Letting of 7/28/2004 LA DOTD Headquarters


READV
go back
Go Back
DBE GOAL FED
Lead Project: 713-34-0100
Parish: MOREHOUSE
Routes:
Description: OFF SYSTEM BRIDGE REPLACEMENT IN MOREHOUSE PARISH
Type Const: grading, drainage structures, class ii base course, superpave asphaltic concrete
pavement, concrete slab span bridges, and related work.
 
RankLicenseBidderAmount
125747 KOSTMAYER CONSTRUCTION, LLC $1,249,547.42
214788 LOUISIANA BRIDGE, INC. $1,397,992.37
18546 C,W & W CONTRACTORS, INC. IRREGULAR
 
Item Number Item Description Quantity Unit of Measure - 1 -
KOSTMAYER CONSTRUCTION, LLC
- 2 -
LOUISIANA BRIDGE, INC.

C,W & W CONTRACTORS, INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      lump 39,000.00 39,000.00 16,780.00 16,780.00 63,000.00 63,000.00    
202-02-A-01 removal of bridge(sta.1 +176, 9.294m(l) x 7.052m(w),
2-span timber w/gravel deck)
1      ea 5,500.00 5,500.00 7,915.00 7,915.00 5,000.00 5,000.00    
202-02-A-02 removal of bridge(sta.1 +153, 9.135m(l) x 6.837m(w),
2-span timber w/asphalt deck)
1      ea 5,500.00 5,500.00 3,000.00 3,000.00 10,000.00 10,000.00    
202-02-A-03 removal of bridge(sta.1 +155,11.387m(l) x 7.277m(w),
2-span timber w/gravel deck)
1      ea 5,500.00 5,500.00 3,000.00 3,000.00 5,000.00 5,000.00    
202-02-A-04 removal of bridge(sta.1 +154,10.021m(l) x 6.819m(w),
2-span timber w/asphalt deck)
1      ea 5,500.00 5,500.00 3,000.00 3,000.00 5,000.00 5,000.00    
202-02-A-05 removal of bridge(sta.1 +163,28.118m(l) x 6.961m(w),
6-span timber w/asphalt deck)
1      ea 10,500.00 10,500.00 6,000.00 6,000.00 30,000.00 30,000.00    
203-06 excavation & embankment lump      lump 37,000.00 37,000.00 90,275.00 90,275.00 80,000.00 80,000.00    
204-02 temporary hay or straw bales 220      ea 11.00 2,420.00 7.00 1,540.00 10.00 2,200.00    
204-03 temporary slope drains 180      ln m 30.00 5,400.00 1.00 180.00 20.00 3,600.00    
204-05-A temporary sediment check dams (hay) 20      ea 120.00 2,400.00 85.25 1,705.00 140.00 2,800.00    
204-06 temporary silt fencing 210      ln m 5.00 1,050.00 4.75 997.50 8.00 1,680.00    
302-01 class ii base course 868.2    cu m 60.00 52,092.00 85.00 73,797.00 55.00 47,751.00    
401-02 aggregate surface course (adjusted vehicular
measurement)
8      cu m 60.00 480.00 100.00 800.00 70.00 560.00    
403-01 aggregate roadway surfacing (vehicular measurement) 74.5    cu m 60.00 4,470.00 100.00 7,450.00 70.00 5,215.00    
502-01-A superpave asphaltic concrete (level 1) 641.9    Mg 160.00 102,704.00 142.00 91,149.80 200.00 128,380.00    
701-05-G side drain pipe (450 mm) 12.6    ln m 130.00 1,638.00 195.00 2,457.00 95.00 1,197.00    
701-05-G-01 side drain pipe (450 mm)(erosion) 32.0    ln m 130.00 4,160.00 195.00 6,240.00 95.00 3,040.00    
701-05-I side drain pipe (600 mm) 10.6    ln m 170.00 1,802.00 220.00 2,332.00 110.00 1,166.00    
701-05-I-01 side drain pipe (600 mm)(erosion) 40.0    ln m 170.00 6,800.00 220.00 8,800.00 110.00 4,400.00    
