| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BOH BROS. CONSTRUCTION CO., LLC. |
- 2 - T. L. WALLACE CONSTRUCTION, INC. |
- 3 - GULF SOUTH PILING & CONST., INC. |
- 4 - SHAVERS-WHITTLE CONSTRUCTION INC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
37,300.00 |
37,300.00 |
505,000.00 |
505,000.00 |
100,000.00 |
100,000.00 |
50,000.00 |
50,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,500.00 |
5,500.00 |
5,000.00 |
5,000.00 |
20,000.00 |
20,000.00 |
34,000.00 |
34,000.00 |
| 202-02-A-01 |
removal of bridges, (58' x 24' concrete bridge)
|
1   |
EACH |
7,200.00 |
7,200.00 |
5,600.00 |
5,600.00 |
10,000.00 |
10,000.00 |
7,500.00 |
7,500.00 |
| 202-02-A-02 |
removal of bridges, (135' x 24' concrete bridge)
|
1   |
EACH |
13,200.00 |
13,200.00 |
11,500.00 |
11,500.00 |
12,000.00 |
12,000.00 |
13,000.00 |
13,000.00 |
| 202-02-A-03 |
removal of bridges, (324' x 32' concrete bridge)
|
1   |
EACH |
33,000.00 |
33,000.00 |
21,500.00 |
21,500.00 |
20,000.00 |
20,000.00 |
32,000.00 |
32,000.00 |
| 202-02-A-04 |
removal of bridges, (230' x 24' concrete bridge)
|
1   |
EACH |
16,500.00 |
16,500.00 |
21,500.00 |
21,500.00 |
15,000.00 |
15,000.00 |
16,500.00 |
16,500.00 |
| 202-02-A-05 |
removal of bridges, (230' x 24' concrete bridge)
|
1   |
EACH |
16,500.00 |
16,500.00 |
21,500.00 |
21,500.00 |
15,000.00 |
15,000.00 |
16,500.00 |
16,500.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
8,714.8 |
SQYD |
4.20 |
36,602.16 |
2.00 |
17,429.60 |
5.00 |
43,574.00 |
4.25 |
37,037.90 |
| 203-01 |
general excavation
|
14,177   |
CUYD |
3.00 |
42,531.00 |
2.95 |
41,822.15 |
3.00 |
42,531.00 |
3.50 |
49,619.50 |
| 203-02 |
drainage excavation
|
965   |
CUYD |
9.00 |
8,685.00 |
7.00 |
6,755.00 |
10.00 |
9,650.00 |
11.50 |
11,097.50 |
| 203-04 |
embankment
|
81,908   |
CUYD |
8.40 |
688,027.20 |
7.40 |
606,119.20 |
9.50 |
778,126.00 |
9.50 |
778,126.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
16   |
EACH |
100.00 |
1,600.00 |
75.00 |
1,200.00 |
100.00 |
1,600.00 |
110.00 |
1,760.00 |
| 204-05-B |
temporary sediment check dams (stone)
|
15   |
EACH |
500.00 |
7,500.00 |
300.00 |
4,500.00 |
300.00 |
4,500.00 |
325.00 |
4,875.00 |
| 204-06 |
temporary silt fencing
|
3,580   |
LNFT |
1.50 |
5,370.00 |
2.50 |
8,950.00 |
1.50 |
5,370.00 |
1.50 |
5,370.00 |
| 303-01-D |
in-place cement stabilized base couse (12" thick)
|
10,493   |
SQYD |
7.70 |
80,796.10 |
11.10 |
116,472.30 |
10.00 |
104,930.00 |
12.50 |
131,162.50 |
| 401-01 |
aggregate surface course (net section)
|
3,623.1 |
CUYD |
50.60 |
183,328.86 |
45.00 |
163,039.50 |
62.00 |
224,632.20 |
65.00 |
235,501.50 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
38.0 |
CUYD |
38.00 |
1,444.00 |
30.00 |
1,140.00 |
40.00 |
1,520.00 |
35.00 |
1,330.00 |
| 502-01 |
superpave asphaltic concrete
|
4,918.3 |
TON |
69.00 |
339,362.70 |
62.37 |
306,754.37 |
62.00 |
304,934.60 |
72.00 |
354,117.60 |
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
413.2 |
TON |
171.00 |
70,657.20 |
155.17 |
64,116.24 |
160.00 |
66,112.00 |
175.00 |
72,310.00 |
| 509-01 |
cold planing asphaltic pavement
|
2,851   |
SQYD |
7.50 |
21,382.50 |
5.68 |
16,193.68 |
6.00 |
17,106.00 |
7.00 |
19,957.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 60   |
CUYD |
1.00 |
- 60.00 |
0.10 |
- 6.00 |
1.00 |
- 60.00 |
FREE |
FREE |
| 701-04-J |
storm drain pipe arch (60" equiv. rcpa)
|
106   |
LNFT |
178.00 |
18,868.00 |
250.00 |
26,500.00 |
200.00 |
21,200.00 |
225.00 |
23,850.00 |
| 701-04-L |
storm drain pipe arch (72" equiv. rcpa)
|
110   |
LNFT |
237.00 |
26,070.00 |
350.00 |
38,500.00 |
250.00 |
27,500.00 |
275.00 |
30,250.00 |
| 701-06-D |
side drain pipe arch (24" equiv.)
