| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - R. E. HEIDT CONSTRUCTION CO., INC. |
- 2 - PRAIRIE CONTRACTORS INC. |
- 3 - BESSETTE DEVELOPMENT CORP. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-E |
removal of concrete curbs
|
450.0 |
LNFT |
4.20 |
1,890.00 |
15.00 |
6,750.00 |
5.50 |
2,475.00 |
|
|
| 202-02-H |
removal of guard rail
|
673   |
LNFT |
7.00 |
4,711.00 |
4.00 |
2,692.00 |
4.25 |
2,860.25 |
|
|
| 203-01 |
general excavation
|
165   |
CUYD |
18.15 |
2,994.75 |
5.00 |
825.00 |
8.75 |
1,443.75 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
100   |
CUYD |
43.00 |
4,300.00 |
18.00 |
1,800.00 |
63.75 |
6,375.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
46   |
CUYD |
79.00 |
3,634.00 |
90.00 |
4,140.00 |
56.25 |
2,587.50 |
|
|
| 502-01 |
superpave asphaltic concrete
|
12,653.4 |
TON |
50.30 |
636,466.02 |
52.00 |
657,976.80 |
54.25 |
686,446.95 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
824.2 |
TON |
39.00 |
32,143.80 |
60.00 |
49,452.00 |
58.00 |
47,803.60 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
65,237   |
SQYD |
1.20 |
78,284.40 |
1.35 |
88,069.95 |
0.60 |
39,142.20 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,812   |
CUYD |
1.00 |
- 1,812.00 |
0.01 |
- 18.12 |
1.00 |
- 1,812.00 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
19,026   |
LNFT |
1.13 |
21,499.38 |
1.15 |
21,879.90 |
1.20 |
22,831.20 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
22,824   |
LNFT |
1.29 |
29,442.96 |
1.35 |
30,812.40 |
1.35 |
30,812.40 |
|
|
| 704-03 |
blocked out guard rail
|
362.5 |
LNFT |
18.00 |
6,525.00 |
16.00 |
5,800.00 |
19.25 |
6,978.12 |
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
50.0 |
LNFT |
37.00 |
1,850.00 |
50.00 |
2,500.00 |
32.75 |
1,637.50 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
51.50 |
5,150.00 |
60.00 |
6,000.00 |
49.25 |
4,925.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
1,900.00 |
7,600.00 |
1,900.00 |
7,600.00 |
2,188.00 |
8,752.00 |
|
|
| 707-01 |
concrete curb
|
100.0 |
LNFT |
20.60 |
2,060.00 |
30.00 |
3,000.00 |
19.25 |
1,925.00 |
|
|
| 707-04 |
asphaltic curb
|
40.0 |
LNFT |
28.00 |
1,120.00 |
50.00 |
2,000.00 |
35.00 |
1,400.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,100.00 |
6,100.00 |
30,000.00 |
30,000.00 |
12,500.00 |
12,500.00 |
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
4,917   |
LNFT |
0.16 |
786.72 |
0.01 |
49.17 |
0.20 |
983.40 |
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
5,277   |
LNFT |
0.93 |
4,907.61 |
0.01 |
52.77 |
1.00 |
5,277.00 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
12.208 |
MILE |
160.00 |
1,953.28 |
300.00 |
3,662.40 |
350.00 |
4,272.80 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
6.210 |
MILE |
309.00 |
1,918.89 |
1.00 |
6.21 |
330.00 |
2,049.30 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
17.088 |
MILE |
515.00 |
8,800.32 |
1.00 |
17.08 |
545.00 |
9,312.96 |
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
45   |
EACH |
51.50 |
2,317.50 |
1.00 |
45.00 |
55.00 |
2,475.00 |
|
|
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
6   |
EACH |
206.00 |
1,236.00 |
1.00 |
6.00 |
215.00 |
1,290.00 |
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
3,882   |
SQYD |
43.50 |
168,867.00 |
48.00 |
186,336.00 |
50.25 |
195,070.50 |
|
|
| 724-03 |
pavement joint repair
|
10.0 |
TON |
330.00 |
3,300.00 |
300.00 |
3,000.00 |
345.00 |
3,450.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
14,000.00 |
14,000.00 |
4,000.00 |
4,000.00 |
20,000.00 |
20,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
14   |
EACH |
51.50 |
721.00 |
60.00 |
840.00 |
65.75 |
920.50 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
72.00 |
288.00 |
100.00 |
400.00 |
78.00 |
312.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
600   |
EACH |
5.15 |
3,090.00 |
5.50 |
3,300.00 |
5.50 |
3,300.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,639   |
LNFT |
1.03 |
1,688.17 |
1.50 |
2,458.50 |
1.10 |
1,802.90 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
1,759   |
LNFT |
3.09 |
5,435.31 |
3.00 |
5,277.00 |
3.25 |
5,716.75 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
5.696 |
MILE |
2,000.00 |
11,392.00 |
2,000.00 |
11,392.00 |
2,080.00 |
11,847.68 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.070 |
MILE |
824.00 |
1,705.68 |
800.00 |
1,656.00 |
875.25 |
1,811.76 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
15   |
EACH |
155.00 |
2,325.00 |
200.00 |
3,000.00 |
165.00 |
2,475.00 |
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
2   |
EACH |
412.00 |
824.00 |
500.00 |
1,000.00 |
440.00 |
880.00 |
|
|
| 735-01 |
mailboxes
|
23   |
EACH |
1.03 |
23.69 |
2.00 |
46.00 |
1.25 |
28.75 |
|
|
| 735-02 |
mailbox supports (single)
|
23   |
EACH |
128.00 |
2,944.00 |
145.00 |
3,335.00 |
140.00 |
3,220.00 |
|
|
| 736-09 |
loop detector
|
186   |
LNFT |
16.50 |
3,069.00 |
20.00 |
3,720.00 |
37.25 |
6,928.50 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
3,800.00 |
3,800.00 |
100.00 |
100.00 |
7,000.00 |
7,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
7,500.00 |
7,500.00 |
100.00 |
100.00 |
24,500.00 |
24,500.00 |
|
|
| S-001 |
rumble strips (ground-in)
|
5.4 |
MILE |
1,160.00 |
6,264.00 |
825.00 |
4,455.00 |
865.00 |
4,671.00 |
|
|
| S-002 |
saw cutting portland cement concrete
|
3,372   |
INFT |
1.14 |
3,844.08 |
1.25 |
4,215.00 |
1.20 |
4,046.40 |
|
|
| S-922 |
sawing and sealing longitudinal joints in asphaltic
concrete overlay |
21,892   |
LNFT |
1.03 |
22,548.76 |
1.05 |
22,986.60 |
1.10 |
24,081.20 |
|
|
| S-923 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
22,824   |
LNFT |
1.14 |
26,019.36 |
1.15 |
26,247.60 |
1.20 |
27,388.80 |
|
|
| S-927 |
sawcuts in asphaltic concrete lifts
|
58,290   |
LNFT |
0.67 |
39,054.30 |
0.67 |
39,054.30 |
0.75 |
43,717.50 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,194,582.98 |
|
1,252,037.56 |
|
1,297,913.17 |
|
|
|