| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - MCMANUS CONSTRUCTION, INC. |
- 2 - BESSETTE DEVELOPMENT CORP. |
- 3 - JAMES CONSTRUCTION GROUP LLC |
- 4 - CIRCLE, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
100,000.00 |
100,000.00 |
4,900.00 |
4,900.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
25,000.00 |
25,000.00 |
25,000.00 |
25,000.00 |
5,000.00 |
5,000.00 |
8,250.00 |
8,250.00 |
| 202-02-D |
removal of concrete walks & drives
|
1,206   |
SQYD |
6.50 |
7,839.00 |
15.00 |
18,090.00 |
4.00 |
4,824.00 |
9.50 |
11,457.00 |
| 203-03 |
muck excavation
|
500   |
CUYD |
15.00 |
7,500.00 |
10.00 |
5,000.00 |
5.00 |
2,500.00 |
11.50 |
5,750.00 |
| 203-06 |
excavation & embankment
|
lump |
LUMP |
145,000.00 |
145,000.00 |
63,500.00 |
63,500.00 |
362,000.00 |
362,000.00 |
68,000.00 |
68,000.00 |
| 204-02 |
temporary hay or straw bales
|
1,100   |
EACH |
10.00 |
11,000.00 |
10.00 |
11,000.00 |
5.00 |
5,500.00 |
8.00 |
8,800.00 |
| 204-04 |
temporary sediment basins
|
2   |
EACH |
600.00 |
1,200.00 |
100.00 |
200.00 |
200.00 |
400.00 |
472.00 |
944.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
8   |
EACH |
350.00 |
2,800.00 |
150.00 |
1,200.00 |
150.00 |
1,200.00 |
81.00 |
648.00 |
| 204-06 |
temporary silt fencing
|
6,000   |
LNFT |
1.50 |
9,000.00 |
1.75 |
10,500.00 |
1.00 |
6,000.00 |
2.50 |
15,000.00 |
| 302-02 |
class ii base course (4" thick)
|
4,758.2 |
SQYD |
6.50 |
30,928.30 |
7.50 |
35,686.50 |
9.00 |
42,823.80 |
11.00 |
52,340.20 |
| 302-02-C |
class ii base course (10" thick)
|
1,268.4 |
SQYD |
14.30 |
18,138.12 |
14.50 |
18,391.80 |
17.00 |
21,562.80 |
1,750.00 |
2,219,700.00 |
| 302-02-E |
class ii base course (8" thick)
|
19,352.7 |
SQYD |
11.50 |
222,556.05 |
12.50 |
241,908.75 |
14.00 |
270,937.80 |
14.20 |
274,808.34 |
| 304-05 |
lime treatment (type e)
|
1,324.40 |
TON |
155.00 |
205,282.00 |
200.00 |
264,880.00 |
1.00 |
1,324.40 |
142.00 |
188,064.80 |
| 305-01 |
subgrade layer (12" thick)
|
19,353   |
SQYD |
6.20 |
119,988.60 |
8.00 |
154,824.00 |
7.00 |
135,471.00 |
3.40 |
65,800.20 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
131   |
CUYD |
55.00 |
7,205.00 |
50.00 |
6,550.00 |
10.00 |
1,310.00 |
40.00 |
5,240.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
2,512.1 |
CUYD |
55.00 |
138,165.50 |
50.00 |
125,605.00 |
45.00 |
113,044.50 |
45.00 |
113,044.50 |
| 502-01 |
superpave asphaltic concrete
|
786.6 |
TON |
116.00 |
91,245.60 |
60.00 |
47,196.00 |
130.00 |
102,258.00 |
118.00 |
92,818.80 |
| 509-01 |
cold planing asphaltic pavement
|
8,791   |
SQYD |
4.00 |
35,164.00 |
3.00 |
26,373.00 |
6.00 |
52,746.00 |
4.00 |
35,164.00 |
| 601-01-G |
portland cement concrete pavement (8" thick)
|
16,357.4 |
SQYD |
39.00 |
637,938.60 |