|
68   |
LNFT |
67.00 |
4,556.00 |
100.00 |
6,800.00 |
50.00 |
3,400.00 |
60.00 |
4,080.00 |
| 702-08-B |
side drain safety end (type 2)
|
4   |
EACH |
3,100.00 |
12,400.00 |
2,500.00 |
10,000.00 |
4,000.00 |
16,000.00 |
3,000.00 |
12,000.00 |
| 704-03 |
blocked out guard rail
|
237.5 |
LNFT |
20.00 |
4,750.00 |
16.50 |
3,918.75 |
18.00 |
4,275.00 |
18.00 |
4,275.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
42.00 |
4,200.00 |
40.00 |
4,000.00 |
40.00 |
4,000.00 |
42.00 |
4,200.00 |
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
1,900.00 |
7,600.00 |
2,000.00 |
8,000.00 |
1,800.00 |
7,200.00 |
2,200.00 |
8,800.00 |
| 705-01 |
barbed wire fence
|
3,706   |
LNFT |
6.00 |
22,236.00 |
5.50 |
20,383.00 |
6.00 |
22,236.00 |
6.50 |
24,089.00 |
| 708-01 |
right-of-way monument
|
30   |
EACH |
335.00 |
10,050.00 |
50.00 |
1,500.00 |
125.00 |
3,750.00 |
100.00 |
3,000.00 |
| 708-02 |
right-of-way monument witness post
|
30   |
EACH |
60.00 |
1,800.00 |
50.00 |
1,500.00 |
150.00 |
4,500.00 |
125.00 |
3,750.00 |
| 711-01-D |
riprap (55 lb, 18 in thick)
|
1,104   |
SQYD |
29.00 |
32,016.00 |
46.00 |
50,784.00 |
50.00 |
55,200.00 |
35.00 |
38,640.00 |
| 711-04 |
geotextile fabric
|
1,104   |
SQYD |
1.80 |
1,987.20 |
1.75 |
1,932.00 |
2.00 |
2,208.00 |
2.00 |
2,208.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
22,000.00 |
22,000.00 |
26,000.00 |
26,000.00 |
50,000.00 |
50,000.00 |
45,000.00 |
45,000.00 |
| 713-03-A |
temporary pavement markings (4" width)
|
5,038   |
LNFT |
0.35 |
1,763.30 |
1.00 |
5,038.00 |
0.30 |
1,511.40 |
0.35 |
1,763.30 |
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
0.447 |
MILE |
2,200.00 |
983.40 |
250.00 |
111.75 |
300.00 |
134.10 |
1,500.00 |
670.50 |
| 715-01 |
topsoil
|
77   |
CUYD |
44.00 |
3,388.00 |
30.00 |
2,310.00 |
30.00 |
2,310.00 |
37.50 |
2,887.50 |
| 716-01-A |
mulch (vegetative)
|
7.29 |
ACRE |
750.00 |
5,467.50 |
650.00 |
4,738.50 |
700.00 |
5,103.00 |
850.00 |
6,196.50 |
| 717-01 |
seeding
|
313   |
LB |
8.00 |
2,504.00 |
6.00 |
1,878.00 |
7.00 |
2,191.00 |
8.50 |
2,660.50 |
| 718-01 |
fertilizer
|
10,406   |
LB |
0.25 |
2,601.50 |
0.30 |
3,121.80 |
0.30 |
3,121.80 |
0.25 |
2,601.50 |
| 720-01-B |
erosion control sysyem, slope protection (type b)
|
35   |
SQYD |
385.00 |
13,475.00 |
2.00 |
70.00 |
3.50 |
122.50 |
2.50 |
87.50 |
| 727-01 |
mobilization
|
lump |
LUMP |
540,000.00 |
540,000.00 |
120,000.00 |
120,000.00 |
525,000.00 |
525,000.00 |
380,000.00 |
380,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
72.00 |
288.00 |
70.00 |
280.00 |
65.00 |
260.00 |
80.00 |
320.00 |
| 731-01 |
nonreflectorized raised pavement markers
|
330   |
EACH |
10.00 |
3,300.00 |
12.00 |
3,960.00 |
9.00 |
2,970.00 |
11.00 |
3,630.00 |
