Letting of 4/27/2005 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 858-08-0009
Parish: VERNON
Routes: LA 1212
Description: JCT. US 171 - JCT. LA 8
Type Const: grading, in-place cement stabilized bc, cold planing acp, drain struct, superpave
acp ovly, lime trmt, pvmt patch, and related work
 
RankLicenseBidderAmount
112312 GILCHRIST CONSTRUCTION CO. LLC $641,398.22
205789 D & J CONSTRUCTION CO., INC. $1,055,386.48
334356 PRAIRIE CONTRACTORS INC. $1,112,180.16
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
D & J CONSTRUCTION CO., INC.
- 3 -
PRAIRIE CONTRACTORS INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-I removal of rip rap and unfinished concrete revetment lump      LUMP 1,500.00 1,500.00 10,000.00 10,000.00 5,000.00 5,000.00    
202-02-J removal of surfacing 635.0    SQYD 9.00 5,715.00 15.00 9,525.00 20.00 12,700.00    
203-08 borrow (vehicular measurement) 100      CUYD 26.00 2,600.00 90.00 9,000.00 18.00 1,800.00    
203-08-A borrow (vehicular meas.)(selected soils) 3,055      CUYD 20.00 61,100.00 17.00 51,935.00 18.00 54,990.00    
303-01-B in-place cement stabilized base course (8 1/2" thick) 19,685      SQYD 7.50 147,637.50 15.00 295,275.00 16.50 324,802.50    
303-02 removal of existing patches 500      SQYD 20.00 10,000.00 25.00 12,500.00 10.00 5,000.00    
304-01 lime 68.28   TON 140.00 9,559.20 175.00 11,949.00 228.00 15,567.84    
304-02-B lime treatment (type b) (8 1/2" thick) 10,200      SQYD 1.50 15,300.00 11.00 112,200.00 13.00 132,600.00    
401-02 aggregate surface course (adjusted vehicular
measurement)
136      CUYD 33.00 4,488.00 100.00 13,600.00 80.00 10,880.00    
502-01 superpave asphaltic concrete 3,307.0    TON 56.00 185,192.00 60.00 198,420.00 58.00 191,806.00    
502-01-A superpave asphaltic concrete, paved drives and
turnouts
60.0    TON 100.00 6,000.00 255.00 15,300.00 100.00 6,000.00    
509-01 cold planing asphaltic pavement 22,755      SQYD 1.75 39,821.25 1.75 39,821.25 3.00 68,265.00    
602-05-G full depth patching of jointed concrete pavement (8"
thick)
88.5    SQYD 92.00 8,142.00 150.00 13,275.00 150.00 13,275.00    
701-01-I cross drain pipe (24" rcp/pcp) 56      LNFT 90.00 5,040.00 110.00 6,160.00 110.00 6,160.00    
701-15 concrete collar 1      EACH 1,100.00 1,100.00 1,000.00 1,000.00 1,300.00 1,300.00    
702-03-A catch basins (cb-01) 1      EACH 3,000.00 3,000.00 3,500.00 3,500.00 5,000.00 5,000.00    
702-04-A adjusting manholes 3      EACH 500.00 1,500.00 1,000.00 3,000.00 4,000.00 12,000.00    
712-04 flexible revetment 23      SQYD 50.00 1,150.00 90.00 2,070.00 200.00 4,600.00    
713-01 temporary signs & barricades lump      LUMP 5,000.00 5,000.00 50,000.00 50,000.00 25,000.00 25,000.00    
713-03-E temporary pavement markings (24" width) 158      LNFT 0.70 110.60 4.00 632.00 1.00 158.00    
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
4.111  MILE 320.00 1,315.52 176.00 723.53 400.00 1,644.40    
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
1.132  MILE 350.00 396.20 1,000.00 1,132.00 1.00 1.13    
713-05-A temporary pavement markings (solid line)(4" width) 14.695  MILE 470.00 6,906.65 560.00 8,229.20 1.00 14.69    
717-01 seeding 27      LB 9.00 243.00 10.00 270.00 20.00 540.00    
718-01 fertilizer 600      LB 1.00 600.00 0.40 240.00 1.00 600.00    
720-01-A erosion control system, slope protection (type a) 120      SQYD 2.00 240.00 2.00 240.00 5.00 600.00    
722-01 project site laboratory 1      EACH 4,000.00 4,000.00 5,000.00 5,000.00 6,000.00 6,000.00    
724-01-A pavement patching (6" minimum thickness) 100      SQYD 80.00 8,000.00 75.00 7,500.00 50.00 5,000.00    
724-01-B pavement patching (12" minimum thickness) 500      SQYD 100.00 50,000.00 90.00 45,000.00 100.00 50,000.00    
726-01 bedding material 6.8    CUYD 90.00 612.00 125.00 850.00 200.00 1,360.00    
727-01 mobilization lump      LUMP 15,000.00 15,000.00 90,000.00 90,000.00 86,000.00 86,000.00    
731-02 reflectorized raised pavement markers 276      EACH 6.00 1,656.00 6.50 1,794.00 10.00 2,760.00    
732-01-C plastic pavement striping (8" width) 50      LNFT 1.20 60.00 13.00 650.00 5.00 250.00    
732-01-E plastic pavement striping (24" width) 79      LNFT 3.50 276.50 12.00 948.00 6.00 474.00    
732-02-A plastic pavement striping (solid line) (4" width) 7.348  MILE 2,000.00 14,696.00 2,500.00 18,370.00 2,200.00 16,165.60    
732-03-A plastic pavement striping (broken line)(4" width) 0.566  MILE 800.00 452.80 1,250.00 707.50 1,000.00 566.00    
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 180.00 360.00 525.00 1,050.00 500.00 1,000.00    
740-01 construction layout lump      LUMP 10,000.00 10,000.00 5,000.00 5,000.00 4,000.00 4,000.00    
S-001 cleaning grated cross drains 84      LNFT 17.00 1,428.00 30.00 2,520.00 75.00 6,300.00    
S-002 slotted drain 40      LNFT 280.00 11,200.00 150.00 6,000.00 800.00 32,000.00    
                       
 CONTRACTOR TOTAL       641,398.22   1,055,386.48   1,112,180.16    