Letting of 6/30/2004 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 262-01-0032
Parish: LIVINGSTON
Routes: LA 16
Description: NORTH JCT. LA 42 - JCT. LA 447
Type Const: cold planing asphaltic concrete, pavement widening, drainage structures, superpave
asphaltic concrete pavement and relat ed work.
 
RankLicenseBidderAmount
100481 COASTAL BRIDGE CO., L.L.C. $823,013.40
200046 BARBER BROS. CONTRACTING CO., L.L.C $862,207.00
300849 F.G. SULLIVAN, JR. CONTRACTOR LLC $893,654.56
406276 BARRIERE CONSTRUCTION CO., LLC $898,233.30
512487 DIAMOND B CONSTRUCTION CO., L.L.C. $954,385.59
 
Item Number Item Description Quantity Unit of Measure - 1 -
COASTAL BRIDGE CO., L.L.C.
- 2 -
BARBER BROS. CONTRACTING CO., L.L.C
- 3 -
F.G. SULLIVAN, JR. CONTRACTOR LLC
- 4 -
BARRIERE CONSTRUCTION CO., LLC
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-H removal of guard rail 710      LNFT 7.00 4,970.00 5.00 3,550.00 3.00 2,130.00 6.00 4,260.00
203-08 borrow (vehicular measurement) 1,779      CUYD 1.00 1,779.00 12.00 21,348.00 13.00 23,127.00 14.00 24,906.00
502-01 superpave asphaltic concrete 7,758.5    TON 45.50 353,011.75 45.00 349,132.50 40.00 310,340.00 52.00 403,442.00
502-01-A superpave asphaltic concrete, paved drives and
turnouts
963.2    TON 1.00 963.20 60.00 57,792.00 70.00 67,424.00 1.00 963.20
509-01 cold planing asphaltic pavement 24,098      SQYD 5.90 142,178.20 2.00 48,196.00 1.50 36,147.00 1.80 43,376.40
509-02 contractor retained reclaimed asphaltic pavement - 669      CUYD 25.00 - 16,725.00 FREE FREE 0.10 - 66.90 6.00 - 4,014.00
701-02-E/F cross drain pipe arch (30" equiv. rcpa or 36" equiv.
cmpa)
60      LNFT 85.00 5,100.00 210.00 12,600.00 225.00 13,500.00 170.00 10,200.00
701-08 relaying pipe 4      LNFT 100.00 400.00 60.00 240.00 60.00 240.00 140.00 560.00
701-10-G reinforced concrete pipe (extension)(18") 8      LNFT 250.00 2,000.00 125.00 1,000.00 115.00 920.00 180.00 1,440.00
701-10-I reinforced concrete pipe (extension)(24") 20      LNFT 200.00 4,000.00 150.00 3,000.00 150.00 3,000.00 200.00 4,000.00
701-15 concrete collar 8      EACH 750.00 6,000.00 600.00 4,800.00 600.00 4,800.00 900.00 7,200.00
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 200.0    LNFT 30.00 6,000.00 32.00 6,400.00 30.00 6,000.00 32.00 6,400.00
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 310.0    LNFT 30.00 9,300.00 30.00 9,300.00 30.00 9,300.00 32.00 9,920.00
704-03 blocked out guard rail 175.0    LNFT 16.50 2,887.50 20.00 3,500.00 17.00 2,975.00 18.00 3,150.00
704-11-A guard rail end treatment (flared) 8      EACH 1,750.00 14,000.00 2,000.00 16,000.00 1,800.00 14,400.00 1,900.00 15,200.00
711-02-C riprap (30 lb) 10      CUYD 100.00 1,000.00 150.00 1,500.00 100.00 1,000.00 270.00 2,700.00
713-01 temporary signs & barricades lump      LUMP 8,500.00 8,500.00 20,000.00 20,000.00 49,000.00 49,000.00 14,400.00 14,400.00
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
5.544  MILE 275.00 1,524.60 400.00 2,217.60 500.00 2,772.00 130.00 720.72
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
0.900  MILE 200.00 180.00 300.00 270.00 100.00 90.00 20.00 18.00
713-05-A temporary pavement markings (solid line)(4" width) 21.228  MILE 100.00 2,122.80 300.00 6,368.40 20.00 424.56 10.00 212.28
724-01-B pavement patching (12" minimum thickness) 2,200      SQYD 25.00 55,000.00 48.00 105,600.00 50.00 110,000.00 42.00 92,400.00
724-02 pavement widening 5,336.7    SQYD 24.00 128,080.80 25.00 133,417.50 27.00 144,090.90 27.00 144,090.90
726-01 bedding material 20.1    CUYD 75.00 1,507.50 60.00 1,206.00 50.00 1,005.00 60.00 1,206.00
727-01 mobilization lump      LUMP 50,000.00 50,000.00 20,000.00 20,000.00 45,000.00 45,000.00 80,000.00 80,000.00
729-16-C object marker assembly (type 3) 20      EACH 65.00 1,300.00 72.00 1,440.00 65.00 1,300.00 70.00 1,400.00
731-02 reflectorized raised pavement markers 251      EACH 4.75 1,192.25 5.00 1,255.00 6.00 1,506.00 5.00 1,255.00
732-02-A plastic pavement striping (solid line) (4" width) 7.076  MILE 1,800.00 12,736.80 2,000.00 14,152.00 2,000.00 14,152.00 1,800.00 12,736.80
732-03-A plastic pavement striping (broken line)(4" width) 0.300  MILE 700.00 210.00 800.00 240.00 800.00 240.00 700.00 210.00
735-01 mailboxes 44      EACH 1.00 44.00 1.00 44.00 1.00 44.00 1.00 44.00
735-02 mailbox supports (single) 44      EACH 100.00 4,400.00 110.00 4,840.00 120.00 5,280.00 100.00 4,400.00
739-01 hydro-seeding 2.24   ACRE 1,000.00 2,240.00 1,200.00 2,688.00 850.00 1,904.00 900.00 2,016.00
740-01 construction layout lump      LUMP 13,500.00 13,500.00 6,000.00 6,000.00 18,000.00 18,000.00 5,000.00 5,000.00
S-001 u-channel post installation 58      ea 45.00 2,610.00 45.00 2,610.00 45.00 2,610.00 40.00 2,320.00
S-002 cleaning existing ditches 100      LNFT 10.00 1,000.00 15.00 1,500.00 10.00 1,000.00 21.00 2,100.00
                       
