| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
- 3 - D & J CONSTRUCTION CO., INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
1,550.00 |
1,550.00 |
2,000.00 |
2,000.00 |
1,200.00 |
1,200.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
4,750   |
CUYD |
42.06 |
199,785.00 |
32.00 |
152,000.00 |
30.00 |
142,500.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
13,766.4 |
TON |
42.66 |
587,274.62 |
47.00 |
647,020.80 |
50.00 |
688,320.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
1,251.5 |
TON |
68.67 |
85,940.50 |
75.00 |
93,862.50 |
95.00 |
118,892.50 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
1,865   |
SQYD |
5.33 |
9,940.45 |
5.00 |
9,325.00 |
12.50 |
23,312.50 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 84   |
CUYD |
0.10 |
- 8.40 |
1.00 |
- 84.00 |
0.01 |
- 0.84 |
|
|
| 701-02-D/E |
cross drain pipe arch (24" equiv. rcpa or 30" equiv.
cmpa) |
48   |
LNFT |
155.00 |
7,440.00 |
100.00 |
4,800.00 |
100.00 |
4,800.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
7,000.00 |
7,000.00 |
7,500.00 |
7,500.00 |
40,000.00 |
40,000.00 |
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
60   |
LNFT |
0.62 |
37.20 |
0.65 |
39.00 |
3.00 |
180.00 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
10.761 |
MILE |
592.00 |
6,370.51 |
550.00 |
5,918.55 |
195.00 |
2,098.39 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
6.842 |
MILE |
100.00 |
684.20 |
275.00 |
1,881.55 |
230.00 |
1,573.66 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
31.963 |
MILE |
200.00 |
6,392.60 |
525.00 |
16,780.57 |
1.00 |
31.96 |
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
2,000   |
SQYD |
52.25 |
104,500.00 |
80.00 |
160,000.00 |
62.00 |
124,000.00 |
|
|
| 726-01 |
bedding material
|
9.3 |
CUYD |
77.19 |
717.86 |
60.00 |
558.00 |
50.00 |
465.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
23,700.00 |
23,700.00 |
24,000.00 |
24,000.00 |
90,000.00 |
90,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
2   |
EACH |
103.00 |
206.00 |
50.00 |
100.00 |
75.00 |
150.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
985   |
EACH |
4.63 |
4,560.55 |
5.00 |
4,925.00 |
7.00 |
6,895.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
60   |
LNFT |
2.47 |
148.20 |
2.50 |
150.00 |
14.00 |
840.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
23.128 |
MILE |
1,853.00 |
42,856.18 |
1,900.00 |
43,943.20 |
2,015.00 |
46,602.92 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.630 |
MILE |
670.00 |
3,102.10 |
700.00 |
3,241.00 |
950.00 |
4,398.50 |
|
|
| 735-01 |
mailboxes
|
132   |
EACH |
12.00 |
1,584.00 |
1.00 |
132.00 |
1.00 |
132.00 |
|
|
| 735-02 |
mailbox supports (single)
|
128   |
EACH |
173.00 |
22,144.00 |
100.00 |
12,800.00 |
105.00 |
13,440.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
341.00 |
682.00 |
150.00 |
300.00 |
150.00 |
300.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
5,950.00 |
5,950.00 |
7,500.00 |
7,500.00 |
12,000.00 |
12,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,122,557.57 |
|
1,198,693.17 |
|
1,322,131.59 |
|
|
|