| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
- 2 - BARRIERE CONSTRUCTION CO., LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
215   |
SQYD |
10.00 |
2,150.00 |
14.00 |
3,010.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
245.6 |
SQYD |
10.00 |
2,456.00 |
15.00 |
3,684.00 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
830   |
CUYD |
10.00 |
8,300.00 |
15.00 |
12,450.00 |
|
|
|
|
| 302-02-D-01 |
class ii base course (12" thick) (crushed stone or
recycled pccp only) |
1,047.1 |
SQYD |
25.00 |
26,177.50 |
18.00 |
18,847.80 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
634   |
CUYD |
25.00 |
15,850.00 |
50.00 |
31,700.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
1,842.3 |
TON |
50.00 |
92,115.00 |
73.00 |
134,487.90 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
418.9 |
TON |
50.00 |
20,945.00 |
73.00 |
30,579.70 |
|
|
|
|
| 509-01-A |
cold planing asphaltic pavement (1" avg. depth)
|
444   |
SQYD |
10.00 |
4,440.00 |
8.00 |
3,552.00 |
|
|
|
|
| 509-01-B |
cold planing asphaltic pavement (2" deep)
|
1,877   |
SQYD |
10.00 |
18,770.00 |
2.50 |
4,692.50 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
444   |
LNFT |
85.00 |
37,740.00 |
69.00 |
30,636.00 |
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
48   |
LNFT |
95.00 |
4,560.00 |
130.00 |
6,240.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
2   |
EACH |
2,500.00 |
5,000.00 |
3,500.00 |
7,000.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
1   |
EACH |
1,500.00 |
1,500.00 |
2,300.00 |
2,300.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
141.0 |
SQYD |
50.00 |
7,050.00 |
63.00 |
8,883.00 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
90.0 |
LNFT |
32.00 |
2,880.00 |
66.00 |
5,940.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
30,000.00 |
30,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
400   |
LNFT |
0.20 |
80.00 |
0.10 |
40.00 |
|
|
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
580   |
LNFT |
0.60 |
348.00 |
0.10 |
58.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
2.460 |
MILE |
400.00 |
984.00 |
100.00 |
246.00 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
0.382 |
MILE |
100.00 |
38.20 |
100.00 |
38.20 |
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
4   |
EACH |
25.00 |
100.00 |
50.00 |
200.00 |
|
|
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
2   |
EACH |
25.00 |
50.00 |
50.00 |
100.00 |
|
|
|
|
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
1   |
EACH |
100.00 |
100.00 |
50.00 |
50.00 |
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
100   |
SQYD |
75.00 |
7,500.00 |
89.00 |
8,900.00 |
|
|
|
|
| 726-01 |
bedding material
|
182.2 |
CUYD |
FREE |
FREE |
35.00 |
6,377.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
30,000.00 |
30,000.00 |
27,000.00 |
27,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
336   |
EACH |
6.00 |
2,016.00 |
6.00 |
2,016.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
200   |
LNFT |
1.50 |
300.00 |
1.00 |
200.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
290   |
LNFT |
3.50 |
1,015.00 |
3.00 |
870.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
0.191 |
MILE |
2,500.00 |
477.50 |
2,500.00 |
477.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.090 |
MILE |
1,000.00 |
90.00 |
900.00 |
81.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
150.00 |
600.00 |
150.00 |
600.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
200.00 |
400.00 |
150.00 |
300.00 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
1   |
EACH |
600.00 |
600.00 |
550.00 |
550.00 |
|
|
|
|
| 735-01 |
mailboxes
|
2   |
EACH |
2.00 |
4.00 |
1.00 |
2.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
2   |
EACH |
175.00 |
350.00 |
100.00 |
200.00 |
|
|
|
|
| 736-09 |
loop detector
|
542   |
LNFT |
14.00 |
7,588.00 |
14.00 |
7,588.00 |
|
|
|
|
| 736-10 |
underground junction box
|
1   |
EACH |
450.00 |
450.00 |
450.00 |
450.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
9,500.00 |
9,500.00 |
|
|
|
|
| S-001 |
removal of grassed area (12" avg thickness)
|
704.8 |
SQYD |
6.00 |
4,228.80 |
7.00 |
4,933.60 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
347,253.00 |
|
384,780.20 |
|
|
|
|
|