| 731-02 |
reflectorized raised pavement markers
|
135   |
EACH |
5.40 |
729.00 |
8.00 |
1,080.00 |
5.00 |
675.00 |
6.00 |
810.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
36   |
LNFT |
3.20 |
115.20 |
3.00 |
108.00 |
3.00 |
108.00 |
3.50 |
126.00 |
| 732-02-A |
plastic pavement striping (solid line)(4" width)
|
3.355 |
MILE |
2,310.00 |
7,750.05 |
5,000.00 |
16,775.00 |
2,100.00 |
7,045.50 |
2,500.00 |
8,387.50 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.739 |
MILE |
700.00 |
517.30 |
2,000.00 |
1,478.00 |
630.00 |
465.57 |
750.00 |
554.25 |
| 740-01 |
construction layout
|
lump |
LUMP |
325,000.00 |
325,000.00 |
60,000.00 |
60,000.00 |
150,000.00 |
150,000.00 |
35,000.00 |
35,000.00 |
| 804-01-B |
precast concrete piles (14")
|
172   |
LNFT |
30.00 |
5,160.00 |
65.00 |
11,180.00 |
60.00 |
10,320.00 |
36.50 |
6,278.00 |
| 804-01-F |
precast concrete piles (24")
|
3,056   |
LNFT |
63.00 |
192,528.00 |
110.00 |
336,160.00 |
90.00 |
275,040.00 |
85.00 |
259,760.00 |
| 804-01-G |
precast concrete piles (30")
|
5,260   |
LNFT |
91.00 |
478,660.00 |
155.00 |
815,300.00 |
100.00 |
526,000.00 |
135.00 |
710,100.00 |
| 804-12 |
loading permanent piles
|
2   |
EACH |
20,000.00 |
40,000.00 |
30,000.00 |
60,000.00 |
500.00 |
1,000.00 |
1.00 |
2.00 |
| 805-01-F |
class a concrete (bents)
|
405.03 |
CUYD |
500.00 |
202,515.00 |
475.00 |
192,389.25 |
500.00 |
202,515.00 |
650.00 |
263,269.50 |
| 805-03 |
class aa concrete
|
1,771.93 |
CUYD |
365.00 |
646,754.45 |
400.00 |
708,772.00 |
425.00 |
753,070.25 |
435.00 |
770,789.55 |
| 805-08-C |
precast-prestressed concrete girder (type iii)
|
8,940.0 |
LNFT |
80.00 |
715,200.00 |
65.00 |
581,100.00 |
65.00 |
581,100.00 |
80.00 |
715,200.00 |
| 805-11 |
strip seal joints
|
320.00 |
LNFT |
100.00 |
32,000.00 |
100.00 |
32,000.00 |
120.00 |
38,400.00 |
125.00 |
40,000.00 |
| 806-01 |
deformed reinforcing steel
|
495,704   |
LB |
0.70 |
346,992.80 |
0.60 |
297,422.40 |
0.75 |
371,778.00 |
0.65 |
322,207.60 |
| 807-06 |
structural metalwork
|
lump |
LUMP |
7,300.00 |
7,300.00 |
15,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
18,500.00 |
18,500.00 |
| 810-01 |
concrete railing (barrier)
|
3,000.00 |
LNFT |
25.00 |
75,000.00 |
30.50 |
91,500.00 |
42.00 |
126,000.00 |
40.00 |
120,000.00 |
| 813-01 |
concrete approach slabs
|
359.82 |
SQYD |
125.00 |
44,977.50 |
165.00 |
59,370.30 |
145.00 |
52,173.90 |
135.00 |
48,575.70 |
| S-101 |
retroreflective sheeting panels
|
lump |
LUMP |
3,000.00 |
3,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
650.00 |
650.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
5,482,929.92 |
|
5,568,046.79 |
|
5,672,409.82 |
|
5,796,933.90 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - JAMES CONSTRUCTION GROUP LLC |
