| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - HARD ROCK CONSTRUCTION CO. |
- 3 - GRADY CRAWFORD CONST. CO., INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
11   |
SQYD |
25.00 |
275.00 |
20.00 |
220.00 |
75.00 |
825.00 |
|
|
| 202-02-E |
removal of concrete curbs
|
2,016.0 |
LNFT |
FREE |
FREE |
4.00 |
8,064.00 |
5.50 |
11,088.00 |
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
20.0 |
LNFT |
10.00 |
200.00 |
15.00 |
300.00 |
75.00 |
1,500.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
29,338.0 |
SQYD |
3.00 |
88,014.00 |
3.25 |
95,348.50 |
6.50 |
190,697.00 |
|
|
| 202-02-H |
removal of guard rail
|
738   |
LNFT |
4.00 |
2,952.00 |
4.00 |
2,952.00 |
5.50 |
4,059.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
1,279   |
CUYD |
20.00 |
25,580.00 |
30.00 |
38,370.00 |
19.87 |
25,413.73 |
|
|
| 302-02-A-01 |
class ii base course (6" thick)(stone only)
|
30,600.1 |
SQYD |
8.00 |
244,800.80 |
8.00 |
244,800.80 |
15.30 |
468,181.53 |
|
|
| 502-01 |
superpave asphaltic concrete
|
5,904.2 |
TON |
55.00 |
324,731.00 |
70.00 |
413,294.00 |
79.35 |
468,498.27 |
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives & turnouts
|
286.6 |
TON |
55.00 |
15,763.00 |
100.00 |
28,660.00 |
120.95 |
34,664.27 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
31,843   |
LNFT |
1.00 |
31,843.00 |
1.75 |
55,725.25 |
1.85 |
58,909.55 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
45,566   |
LNFT |
1.20 |
54,679.20 |
1.75 |
79,740.50 |
1.99 |
90,676.34 |
|
|
| 602-03 |
cleaning and sealing random cracks
|
5,590   |
LNFT |
3.00 |
16,770.00 |
2.50 |
13,975.00 |
4.00 |
22,360.00 |
|
|
| 602-05-G-01 |
full depth patching of jointed conc pvmt (8" thick)
(16.0 sq yds & under) |
1,200.0 |
SQYD |
130.00 |
156,000.00 |
115.00 |
138,000.00 |
258.65 |
310,380.00 |
|
|
| 602-05-G-02 |
full depth patching of jointed conc pvmt (8" thick)
(16.1-48.0 sq yds) |
2,500.0 |
SQYD |
128.00 |
320,000.00 |
115.00 |
287,500.00 |
247.49 |
618,725.00 |
|
|
| 602-05-G-03 |
full depth patching of jointed conc pvmt (8" thick)
(48.1 sq yds & over) |
3,000.0 |
SQYD |
126.00 |
378,000.00 |
115.00 |
345,000.00 |
237.97 |
713,910.00 |
|
|
| 602-10 |
longitudinal shoulder joints
|
49,320   |
LNFT |
1.50 |
73,980.00 |
1.60 |
78,912.00 |
2.20 |
108,504.00 |
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
30   |
LNFT |
120.00 |
3,600.00 |
300.00 |
9,000.00 |
95.00 |
2,850.00 |
|
|
| 701-15 |
concrete collar
|
3   |
EACH |
600.00 |
1,800.00 |
200.00 |
600.00 |
1,500.00 |
4,500.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
3   |
EACH |
3,500.00 |
10,500.00 |
4,000.00 |
12,000.00 |
3,000.00 |
9,000.00 |
|
|
| 702-04-A |
adjusting manholes
|
2   |
EACH |
500.00 |
1,000.00 |
200.00 |
400.00 |
1,500.00 |
3,000.00 |
|
|
| 702-04-B |
adjusting catch basins
|
2   |
EACH |
1,000.00 |
2,000.00 |
700.00 |
1,400.00 |
2,000.00 |
4,000.00 |
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
894.0 |
LNFT |
34.00 |
30,396.00 |
25.00 |
22,350.00 |
35.00 |
31,290.00 |
|
|
| 704-03 |
blocked out guard rail
|
900.0 |
LNFT |
19.00 |
17,100.00 |
14.50 |
13,050.00 |
20.00 |
18,000.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
45.00 |
4,500.00 |
36.50 |
3,650.00 |
49.50 |
4,950.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
2   |
EACH |
2,200.00 |
4,400.00 |
1,550.00 |
3,100.00 |
2,100.00 |
4,200.00 |
|
|
| 704-11-C |
guard rail end treatment (bi-directional)
|
2   |
EACH |
6,200.00 |
12,400.00 |
4,600.00 |
9,200.00 |
6,200.00 |
12,400.00 |
|
|
| 706-01-A |
concrete walk (4" thick)
|
10.7 |
SQYD |
60.00 |
642.00 |
60.00 |
642.00 |
100.00 |
1,070.00 |
|
|
| 707-01 |
concrete curb
|
2,300.0 |
LNFT |
6.00 |
13,800.00 |
20.00 |
46,000.00 |
15.00 |
34,500.00 |
|
|
| 707-03 |
combination concrete curb & gutter
|
20.0 |
LNFT |
30.00 |
600.00 |
100.00 |
2,000.00 |
75.00 |
1,500.00 |
|
|
| 710-01 |
flowable fill
|
150   |
CUYD |
100.00 |
15,000.00 |
50.00 |
7,500.00 |
175.00 |
26,250.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
80,000.00 |
80,000.00 |
50,000.00 |