701-05-M side drain pipe (900 mm) 12.0    ln m 210.00 2,520.00 265.00 3,180.00 175.00 2,100.00    
701-05-O-01 side drain pipe (1200 mm)(erosion) 136.0    ln m 310.00 42,160.00 322.00 43,792.00 160.00 21,760.00    
704-08-B guard rail transitions (double thrie beam) 121.92   ln m 170.00 20,726.40 156.25 19,050.00 170.00 20,726.40    
704-09 guard rail anchor sections (turndown) 60.96   ln m 112.00 6,827.52 96.50 5,882.64 105.00 6,400.80    
704-11-A guard rail end treatment (flared) 8      ea 2,400.00 19,200.00 1,875.00 15,000.00 2,100.00 16,800.00    
705-01 barbed wire fence 20      ln m 24.00 480.00 17.25 345.00 40.00 800.00    
705-06-B chain link fence (1500 mm height) 30      ln m 55.00 1,650.00 45.50 1,365.00 45.00 1,350.00    
711-01-C riprap (15 kg,360mm thick ) 453      sq m 50.00 22,650.00 60.00 27,180.00 60.00 27,180.00    
711-04 geotextile fabric 453      sq m 3.00 1,359.00 3.00 1,359.00 4.00 1,812.00    
712-04 flexible revetment 580      sq m 43.00 24,940.00 60.00 34,800.00 55.00 31,900.00    
713-01 temporary signs & barricades lump      lump 36,000.00 36,000.00 30,000.00 30,000.00 35,000.00 35,000.00    
726-01 bedding material 77.3    cu m 60.00 4,638.00 85.25 6,589.82 75.00 5,797.50    
727-01 mobilization lump      lump 100,000.00 100,000.00 75,071.50 75,071.50 120,000.00 120,000.00    
729-16-B object marker assembly (type 2) 4      ea 85.00 340.00 75.00 300.00 85.00 340.00    
729-16-C object marker assembly (type 3) 24      ea 110.00 2,640.00 75.00 1,800.00 85.00 2,040.00    
740-01 construction layout lump      lump 50,000.00 50,000.00 26,025.00 26,025.00 41,500.00 41,500.00    
804-01-B precast concrete piles (350 mm) 1,345.6    ln m 120.00 161,472.00 133.50 179,637.60 190.00 255,664.00    
804-12 loading permanent piles 4      ea 100.00 400.00 1.00 4.00 NO BID NO BID    
805-01-B class a concrete (box culvert headwalls) 23.58   cu m 1,100.00 25,938.00 1,192.00 28,107.36 190.00 4,480.20    
805-10-A bridge superstructure & substructure(7.3m clr. rdwy;
90 degree crossing)
3      span 20,000.00 60,000.00 17,631.75 52,895.25 1,000.00 3,000.00    
805-10-B bridge superstructure & substructure(8.5m clr. rdwy;
90 degree crossing)
13      span 20,000.00 260,000.00 19,045.00 247,585.00 1,000.00 13,000.00    
805-12-I reinforced concrete box culverts (1500 mm x 1500 mm) 70.00   ln m 950.00 66,500.00 3,204.00 224,280.00 18,000.00 1,260,000.00    
806-01 deformed reinforcing steel 1,418      kg 2.25 3,190.50 3.05 4,324.90 1.50 2,127.00    
S-101 concrete approach slabs (7.3 m clr. rdwy.; 90 deg.
crossing)
2      ea 7,000.00 14,000.00 6,000.00 12,000.00 4,000.00 8,000.00    
S-102 concrete approach slabs (8.5 m clr. rdwy.; 90 deg.
crossing)
4      ea 7,000.00 28,000.00 7,500.00 30,000.00 5,000.00 20,000.00    
                       
 CONTRACTOR TOTAL       1,249,547.42   1,397,992.37   IRREGULAR    