Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 047-02-0034 | |
| Parish: Washington, St. Helena, Tangipahoa | |
| Routes: LA 16 | |
| Description: LA 16 MICRO-SURFACING PROJECT | |
| Type Const: COLD PLANING ASPHALTIC PAVEMENT, MICRO-SURFACING, PERMANENT STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $2,728,376.12 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 32934 | Vance Brothers Inc | $2,565,361.25 |
| 2 | 30339 | Missouri Petroleum Products Co. LLC | $3,345,363.01 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Vance Brothers Inc |
- 2 - Missouri Petroleum Products Co. LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 509-01-00100 | Cold Planing Asphaltic Pavement | 20,277 | SQYD | 3.52 | 71,375.04 | 3.75 | 76,038.75 |
| 0002 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -563 | CUYD | 0.10 | -56.30 | 1.00 | -563.00 |
| 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 28,500.00 | 28,500.00 | 30,000.00 | 30,000.00 |
| 0004 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 300 | LNFT | 0.55 | 165.00 | 0.22 | 66.00 |
| 0005 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,360 | LNFT | 1.10 | 1,496.00 | 0.75 | 1,020.00 |
| 0006 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 33.857 | MILE | 250.00 | 8,464.25 | 500.00 | 16,928.50 |
| 0007 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 54.108 | MILE | 495.00 | 26,783.46 | 475.00 | 25,701.30 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 173.084 | MILE | 660.00 | 114,235.44 | 550.00 | 95,196.20 |
| 0009 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 28 | EACH | 55.00 | 1,540.00 | 45.00 | 1,260.00 |
| 0010 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 55.00 | 220.00 | 45.00 | 180.00 |
| 0011 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 10,627 | EACH | 0.75 | 7,970.25 | 2.50 | 26,567.50 |
| 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 38,130.00 | 38,130.00 | 275,000.00 | 275,000.00 |
| 0013 | 731-02-00100 | Reflectorized Raised Pavement Markers | 5,824 | EACH | 5.23 | 30,459.52 | 5.00 | 29,120.00 |
| 0014 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 150 | LNFT | 1.05 | 157.50 | 1.35 | 202.50 |
| 0015 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 680 | LNFT | 3.19 | 2,169.20 | 4.50 | 3,060.00 |
| 0016 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 86.542 | MILE | 2,530.00 | 218,951.26 | 2,350.00 | 203,373.70 |
| 0017 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 27.054 | MILE | 770.00 | 20,831.58 | 800.00 | 21,643.20 |
| 0018 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 14 | EACH | 165.00 | 2,310.00 | 200.00 | 2,800.00 |
| 0019 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 176.00 | 352.00 | 200.00 | 400.00 |
| 0020 | 732-05-00100 | Removal of Existing Markings | 31.461 | MILE | 2,420.00 | 76,135.62 | 3,000.00 | 94,383.00 |
| 0021 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 8,500.00 | 8,500.00 |
| 0022 | NS-500-00380 | Micro-surfacing Aggregate | 8,913 | TON | 120.00 | 1,069,560.00 | 162.00 | 1,443,906.00 |
| 0023 | NS-500-00400 | Micro-surfacing Asphalt | 303,858.7 | GAL | 2.75 | 835,611.43 | 3.26 | 990,579.36 |
| CONTRACTOR TOTAL | 2,565,361.25 | 3,345,363.01 | ||||||