 CONTRACTOR TOTAL       823,013.40   862,207.00   893,654.56   898,233.30
 
Item Number Item Description Quantity Unit of Measure - 5 -
DIAMOND B CONSTRUCTION CO., L.L.C.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-H removal of guard rail 710      LNFT 3.16 2,243.60            
203-08 borrow (vehicular measurement) 1,779      CUYD 11.06 19,675.74            
502-01 superpave asphaltic concrete 7,758.5    TON 51.53 399,795.50            
502-01-A superpave asphaltic concrete, paved drives and
turnouts
963.2    TON 118.51 114,148.83            
509-01 cold planing asphaltic pavement 24,098      SQYD 1.69 40,725.62            
509-02 contractor retained reclaimed asphaltic pavement - 669      CUYD 0.10 - 66.90            
701-02-E/F cross drain pipe arch (30" equiv. rcpa or 36" equiv.
cmpa)
60      LNFT 89.50 5,370.00            
701-08 relaying pipe 4      LNFT 52.65 210.60            
701-10-G reinforced concrete pipe (extension)(18") 8      LNFT 105.30 842.40            
701-10-I reinforced concrete pipe (extension)(24") 20      LNFT 115.83 2,316.60            
701-15 concrete collar 8      EACH 685.00 5,480.00            
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 200.0    LNFT 31.59 6,318.00            
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 310.0    LNFT 31.59 9,792.90            
704-03 blocked out guard rail 175.0    LNFT 17.37 3,039.75            
704-11-A guard rail end treatment (flared) 8      EACH 1,850.00 14,800.00            
711-02-C riprap (30 lb) 10      CUYD 63.18 631.80            
713-01 temporary signs & barricades lump      LUMP 4,400.00 4,400.00            
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
5.544  MILE 369.00 2,045.73            
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
0.900  MILE 210.00 189.00            
713-05-A temporary pavement markings (solid line)(4" width) 21.228  MILE 421.00 8,936.98            
724-01-B pavement patching (12" minimum thickness) 2,200      SQYD 61.70 135,740.00            
724-02 pavement widening 5,336.7    SQYD 20.82 111,110.09            
726-01 bedding material 20.1    CUYD 36.85 740.68            
727-01 mobilization lump      LUMP 27,100.00 27,100.00            
729-16-C object marker assembly (type 3) 20      EACH 68.44 1,368.80            
731-02 reflectorized raised pavement markers 251      EACH 5.26 1,320.26            
732-02-A plastic pavement striping (solid line) (4" width) 7.076  MILE 1,792.00 12,680.19            
732-03-A plastic pavement striping (broken line)(4" width) 0.300  MILE 737.00 221.10            
735-01 mailboxes 44      EACH 12.00 528.00            
735-02 mailbox supports (single) 44      EACH 205.00 9,020.00            
739-01 hydro-seeding 2.24   ACRE 843.00 1,888.32            
740-01 construction layout lump      LUMP 6,900.00 6,900.00            
S-001 u-channel post installation 58      ea 79.00 4,582.00            
S-002 cleaning existing ditches 100      LNFT 2.90 290.00            
                       
 CONTRACTOR TOTAL       954,385.59            