| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - AMERICAN CONTRACTING & SERVICES,INC |
- 2 - HIGHWAY SPECIALISTS INC. |
- 3 - GILBERT SOUTHERN CORP |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
109,000.00 |
109,000.00 |
100,000.00 |
100,000.00 |
55,000.00 |
55,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
2,574   |
SQYD |
12.00 |
30,888.00 |
10.00 |
25,740.00 |
15.00 |
38,610.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
1,336.8 |
SQYD |
9.00 |
12,031.20 |
8.00 |
10,694.40 |
5.00 |
6,684.00 |
|
|
| 202-02-H |
removal of guard rail
|
156   |
LNFT |
6.00 |
936.00 |
7.00 |
1,092.00 |
5.50 |
858.00 |
|
|
| 202-02-J |
removal of median fence
|
2,084   |
LNFT |
5.00 |
10,420.00 |
8.00 |
16,672.00 |
10.00 |
20,840.00 |
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
15,000.00 |
15,000.00 |
100,000.00 |
100,000.00 |
50,000.00 |
50,000.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
124   |
CUYD |
70.00 |
8,680.00 |
30.00 |
3,720.00 |
30.61 |
3,795.64 |
|
|
| 302-02-D |
class ii base course (12" thick)
|
3,303.7 |
SQYD |
35.00 |
115,629.50 |
28.00 |
92,503.60 |
30.00 |
99,111.00 |
|
|
| 601-01-K |
portland cement concrete pavement (10" thick)
|
1,992.6 |
SQYD |
75.00 |
149,445.00 |
88.00 |
175,348.80 |
60.00 |
119,556.00 |
|
|
| 601-03-K |
portland cement concrete shoulder (10" thick)
|
1,243.5 |
SQYD |
75.00 |
93,262.50 |
92.00 |
114,402.00 |
70.00 |
87,045.00 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
8,339   |
LNFT |
2.00 |
16,678.00 |
1.75 |
14,593.25 |
3.00 |
25,017.00 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
4,851   |
LNFT |
2.00 |
9,702.00 |
1.75 |
8,489.25 |
5.00 |
24,255.00 |
|
|
| 602-03 |
cleaning and sealing random cracks
|
20   |
LNFT |
3.00 |
60.00 |
25.00 |
500.00 |
10.00 |
200.00 |
|
|
| 602-05-G-01 |
full depth patching of jointed concrete pavement (8"
thick) (16.0 sq yds & under) |
231.2 |
SQYD |
110.00 |
25,432.00 |
165.00 |
38,148.00 |
200.00 |
46,240.00 |
|
|
| 602-05-G-02 |
full depth patching of jointed concrete pavement (8"
thick) (16.1 to 48.0 sq yds) |
665.2 |
SQYD |
70.00 |
46,564.00 |
155.00 |
103,106.00 |
150.00 |
99,780.00 |
|
|
| 602-05-G-03 |
full depth patching of jointed concrete pavement (8"
thick) (48.1 sq yds & over) |
1,257.2 |
SQYD |
60.00 |
75,432.00 |
135.00 |
169,722.00 |
125.00 |
157,150.00 |
|
|
| 602-05-I-01 |
full depth patching of jointed concrete pavement (9"
thick) (16.0 sq yds & under) |
134.3 |
SQYD |
115.00 |
15,444.50 |
175.00 |
23,502.50 |
200.00 |
26,860.00 |
|
|
| 602-05-I-02 |
full depth patching of jointed concrete pavement (9"
thick) (16.1 to 48.0 sq yds) |
48.0 |
SQYD |
75.00 |
3,600.00 |
165.00 |
7,920.00 |
150.00 |
7,200.00 |
|
|
| 602-05-I-03 |
full depth patching of jointed concrete pavement (9"
thick) (48.1 sq yds & over) |
639.5 |
SQYD |
65.00 |
41,567.50 |
145.00 |
92,727.50 |
100.00 |
63,950.00 |
|
|
| 602-05-K-01 |
full depth patching of jointed concrete pavement (10"
thick) (16.0 sq yds & under) |
6.0 |
SQYD |
250.00 |
1,500.00 |
220.00 |
1,320.00 |
250.00 |
1,500.00 |
|
|
| 602-05-K-03 |
full depth patching of jointed concrete pavement (10"
thick) (48.1 sq yds & over) |
840.9 |
SQYD |
85.00 |
71,476.50 |
145.00 |
121,930.50 |
125.00 |
105,112.50 |
|
|
| 701-10-E |
reinforced concrete pipe (extension) (12")
|
20   |
LNFT |
100.00 |
2,000.00 |
250.00 |
5,000.00 |
125.00 |
2,500.00 |
|
|
| 701-16-F |
plastic pipe (extension) (15" rpvcp)
|
16   |
LNFT |
125.00 |
2,000.00 |
50.00 |
800.00 |
125.00 |
2,000.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