- 6 - KOSTMAYER CONSTRUCTION, LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
200,000.00 |
200,000.00 |
85,000.00 |
85,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
35,000.00 |
35,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| 202-02-A-01 |
removal of bridges, (58' x 24' concrete bridge)
|
1   |
EACH |
8,000.00 |
8,000.00 |
30,000.00 |
30,000.00 |
|
|
|
|
| 202-02-A-02 |
removal of bridges, (135' x 24' concrete bridge)
|
1   |
EACH |
12,500.00 |
12,500.00 |
48,000.00 |
48,000.00 |
|
|
|
|
| 202-02-A-03 |
removal of bridges, (324' x 32' concrete bridge)
|
1   |
EACH |
65,000.00 |
65,000.00 |
90,000.00 |
90,000.00 |
|
|
|
|
| 202-02-A-04 |
removal of bridges, (230' x 24' concrete bridge)
|
1   |
EACH |
16,000.00 |
16,000.00 |
60,000.00 |
60,000.00 |
|
|
|
|
| 202-02-A-05 |
removal of bridges, (230' x 24' concrete bridge)
|
1   |
EACH |
16,000.00 |
16,000.00 |
60,000.00 |
60,000.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
8,714.8 |
SQYD |
4.00 |
34,859.20 |
7.00 |
61,003.60 |
|
|
|
|
| 203-01 |
general excavation
|
14,177   |
CUYD |
3.00 |
42,531.00 |
6.00 |
85,062.00 |
|
|
|
|
| 203-02 |
drainage excavation
|
965   |
CUYD |
7.50 |
7,237.50 |
10.00 |
9,650.00 |
|
|
|
|
| 203-04 |
embankment
|
81,908   |
CUYD |
9.25 |
757,649.00 |
9.00 |
737,172.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
16   |
EACH |
100.00 |
1,600.00 |
290.00 |
4,640.00 |
|
|
|
|
| 204-05-B |
temporary sediment check dams (stone)
|
15   |
EACH |
275.00 |
4,125.00 |
900.00 |
13,500.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
3,580   |
LNFT |
1.20 |
4,296.00 |
1.45 |
5,191.00 |
|
|
|
|
| 303-01-D |
in-place cement stabilized base couse (12" thick)
|
10,493   |
SQYD |
8.00 |
83,944.00 |
36.00 |
377,748.00 |
|
|
|
|
| 401-01 |
aggregate surface course (net section)
|
3,623.1 |
CUYD |
50.00 |
181,155.00 |
75.00 |
271,732.50 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
38.0 |
CUYD |
55.00 |
2,090.00 |
70.00 |
2,660.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
4,918.3 |
TON |
63.00 |
309,852.90 |
100.00 |
491,830.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
413.2 |
TON |
160.00 |
66,112.00 |
110.00 |
45,452.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
2,851   |
SQYD |
6.00 |
17,106.00 |
27.00 |
76,977.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 60   |
CUYD |
1.00 |
- 60.00 |
1.00 |
- 60.00 |
|
|
|
|
| 701-04-J |
storm drain pipe arch (60" equiv. rcpa)
|
106   |
LNFT |
200.00 |
21,200.00 |
225.00 |
23,850.00 |
|
|
|
|
| 701-04-L |
storm drain pipe arch (72" equiv. rcpa)
|
110   |
LNFT |
240.00 |
26,400.00 |
285.00 |
31,350.00 |
|
|
|
|
| 701-06-D |
side drain pipe arch (24" equiv.)
