February 06, 2014 Error processing SSI file

Letting of 3/30/2005 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 852-04-0010
Parish: ST TAMMANY
Routes: LA 1077
Description: JUNCTION ROUTE US 190 - TANGIPAHOA PARISH LINE
Type Const: grading, cement treated base course, superpave asphaltic concrete pavement, and
related work.
 
RankLicenseBidderAmount
122040 COVINGTON PAVING CO. $609,494.04
206276 BARRIERE CONSTRUCTION CO., LLC. $614,699.40
306487 HUEY STOCKSTILL, INC. $698,612.45
402179 BOH BROS. CONSTRUCTION CO., LLC. $772,314.60
512487 DIAMOND B CONSTRUCTION CO., L.L.C. $773,471.53
 
Item Number Item Description Quantity Unit of Measure - 1 -
COVINGTON PAVING CO.
- 2 -
BARRIERE CONSTRUCTION CO., LLC.
- 3 -
HUEY STOCKSTILL, INC.
- 4 -
BOH BROS. CONSTRUCTION CO., LLC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
203-08 borrow (vehicular measurement) 652      CUYD 11.00 7,172.00 7.00 4,564.00 8.00 5,216.00 15.00 9,780.00
203-08-A borrow (vehicular meas.)(selected soils) 1,956      CUYD 9.00 17,604.00 7.00 13,692.00 8.00 15,648.00 6.00 11,736.00
303-02-A removal of existing patches (12" depth) 750      SQYD FREE FREE 1.00 750.00 5.00 3,750.00 5.00 3,750.00
502-01 superpave asphaltic concrete 7,084.0    TON 47.00 332,948.00 44.00 311,696.00 45.00 318,780.00 55.00 389,620.00
502-01-A superpave asphaltic concrete, paved drives and
turnouts
732.4    TON FREE FREE 1.00 732.40 80.00 58,592.00 75.00 54,930.00
713-01 temporary signs & barricades lump      LUMP 20,000.00 20,000.00 5,000.00 5,000.00 30,000.00 30,000.00 19,000.00 19,000.00
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
5.000  MILE 250.00 1,250.00 130.00 650.00 400.00 2,000.00 10.00 50.00
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
5.000  MILE 240.00 1,200.00 230.00 1,150.00 300.00 1,500.00 10.00 50.00
713-05-A temporary pavement markings (solid line)(4" width) 10.320  MILE 490.00 5,056.80 450.00 4,644.00 500.00 5,160.00 20.00 206.40
717-01 seeding 73      LB 9.00 657.00 10.00 730.00 8.00 584.00 10.00 730.00
718-01 fertilizer 2,424      LB 0.38 921.12 0.40 969.60 0.35 848.40 0.50 1,212.00
721-01 asphalt mulch 587      GAL 3.00 1,761.00 2.70 1,584.90 2.50 1,467.50 2.60 1,526.20
722-01 project site laboratory 1      EACH 1,000.00 1,000.00 500.00 500.00 2,200.00 2,200.00 3,000.00 3,000.00
727-01 mobilization lump      LUMP 23,000.00 23,000.00 45,000.00 45,000.00 47,000.00 47,000.00 75,000.00 75,000.00
731-02 reflectorized raised pavement markers 330      EACH 5.60 1,848.00 5.30 1,749.00 6.00 1,980.00 5.00 1,650.00
732-02-A plastic pavement striping (solid line) (4" width) 5.160  MILE 2,244.00 11,579.04 2,200.00 11,352.00 3,000.00 15,480.00 1,700.00 8,772.00
732-03-A plastic pavement striping (broken line)(4" width) 2.500  MILE 728.20 1,820.50 700.00 1,750.00 1,000.00 2,500.00 700.00 1,750.00
735-01 mailboxes 47      EACH 10.00 470.00 1.00 47.00 5.00 235.00 1.00 47.00
735-02 mailbox supports (single) 47      EACH 115.00 5,405.00 10.00 470.00 110.00 5,170.00 110.00 5,170.00
740-01 construction layout lump      LUMP 2,000.00 2,000.00 6,000.00 6,000.00 10,000.00 10,000.00 1,000.00 1,000.00
S-001 cement treated base course (12 inch depth) 36,667      SQYD 4.74 173,801.58 5.50 201,668.50 4.65 170,501.55 5.00 183,335.00
                       
 CONTRACTOR TOTAL       609,494.04   614,699.40   698,612.45   772,314.60
 
Item Number Item Description Quantity Unit of Measure - 5 -
DIAMOND B CONSTRUCTION CO., L.L.C.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
203-08 borrow (vehicular measurement) 652      CUYD 11.38 7,419.76            
203-08-A borrow (vehicular meas.)(selected soils) 1,956      CUYD 15.17 29,672.52            
303-02-A removal of existing patches (12" depth) 750      SQYD 36.92 27,690.00            
502-01 superpave asphaltic concrete 7,084.0    TON 44.96 318,496.64            
502-01-A superpave asphaltic concrete, paved drives and
turnouts
732.4    TON 106.29 77,846.79            
713-01 temporary signs & barricades lump      LUMP 7,500.00 7,500.00            
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
5.000  MILE 152.00 760.00            
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
5.000  MILE 345.00 1,725.00            
713-05-A temporary pavement markings (solid line)(4" width) 10.320  MILE 545.00 5,624.40            
717-01 seeding 73      LB 9.19 670.87            
718-01 fertilizer 2,424      LB 0.40 969.60            
721-01 asphalt mulch 587      GAL 2.87 1,684.69            
722-01 project site laboratory 1      EACH 4,800.00 4,800.00            
727-01 mobilization lump      LUMP 34,045.00 34,045.00            
731-02 reflectorized raised pavement markers 330      EACH 5.75 1,897.50            
732-02-A plastic pavement striping (solid line) (4" width) 5.160  MILE 2,069.00 10,676.04            
732-03-A plastic pavement striping (broken line)(4" width) 2.500  MILE 776.00 1,940.00            
735-01 mailboxes 47      EACH 13.00 611.00            
735-02 mailbox supports (single) 47      EACH 159.00 7,473.00            
740-01 construction layout lump      LUMP 6,100.00 6,100.00            
S-001 cement treated base course (12 inch depth) 36,667      SQYD 6.16 225,868.72            
                       
 CONTRACTOR TOTAL       773,471.53            