2   |
EACH |
2,200.00 |
4,400.00 |
4,200.00 |
8,400.00 |
2,500.00 |
5,000.00 |
|
|
| 702-03-C |
catch basins (cb-06)
|
1   |
EACH |
2,200.00 |
2,200.00 |
6,000.00 |
6,000.00 |
5,000.00 |
5,000.00 |
|
|
| 702-04-A |
adjusting manholes
|
17   |
EACH |
1,500.00 |
25,500.00 |
3,000.00 |
51,000.00 |
1,250.00 |
21,250.00 |
|
|
| 702-04-B |
adjusting catch basins
|
20   |
EACH |
1,275.00 |
25,500.00 |
4,000.00 |
80,000.00 |
1,500.00 |
30,000.00 |
|
|
| 703-01 |
shoulder underdrain systems
|
1,225   |
LNFT |
16.00 |
19,600.00 |
12.00 |
14,700.00 |
7.50 |
9,187.50 |
|
|
| 703-02 |
shoulder outlet underdrains
|
6   |
EACH |
1,000.00 |
6,000.00 |
1,600.00 |
9,600.00 |
350.00 |
2,100.00 |
|
|
| 704-01-C |
guard rail (double thrie beam) (3'-1 1/2" post spacing)
|
81.3 |
LNFT |
60.00 |
4,878.00 |
55.00 |
4,471.50 |
43.00 |
3,495.90 |
|
|
| 704-03 |
blocked out guard rail
|
50.0 |
LNFT |
16.00 |
800.00 |
25.00 |
1,250.00 |
15.00 |
750.00 |
|
|
| 704-06-A |
guard rail anchor sections (trailing end) (single
thrie beam) |
6.3 |
LNFT |
60.00 |
378.00 |
75.00 |
472.50 |
65.00 |
409.50 |
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
400.0 |
LNFT |
40.00 |
16,000.00 |
45.00 |
18,000.00 |
39.00 |
15,600.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
1   |
EACH |
2,100.00 |
2,100.00 |
2,500.00 |
2,500.00 |
2,000.00 |
2,000.00 |
|
|
| 706-01-A |
concrete walk (4" thick)
|
51.1 |
SQYD |
50.00 |
2,555.00 |
60.00 |
3,066.00 |
60.00 |
3,066.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
30.9 |
SQYD |
90.00 |
2,781.00 |
85.00 |
2,626.50 |
75.00 |
2,317.50 |
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
265.1 |
SQYD |
80.00 |
21,208.00 |
75.00 |
19,882.50 |
85.00 |
22,533.50 |
|
|
| 707-01 |
concrete curb
|
2,108.9 |
LNFT |
16.00 |
33,742.40 |
12.00 |
25,306.80 |
18.00 |
37,960.20 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
440,000.00 |
440,000.00 |
1,200,000.00 |
1,200,000.00 |
975,000.00 |
975,000.00 |
|
|
| 713-03-C-01 |
temporary pavement markings (solid) (8" width) (type
1 removable) |
2,500   |
LNFT |
7.25 |
18,125.00 |
7.00 |
17,500.00 |
5.00 |
12,500.00 |
|
|
| 713-04-B |
temporary pavement markings (broken line) (4" width)
(10' length) |
2.000 |
MILE |
1,100.00 |
2,200.00 |
1,050.00 |
2,100.00 |
600.00 |
1,200.00 |
|
|
| 713-04-B-01 |
temporary pavement markings (broken line) (4" width)
(10' length) (type i removable) |
2.000 |
MILE |
4,200.00 |
8,400.00 |
4,100.00 |
8,200.00 |
4,000.00 |
8,000.00 |
|
|
| 713-05-A |
temporary pavement markings (solid line) (4" width)
|
4.000 |
MILE |
1,150.00 |
4,600.00 |
1,100.00 |
4,400.00 |
1,000.00 |
4,000.00 |
|
|
| 713-05-A-01 |
temporary pavement markings (solid line) (4" width)
(type 1 removable) |
40.000 |
MILE |
7,920.00 |
316,800.00 |
7,920.00 |
316,800.00 |
15,850.00 |
634,000.00 |
|
|
| 713-07 |
temporary reflectorized raised pavement markers
|
375   |
EACH |
16.00 |
6,000.00 |
5.00 |
1,875.00 |
5.00 |
1,875.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
30,000.00 |
30,000.00 |
9,000.00 |
9,000.00 |
100,000.00 |
100,000.00 |
|
|
| 725-01 |
temporary detour roads
|
580.0 |
LNFT |
300.00 |
174,000.00 |
1,000.00 |
580,000.00 |
350.00 |
203,000.00 |
|
|
| 726-01 |
bedding material
|
22.5 |
CUYD |
65.00 |
1,462.50 |
50.00 |
1,125.00 |
35.00 |
787.50 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
900,000.00 |
900,000.00 |
1,200,000.00 |
1,200,000.00 |
1,200,000.00 |
1,200,000.00 |
|
|
| 729-01 |
sign (type a)
|
12.6 |
SQFT |
30.00 |
378.00 |
30.00 |
378.00 |
30.00 |
378.00 |
|
|
| 729-08-B |