44.00 |
719,725.60 |
53.00 |
866,942.20 |
52.00 |
850,584.80 |
| 701-04-A |
storm drain pipe arch (15" equiv. rcpa)
|
105   |
LNFT |
60.00 |
6,300.00 |
40.00 |
4,200.00 |
65.00 |
6,825.00 |
60.00 |
6,300.00 |
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
82   |
LNFT |
65.00 |
5,330.00 |
50.00 |
4,100.00 |
80.00 |
6,560.00 |
74.00 |
6,068.00 |
| 701-04-D |
storm drain pipe arch (24" equiv. rcpa)
|
68   |
LNFT |
70.00 |
4,760.00 |
60.00 |
4,080.00 |
90.00 |
6,120.00 |
123.00 |
8,364.00 |
| 701-04-H |
storm drain pipe arch (48" equiv. rcpa)
|
60   |
LNFT |
160.00 |
9,600.00 |
150.00 |
9,000.00 |
200.00 |
12,000.00 |
186.00 |
11,160.00 |
| 701-07-C |
yard drain pipe (8")
|
280   |
LNFT |
24.00 |
6,720.00 |
15.00 |
4,200.00 |
30.00 |
8,400.00 |
16.50 |
4,620.00 |
| 702-02-B-01 |
manholes (r-cb-11 special detail)
|
19   |
EACH |
1,700.00 |
32,300.00 |
3,000.00 |
57,000.00 |
2,200.00 |
41,800.00 |
2,150.00 |
40,850.00 |
| 702-03-A |
catch basins (cb-01)
|
4   |
EACH |
2,300.00 |
9,200.00 |
2,500.00 |
10,000.00 |
3,000.00 |
12,000.00 |
3,600.00 |
14,400.00 |
| 702-03-D |
catch basins (cb-07)
|
4   |
EACH |
3,000.00 |
12,000.00 |
3,000.00 |
12,000.00 |
5,000.00 |
20,000.00 |
3,900.00 |
15,600.00 |
| 702-03-D-01 |
catch basins (cb-07) special detail
|
39   |
EACH |
1,900.00 |
74,100.00 |
4,000.00 |
156,000.00 |
2,500.00 |
97,500.00 |
2,000.00 |
78,000.00 |
| 702-03-F-01 |
catch basins (cb-08) special detail
|
2   |
EACH |
3,000.00 |
6,000.00 |
8,000.00 |
16,000.00 |
4,000.00 |
8,000.00 |
1,770.00 |
3,540.00 |
| 702-04-B |
adjusting catch basins
|
3   |
EACH |
1,000.00 |
3,000.00 |
1,500.00 |
4,500.00 |
1,500.00 |
4,500.00 |
2,000.00 |
6,000.00 |
| 703-02 |
shoulder outlet underdrains
|
2   |
EACH |
300.00 |
600.00 |
500.00 |
1,000.00 |
200.00 |
400.00 |
1,170.00 |
2,340.00 |
| 703-03 |
perforated pipe underdrains
|
7,516   |
LNFT |
6.00 |
45,096.00 |
12.00 |
90,192.00 |
10.00 |
75,160.00 |
5.50 |
41,338.00 |
| 706-01-A |
concrete walk (4" thick)
|
831.3 |
SQYD |
32.00 |
26,601.60 |
40.00 |
33,252.00 |
55.00 |
45,721.50 |
51.50 |
42,811.95 |
| 706-02-C |
concrete drive (6" thick)
|
991.9 |
SQYD |
34.00 |
33,724.60 |
45.00 |
44,635.50 |
65.00 |
64,473.50 |
55.00 |
54,554.50 |
| 707-01-A |
concrete curb (integral)
|
6,647.00 |
LNFT |
14.00 |
93,058.00 |
15.00 |
99,705.00 |
16.00 |
106,352.00 |
10.00 |
66,470.00 |
| 708-01 |
right-of-way monument
|
4   |
EACH |
200.00 |
800.00 |
150.00 |
600.00 |
200.00 |
800.00 |
711.00 |
2,844.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
60,000.00 |
60,000.00 |
50,000.00 |
50,000.00 |
30,000.00 |
30,000.00 |
17,700.00 |
17,700.00 |
| 713-05-A-01 |
temporary pavement markings (solid line)(4" width)
(type 1 removable) |
3.182 |
MILE |
600.00 |