50,000.00 |
165,000.00 |
165,000.00 |
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
1,630   |
LNFT |
0.10 |
163.00 |
0.40 |
652.00 |
0.52 |
847.60 |
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
773   |
LNFT |
0.30 |
231.90 |
1.20 |
927.60 |
1.54 |
1,190.42 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
8.320 |
MILE |
5.00 |
41.60 |
300.00 |
2,496.00 |
1,000.00 |
8,320.00 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
8.976 |
MILE |
5.00 |
44.88 |
250.00 |
2,244.00 |
300.00 |
2,692.80 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
21.683 |
MILE |
10.00 |
216.83 |
475.00 |
10,299.42 |
583.00 |
12,641.18 |
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
38   |
EACH |
5.00 |
190.00 |
50.00 |
1,900.00 |
62.00 |
2,356.00 |
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
18   |
EACH |
5.00 |
90.00 |
50.00 |
900.00 |
62.00 |
1,116.00 |
|
|
| 724-01-A |
pavement patching (6" minimum thickness)
|
137   |
SQYD |
45.00 |
6,165.00 |
65.00 |
8,905.00 |
125.00 |
17,125.00 |
|
|
| 726-01 |
bedding material
|
25.1 |
CUYD |
40.00 |
1,004.00 |
40.00 |
1,004.00 |
75.00 |
1,882.50 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
220,000.00 |
220,000.00 |
249,000.00 |
249,000.00 |
150,000.00 |
150,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
10   |
EACH |
60.00 |
600.00 |
45.00 |
450.00 |
60.00 |
600.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
80.00 |
320.00 |
65.00 |
260.00 |
90.00 |
360.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
3,292   |
EACH |
5.00 |
16,460.00 |
5.00 |
16,460.00 |
5.90 |
19,422.80 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
815   |
LNFT |
1.00 |
815.00 |
1.00 |
815.00 |
1.11 |
904.65 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
432   |
LNFT |
3.00 |
1,296.00 |
3.00 |
1,296.00 |
3.32 |
1,434.24 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
10.842 |
MILE |
2,200.00 |
23,852.40 |
2,000.00 |
21,684.00 |
2,434.00 |
26,389.42 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.488 |
MILE |
650.00 |
2,917.20 |
600.00 |
2,692.80 |
700.00 |
3,141.60 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
19   |
EACH |
145.00 |
2,755.00 |
125.00 |
2,375.00 |
153.00 |
2,907.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
9   |
EACH |
150.00 |
1,350.00 |
135.00 |
1,215.00 |
165.00 |
1,485.00 |
|
|
| 732-05 |
removal of existing markings
|
2.080 |
MILE |
5,000.00 |
10,400.00 |
4,200.00 |
8,736.00 |
5,160.00 |
10,732.80 |
|
|
| 735-01 |
mailboxes
|
50   |
EACH |
2.00 |
100.00 |
1.00 |
50.00 |
2.00 |
100.00 |
|
|
| 735-02 |
mailbox supports (single)
|
40   |
EACH |
130.00 |
5,200.00 |
120.00 |
4,800.00 |
160.00 |
6,400.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
200.00 |
400.00 |
140.00 |
280.00 |
200.00 |
400.00 |
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
250.00 |
500.00 |
220.00 |
440.00 |
300.00 |
600.00 |
|
|
| 736-09 |
loop detector
|
909   |
LNFT |
14.00 |
12,726.00 |
12.00 |
10,908.00 |
15.00 |
13,635.00 |
|
|
| 736-10 |
underground junction box
|
7   |
EACH |
350.00 |
2,450.00 |
315.00 |
2,205.00 |
380.00 |
2,660.00 |
|
|
| 739-01 |
hydro-seeding
|
3.40 |
ACRE |
900.00 |
3,060.00 |
800.00 |
2,720.00 |
1,100.00 |
3,740.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
30,000.00 |
30,000.00 |
|
|
| S-001 |
dynamic message sign unit
|
2   |
EACH |
9,000.00 |
18,000.00 |
8,000.00 |
16,000.00 |
21,000.00 |
42,000.00 |
|
|
| S-002 |
cleaning concrete curbs
|
5,491   |
LNFT |
1.50 |
8,236.50 |
1.00 |
5,491.00 |
5.80 |
31,847.80 |
|
|
| S-003 |
cleaning and inspecting catch basins and manholes
|
82   |
EACH |
150.00 |
12,300.00 |
500.00 |
41,000.00 |
400.00 |
32,800.00 |
|
|
| S-004 |
repairing catch basins and manholes
|
12   |
EACH |
2,000.00 |
24,000.00 |
3,000.00 |
36,000.00 |
3,000.00 |
36,000.00 |
|
|
| S-005 |
patching catch basins and manholes
|
140   |
SQFT |
35.00 |
4,900.00 |
25.00 |
3,500.00 |
175.00 |
24,500.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,322,111.31 |
|
2,494,459.87 |
|
3,941,133.50 |
|
|
|