mounting (3 1/2" size post)
|
1   |
EACH |
760.00 |
760.00 |
650.00 |
650.00 |
1,000.00 |
1,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
67.00 |
134.00 |
75.00 |
150.00 |
75.00 |
150.00 |
|
|
| 729-21 |
u-channel post
|
1   |
EACH |
105.00 |
105.00 |
100.00 |
100.00 |
150.00 |
150.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
917   |
EACH |
6.00 |
5,502.00 |
15.00 |
13,755.00 |
6.00 |
5,502.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
4,210   |
LNFT |
1.00 |
4,210.00 |
10.00 |
42,100.00 |
1.00 |
4,210.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
716   |
LNFT |
3.00 |
2,148.00 |
30.00 |
21,480.00 |
3.00 |
2,148.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
5.326 |
MILE |
2,250.00 |
11,983.50 |
8,000.00 |
42,608.00 |
2,250.00 |
11,983.50 |
|
|
| 732-03-A-01 |
plastic pavement striping (broken line) (4"width)
preformed marking tape (type v) |
1.642 |
MILE |
4,700.00 |
7,717.40 |
10,000.00 |
16,420.00 |
4,750.00 |
7,799.50 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
3   |
EACH |
160.00 |
480.00 |
1,000.00 |
3,000.00 |
200.00 |
600.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
3   |
EACH |
200.00 |
600.00 |
1,000.00 |
3,000.00 |
200.00 |
600.00 |
|
|
| 732-05 |
removal of existing markings
|
1.775 |
MILE |
8,000.00 |
14,200.00 |
7,500.00 |
13,312.50 |
5,000.00 |
8,875.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
35,000.00 |
35,000.00 |
150,000.00 |
150,000.00 |
100,000.00 |
100,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
150,000.00 |
150,000.00 |
150,000.00 |
150,000.00 |
100,000.00 |
100,000.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
1,000   |
LB |
3.00 |
3,000.00 |
2.00 |
2,000.00 |
2.00 |
2,000.00 |
|
|
| S-101 |
hydro-demolition
|
27,303.2 |
SQYD |
69.00 |
1,883,920.80 |
45.00 |
1,228,644.00 |
75.00 |
2,047,740.00 |
|
|
| S-102-A |
furnishing latex modified cement concrete - very early
strength (1 1/2" depth) |
1,308.36 |
CUYD |
800.00 |
1,046,688.00 |
1,200.00 |
1,570,032.00 |
1,100.00 |
1,439,196.00 |
|
|
| S-102-B |
placing and finishing latex modified concrete - very
early strength overlay |
27,303.2 |
SQYD |
30.00 |
819,096.00 |
35.00 |
955,612.00 |
40.88 |
1,116,154.81 |
|
|
| S-103-A |
full depth deck patching (25.0 sq. ft. and under)
|
5,000.0 |
SQFT |
30.00 |
150,000.00 |
27.50 |
137,500.00 |
35.00 |
175,000.00 |
|
|
| S-103-B |
full depth deck patching ( 25.1 sq. ft. and over)
|
2,000.0 |
SQFT |
30.00 |
60,000.00 |
37.50 |
75,000.00 |
45.00 |
90,000.00 |
|
|
| S-104 |
removal, storage and re-installation of impact
attenuators |
3   |
EACH |
4,000.00 |
12,000.00 |
6,000.00 |
18,000.00 |
6,000.00 |
18,000.00 |
|
|
| S-105 |
bridge rail modifications
|
15,789   |
LNFT |
110.00 |
1,736,790.00 |
161.50 |
2,549,923.50 |
125.00 |
1,973,625.00 |
|
|
| S-109 |
armor joint repair
|
58.5 |
LNFT |
250.00 |
14,625.00 |
125.00 |
7,312.50 |
600.00 |
35,100.00 |
|
|
| S-111 |
remove and replace existing lighting system
|
lump |
LUMP |
20,000.00 |
20,000.00 |
19,000.00 |
19,000.00 |
25,000.00 |
25,000.00 |
|
|
| S-112 |
temporary queue detection system
|
lump |
LUMP |
100,000.00 |
100,000.00 |
98,500.00 |
98,500.00 |
500,000.00 |
500,000.00 |
|
|
| S-113 |
dynamic message signs
|
6   |
EACH |
14,000.00 |
84,000.00 |
13,500.00 |
81,000.00 |
20,000.00 |
120,000.00 |
|
|
| S-114 |
motorist assistance patrol
|
1,082   |
HOUR |
75.00 |
81,150.00 |
100.00 |
108,200.00 |
85.00 |
91,970.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
9,170,466.30 |
|
12,123,885.10 |
|
12,221,478.55 |
|
|
|