1,909.20 |
13,000.00 |
41,366.00 |
10,000.00 |
31,820.00 |
13,900.00 |
44,229.80 |
| 715-01 |
topsoil
|
1,270   |
CUYD |
15.00 |
19,050.00 |
20.00 |
25,400.00 |
20.00 |
25,400.00 |
15.00 |
19,050.00 |
| 716-01-A |
mulch (vegetative)
|
0.50 |
ACRE |
2,400.00 |
1,200.00 |
1,000.00 |
500.00 |
630.00 |
315.00 |
700.00 |
350.00 |
| 717-01 |
seeding
|
15   |
LB |
40.00 |
600.00 |
38.00 |
570.00 |
15.00 |
225.00 |
10.00 |
150.00 |
| 718-01 |
fertilizer
|
500   |
LB |
0.60 |
300.00 |
1.00 |
500.00 |
1.00 |
500.00 |
0.50 |
250.00 |
| 722-01 |
project site laboratory
|
1   |
EACH |
10,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
6,000.00 |
6,000.00 |
19,400.00 |
19,400.00 |
| 726-01 |
bedding material
|
26.7 |
CUYD |
70.00 |
1,869.00 |
50.00 |
1,335.00 |
75.00 |
2,002.50 |
25.00 |
667.50 |
| 727-01 |
mobilization
|
lump |
LUMP |
200,000.00 |
200,000.00 |
50,000.00 |
50,000.00 |
300,000.00 |
300,000.00 |
27,500.00 |
27,500.00 |
| 729-01 |
sign (type a)
|
10.0 |
SQFT |
320.00 |
3,200.00 |
30.00 |
300.00 |
100.00 |
1,000.00 |
57.50 |
575.00 |
| 731-02 |
reflectorized raised pavement markers
|
419   |
EACH |
5.40 |
2,262.60 |
5.50 |
2,304.50 |
6.00 |
2,514.00 |
6.00 |
2,514.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
276   |
LNFT |
1.00 |
276.00 |
1.00 |
276.00 |
1.00 |
276.00 |
1.00 |
276.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
166   |
LNFT |
3.00 |
498.00 |
3.50 |
581.00 |
3.00 |
498.00 |
3.25 |
539.50 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.954 |
MILE |
2,200.00 |
6,498.80 |
2,300.00 |
6,794.20 |
2,000.00 |
5,908.00 |
2,300.00 |
6,794.20 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.975 |
MILE |
800.00 |
780.00 |
800.00 |
780.00 |
1,000.00 |
975.00 |
881.00 |
858.97 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
23   |
EACH |
158.00 |
3,634.00 |
200.00 |
4,600.00 |
125.00 |
2,875.00 |
148.00 |
3,404.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
3   |
EACH |
158.00 |
474.00 |
250.00 |
750.00 |
150.00 |
450.00 |
172.00 |
516.00 |
| 735-01 |
mailboxes
|
5   |
EACH |
25.00 |
125.00 |
100.00 |
500.00 |
50.00 |
250.00 |
54.50 |
272.50 |
| 735-02 |
mailbox supports (single)
|
5   |
EACH |
130.00 |
650.00 |
100.00 |
500.00 |
300.00 |
1,500.00 |
246.00 |
1,230.00 |
| 736-01 |
trenching and backfilling
|
490   |
LNFT |
3.00 |
1,470.00 |
6.60 |
3,234.00 |
5.00 |
2,450.00 |
4.75 |
2,327.50 |
| 736-03 |
jacked or bored conduit (3" p.e.c., sch 80)
|
390   |
LNFT |
36.00 |
14,040.00 |
14.30 |
5,577.00 |
17.00 |
6,630.00 |
19.00 |
7,410.00 |
| 736-04-A |
signal support (mast arm - 35')
|
1   |
EACH |
15,000.00 |
15,000.00 |
9,550.00 |
9,550.00 |
8,300.00 |
8,300.00 |
9,450.00 |
9,450.00 |
| 736-04-B |
signal support (mast arm 40')
|
1   |
