| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - GUINN BROTHERS, LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
lump |
10,000.00 |
10,000.00 |
8,000.00 |
8,000.00 |
|
|
|
|
| 202-02-A-01 |
removal of bridge (station 10+381.8, 7.50 m x 38.80 m,
timber trestle) |
1   |
ea |
50,000.00 |
50,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
1,130.4 |
sq m |
5.20 |
5,878.08 |
6.00 |
6,782.40 |
|
|
|
|
| 202-02-H |
removal of guard rail
|
120   |
ln m |
6.00 |
720.00 |
20.00 |
2,400.00 |
|
|
|
|
| 203-01 |
general excavation
|
354   |
cu m |
15.00 |
5,310.00 |
15.00 |
5,310.00 |
|
|
|
|
| 203-04 |
embankment
|
324   |
cu m |
28.00 |
9,072.00 |
30.00 |
9,720.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
1,300   |
ln m |
4.00 |
5,200.00 |
3.50 |
4,550.00 |
|
|
|
|
| 302-02-B |
class ii base course (220 mm thick)
|
1,426.9 |
sq m |
23.00 |
32,818.70 |
28.00 |
39,953.20 |
|
|
|
|
| 305-01 |
subgrade layer (300 mm thick)
|
326   |
sq m |
41.00 |
13,366.00 |
35.00 |
11,410.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
150.0 |
cu m |
35.00 |
5,250.00 |
10.00 |
1,500.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
362.7 |
Mg |
120.00 |
43,524.00 |
175.00 |
63,472.50 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
49.54 |
ln m |
65.00 |
3,220.10 |
62.00 |
3,071.48 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
30.48 |
ln m |
210.00 |
6,400.80 |
220.00 |
6,705.60 |
|
|
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
4   |
ea |
2,200.00 |
8,800.00 |
2,500.00 |
10,000.00 |
|
|
|
|
| 711-02-B |
riprap (5 kg)
|
359   |
cu m |
95.00 |
34,105.00 |
55.00 |
19,745.00 |
|
|
|
|
| 711-02-D |
riprap (25 kg)
|
258   |
cu m |
145.00 |
37,410.00 |
60.00 |
15,480.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
267   |
sq m |
3.00 |
801.00 |
5.00 |
1,335.00 |
|
|
|
|
| 712-03 |
stone revetment
|
310   |
sq m |
55.00 |
17,050.00 |
60.00 |
18,600.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
lump |
8,000.00 |
8,000.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
lump |
75,000.00 |
75,000.00 |
135,000.00 |
135,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
ea |
80.00 |
320.00 |
100.00 |
400.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
20   |
ea |
6.00 |
120.00 |
10.00 |
200.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line)(100 mm width)
|
0.840 |
km |
1,500.00 |
1,260.00 |
2,000.00 |
1,680.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
1.0 |
hctr |
2,800.00 |
2,800.00 |
4,000.00 |
4,000.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
lump |
12,000.00 |
12,000.00 |
13,000.00 |
13,000.00 |
|
|
|
|
| 804-01-C |
precast concrete piles (400 mm)
|
600.0 |
ln m |
130.00 |
78,000.00 |
155.00 |
93,000.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
ea |
100.00 |
100.00 |
1.00 |
1.00 |
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
43.04 |
cu m |
900.00 |
38,736.00 |
850.00 |
36,584.00 |
|
|
|
|
| 805-03 |
class aa concrete
|
193.05 |
cu m |
700.00 |
135,135.00 |
900.00 |
173,745.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
23,426   |
kg |
2.50 |
58,565.00 |
1.75 |
40,995.50 |
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
108.00 |
ln m |
185.00 |
19,980.00 |
180.00 |
19,440.00 |
|
|
|
|
| 813-01 |
concrete approach slabs
|
223.20 |
sq m |
175.00 |
39,060.00 |
225.00 |
50,220.00 |
|
|
|
|
| S-001 |
geotextile fabric (type s)
|
1,039   |
sq m |
7.00 |
7,273.00 |
5.00 |
5,195.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
765,274.68 |
|
828,495.68 |
|
|
|
|
|