| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BOH BROS. CONSTRUCTION CO., LLC. |
- 2 - BARRIERE CONSTRUCTION CO., LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
3,404   |
LNFT |
5.00 |
17,020.00 |
5.00 |
17,020.00 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
1,200   |
CUYD |
7.00 |
8,400.00 |
25.00 |
30,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
7,789.0 |
TON |
60.00 |
467,340.00 |
63.00 |
490,707.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
33,621   |
SQYD |
2.50 |
84,052.50 |
3.50 |
117,673.50 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,266   |
CUYD |
10.00 |
- 12,660.00 |
10.00 |
- 12,660.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
2   |
EACH |
500.00 |
1,000.00 |
500.00 |
1,000.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
2   |
EACH |
1,000.00 |
2,000.00 |
500.00 |
1,000.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
37.5 |
LNFT |
47.00 |
1,762.50 |
44.00 |
1,650.00 |
|
|
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
62.5 |
LNFT |
47.00 |
2,937.50 |
44.00 |
2,750.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
2,275.0 |
LNFT |
20.00 |
45,500.00 |
20.00 |
45,500.00 |
|
|
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
25.0 |
LNFT |
78.00 |
1,950.00 |
75.00 |
1,875.00 |
|
|
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
50.0 |
LNFT |
38.00 |
1,900.00 |
36.00 |
1,800.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
45.00 |
9,000.00 |
42.00 |
8,400.00 |
|
|
|
|
| 704-10 |
guard rail anchor block
|
1   |
EACH |
1,650.00 |
1,650.00 |
1,600.00 |
1,600.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
10   |
EACH |
2,100.00 |
21,000.00 |
1,900.00 |
19,000.00 |
|
|
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
200.0 |
SQYD |
70.00 |
14,000.00 |
40.00 |
8,000.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
200,000.00 |
200,000.00 |
135,000.00 |
135,000.00 |
|
|
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
1,000   |
LNFT |
0.20 |
200.00 |
0.10 |
100.00 |
|
|
|
|
| 713-04-A-01 |
temporary pavement markings (broken line)(4" width)(4'
length) (type 1 removable) |
3.096 |
MILE |
100.00 |
309.60 |
200.00 |
619.20 |
|
|
|
|
| 713-04-B-01 |
temporary pavement markings (broken line)(4" width)
(10' length) (type i removable) |
3.096 |
MILE |
200.00 |
619.20 |
1,000.00 |
3,096.00 |
|
|
|
|
| 713-05-A-01 |
temporary pavement markings (solid line)(4" width)
(type 1 removable) |
4.644 |
MILE |
500.00 |
2,322.00 |
2,000.00 |
9,288.00 |
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
50.00 |
100.00 |
1.00 |
2.00 |
|
|
|
|
| 713-06-B |
temporary pavement legends and symbols (double arrow)
|
2   |
EACH |
50.00 |
100.00 |
1.00 |
2.00 |
|
|
|
|
| 724-01-A |
pavement patching (6" minimum thickness)
|
200   |
SQYD |
60.00 |
12,000.00 |
30.00 |
6,000.00 |
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
500   |
SQYD |
120.00 |
60,000.00 |
50.00 |
25,000.00 |
|
|
|
|
| 724-03 |
pavement joint repair
|
100.0 |
TON |
200.00 |
20,000.00 |
100.00 |
10,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
115,000.00 |
115,000.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
10   |
EACH |
70.00 |
700.00 |
70.00 |
700.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
250   |
EACH |
5.60 |
1,400.00 |
5.30 |
1,325.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
500   |
LNFT |
3.50 |
1,750.00 |
3.40 |
1,700.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line)(4" width)
|
2.322 |
MILE |
2,300.00 |
5,340.60 |
2,200.00 |
5,108.40 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4"width)
|
1.548 |
MILE |
800.00 |
1,238.40 |
760.00 |
1,176.48 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
150.00 |
300.00 |
130.00 |
260.00 |
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
200.00 |
400.00 |
200.00 |
400.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
30,000.00 |
30,000.00 |
|
|
|
|
| S-001 |
rumble strips (ground-in)
|
1.9 |
MILE |
5,000.00 |
9,500.00 |
2,000.00 |
3,800.00 |
|
|
|
|
| S-002 |
variable message sign unit
|
4   |
EACH |
4,500.00 |
18,000.00 |
6,000.00 |
24,000.00 |
|
|
|
|
| S-003 |
barrier wall transitions
|
72   |
LNFT |
275.00 |
19,800.00 |
400.00 |
28,800.00 |
|
|
|
|
| S-004 |
barrier wall (54" tall)
|
139   |
LNFT |
250.00 |
34,750.00 |
300.00 |
41,700.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,175,682.30 |
|
1,213,392.58 |
|
|
|
|
|