EACH |
16,000.00 |
16,000.00 |
10,400.00 |
10,400.00 |
9,100.00 |
9,100.00 |
10,000.00 |
10,000.00 |
| 736-04-C |
signal support (mast arm - 50')
|
2   |
EACH |
17,000.00 |
34,000.00 |
12,000.00 |
24,000.00 |
11,100.00 |
22,200.00 |
12,650.00 |
25,300.00 |
| 736-05-A |
signal heads (retrofitted with led's)
|
8   |
EACH |
1,200.00 |
9,600.00 |
1,500.00 |
12,000.00 |
1,100.00 |
8,800.00 |
147.50 |
1,180.00 |
| 736-05-B |
signal head (5-section, ryg-y-g, led)
|
2   |
EACH |
1,925.00 |
3,850.00 |
1,815.00 |
3,630.00 |
1,600.00 |
3,200.00 |
1,800.00 |
3,600.00 |
| 736-06 |
signal service
|
1   |
EACH |
1,650.00 |
1,650.00 |
1,550.00 |
1,550.00 |
1,000.00 |
1,000.00 |
1,100.00 |
1,100.00 |
| 736-08 |
signal controller
|
1   |
EACH |
18,200.00 |
18,200.00 |
18,800.00 |
18,800.00 |
16,000.00 |
16,000.00 |
18,300.00 |
18,300.00 |
| 736-09 |
loop detector
|
756   |
LNFT |
10.50 |
7,938.00 |
14.85 |
11,226.60 |
16.00 |
12,096.00 |
18.00 |
13,608.00 |
| 736-10 |
underground junction box
|
11   |
EACH |
550.00 |
6,050.00 |
1,015.00 |
11,165.00 |
700.00 |
7,700.00 |
750.00 |
8,250.00 |
| 736-11-A |
conduit (1/2" p.e.c.)
|
49   |
LNFT |
3.20 |
156.80 |
1.35 |
66.15 |
3.00 |
147.00 |
2.35 |
115.15 |
| 736-11-B |
conduit (1" p.e.c.)
|
380   |
LNFT |
4.60 |
1,748.00 |
2.75 |
1,045.00 |
3.00 |
1,140.00 |
2.35 |
893.00 |
| 736-11-C |
conduit (2" p.e.c.)
|
57   |
LNFT |
7.00 |
399.00 |
5.00 |
285.00 |
4.00 |
228.00 |
3.60 |
205.20 |
| 736-11-D |
conduit (3" p.e.c.)
|
31   |
LNFT |
23.00 |
713.00 |
13.25 |
410.75 |
7.00 |
217.00 |
7.00 |
217.00 |
| 736-12-A |
conductor 2c (loop lead-in/#16 awg, shielded)
|
1,060   |
LNFT |
1.80 |
1,908.00 |
1.10 |
1,166.00 |
2.00 |
2,120.00 |
1.20 |
1,272.00 |
| 736-12-B |
conductor 3c (power, 6 gauge/#6 awg)
|
11   |
LNFT |
1.80 |
19.80 |
8.25 |
90.75 |
5.00 |
55.00 |
3.60 |
39.60 |
| 736-12-C |
conductor 6c (signal, #14 awg)
|
355   |
LNFT |
1.80 |
639.00 |
3.55 |
1,260.25 |
3.00 |
1,065.00 |
2.35 |
834.25 |
| 736-12-D |
conductor 10c (signal,#14 awg)
|
355   |
LNFT |
2.10 |
745.50 |
4.00 |
1,420.00 |
3.00 |
1,065.00 |
2.35 |
834.25 |
| 739-01 |
hydro-seeding
|
2.09 |
ACRE |
2,400.00 |
5,016.00 |
1,800.00 |
3,762.00 |
1,300.00 |
2,717.00 |
1,770.00 |
3,699.30 |
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
40,000.00 |
40,000.00 |
20,000.00 |
20,000.00 |
127,284.35 |
127,284.35 |
| 805-01-A |
class a concrete (pipe headwalls)
|
25.12 |
CUYD |
800.00 |
20,096.00 |
750.00 |
18,840.00 |
200.00 |
5,024.00 |
600.00 |
15,072.00 |
| 806-01 |
deformed reinforcing steel
|
1,500   |
LB |
1.00 |
1,500.00 |
1.00 |
1,500.00 |
2.00 |
3,000.00 |
0.70 |
1,050.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,579,206.67 |
|
2,729,130.35 |
|
3,159,219.00 |
|
4,824,894.16 |
|