.00 40.00 146,200.00 35.00 127,925.00
804-12 loading permanent piles 2      EACH 1,000.00 2,000.00 1.00 2.00 100.00 200.00 1.00 2.00
805-01-A class a concrete (pipe headwalls) 377.13   CUYD 850.00 320,560.50 950.00 358,273.50 700.00 263,991.00 1,500.00 565,695.00
805-01-F class a concrete (bents) 106.90   CUYD 800.00 85,520.00 850.00 90,865.00 500.00 53,450.00 600.00 64,140.00
805-03 class aa concrete 457.45   CUYD 450.00 205,852.50 688.00 314,725.60 600.00 274,470.00 475.00 217,288.75
806-01 deformed reinforcing steel 126,123      LB 0.70 88,286.10 1.00 126,123.00 1.00 126,123.00 5.50 693,676.50
810-01 concrete railing (barrier) 760.18   LNFT 47.00 35,728.46 59.00 44,850.62 50.00 38,009.00 65.00 49,411.70
813-01 concrete approach slabs 546.77   SQYD 160.00 87,483.20 200.00 109,354.00 150.00 82,015.50 185.00 101,152.45
S-002 completion of catch basins lump      LUMP 35,000.00 35,000.00 50,000.00 50,000.00 5,000.00 5,000.00 75,000.00 75,000.00
S-003 sandblasting and painting of catch basin grates lump      LUMP 12,000.00 12,000.00 8,000.00 8,000.00 15,000.00 15,000.00 45,000.00 45,000.00
S-004 maintenance of existing temporary erosion control
features
lump      LUMP 30,000.00 30,000.00 50,000.00 50,000.00 50,000.00 50,000.00 75,000.00 75,000.00
S-005 rumble strips (ground-in) 13.0    MILE 600.00 7,800.00 700.00 9,100.00 600.00 7,800.00 680.00 8,840.00
S-006 redressing slopes and ditches 110,000      SQYD 0.50 55,000.00 2.25 247,500.00 2.00 220,000.00 4.00 440,000.00
S-007 borrow, (vehicular measurement) 150,000      CUYD 5.10 765,000.00 8.00 1,200,000.00 6.50 975,000.00 8.00 1,200,000.00
                       
 CONTRACTOR TOTAL       20,119,608.66   20,703,295.21   21,826,155.30   24,238,872.52