|
68   |
LNFT |
50.00 |
3,400.00 |
57.00 |
3,876.00 |
|
|
|
|
| 702-08-B |
side drain safety end (type 2)
|
4   |
EACH |
4,000.00 |
16,000.00 |
2,900.00 |
11,600.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
237.5 |
LNFT |
18.00 |
4,275.00 |
20.00 |
4,750.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
38.00 |
3,800.00 |
48.00 |
4,800.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,000.00 |
8,000.00 |
2,400.00 |
9,600.00 |
|
|
|
|
| 705-01 |
barbed wire fence
|
3,706   |
LNFT |
6.00 |
22,236.00 |
7.00 |
25,942.00 |
|
|
|
|
| 708-01 |
right-of-way monument
|
30   |
EACH |
200.00 |
6,000.00 |
100.00 |
3,000.00 |
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
30   |
EACH |
200.00 |
6,000.00 |
100.00 |
3,000.00 |
|
|
|
|
| 711-01-D |
riprap (55 lb, 18 in thick)
|
1,104   |
SQYD |
41.00 |
45,264.00 |
60.00 |
66,240.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
1,104   |
SQYD |
2.00 |
2,208.00 |
1.45 |
1,600.80 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
30,000.00 |
30,000.00 |
21,000.00 |
21,000.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (4" width)
|
5,038   |
LNFT |
0.30 |
1,511.40 |
1.20 |
6,045.60 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
0.447 |
MILE |
500.00 |
223.50 |
6,000.00 |
2,682.00 |
|
|
|
|
| 715-01 |
topsoil
|
77   |
CUYD |
30.00 |
2,310.00 |
13.00 |
1,001.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
7.29 |
ACRE |
680.00 |
4,957.20 |
1,200.00 |
8,748.00 |
|
|
|
|
| 717-01 |
seeding
|
313   |
LB |
7.00 |
2,191.00 |
10.00 |
3,130.00 |
|
|
|
|
| 718-01 |
fertilizer
|
10,406   |
LB |
0.20 |
2,081.20 |
0.40 |
4,162.40 |
|
|
|
|
| 720-01-B |
erosion control sysyem, slope protection (type b)
|
35   |
SQYD |
10.00 |
350.00 |
12.00 |
420.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
575,000.00 |
575,000.00 |
300,000.00 |
300,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
65.00 |
260.00 |
80.00 |
320.00 |
|
|
|
|
| 731-01 |
nonreflectorized raised pavement markers
|
330   |
EACH |
9.00 |
2,970.00 |
14.00 |
4,620.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
135   |
EACH |
5.00 |
675.00 |
10.00 |
1,350.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
36   |
LNFT |
3.00 |
108.00 |
3.50 |
126.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line)(4" width)
|
3.355 |
MILE |
2,100.00 |
7,045.50 |
6,000.00 |
20,130.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.739 |
MILE |
630.00 |
465.57 |
2,400.00 |
1,773.60 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
62,000.00 |
62,000.00 |
|
|
|
|
| 804-01-B |
precast concrete piles (14")
|
172   |
LNFT |
50.00 |
8,600.00 |
36.00 |
6,192.00 |
|
|
|
|
| 804-01-F |
precast concrete piles (24")
|
3,056   |
LNFT |
90.00 |
275,040.00 |
110.00 |
336,160.00 |
|
|
|
|
| 804-01-G |
precast concrete piles (30")
|
5,260   |
LNFT |
95.00 |
499,700.00 |
180.00 |
946,800.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
2   |
EACH |
2,500.00 |
5,000.00 |
17,000.00 |
34,000.00 |
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
405.03 |
CUYD |
600.00 |
243,018.00 |
650.00 |
263,269.50 |
|
|
|
|
| 805-03 |
class aa concrete
|
1,771.93 |
CUYD |
525.00 |
930,263.25 |
600.00 |
1,063,158.00 |
|
|
|
|
| 805-08-C |
precast-prestressed concrete girder (type iii)
|
8,940.0 |
LNFT |
75.00 |
670,500.00 |
90.00 |
804,600.00 |
|
|
|
|
| 805-11 |
strip seal joints
|
320.00 |
LNFT |
130.00 |
41,600.00 |
105.00 |
33,600.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
495,704   |
LB |
0.65 |
322,207.60 |
0.75 |
371,778.00 |
|
|
|
|
| 807-06 |
structural metalwork
|
lump |
LUMP |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
3,000.00 |
LNFT |
32.00 |
96,000.00 |
170.00 |
510,000.00 |
|
|
|
|
| 813-01 |
concrete approach slabs
|
359.82 |
SQYD |
135.00 |
48,575.70 |
130.00 |
46,776.60 |
|
|
|
|
| S-101 |
retroreflective sheeting panels
|
lump |
LUMP |
1,000.00 |
1,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
5,911,433.52 |
|
7,634,009.60 |
|
|
|
|
|