| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - D & J CONSTRUCTION CO., INC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
1,000.00 |
1,000.00 |
20,000.00 |
20,000.00 |
|
|
|
|
| 202-02-H |
removal of guard rail
|
363   |
LNFT |
20.00 |
7,260.00 |
3.25 |
1,179.75 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
500   |
CUYD |
30.00 |
15,000.00 |
27.00 |
13,500.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,413   |
CUYD |
42.00 |
101,346.00 |
45.00 |
108,585.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
13,765.0 |
TON |
57.00 |
784,605.00 |
56.39 |
776,208.35 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, paved drives and
turnouts |
1,015.1 |
TON |
68.00 |
69,026.80 |
195.70 |
198,655.07 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
266   |
SQYD |
50.00 |
13,300.00 |
27.14 |
7,219.24 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
212.6 |
LNFT |
19.00 |
4,039.40 |
15.42 |
3,278.29 |
|
|
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
50.0 |
LNFT |
40.50 |
2,025.00 |
33.55 |
1,677.50 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
46.50 |
4,650.00 |
34.63 |
3,463.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,150.00 |
8,600.00 |
1,731.50 |
6,926.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
62,000.00 |
62,000.00 |
19,000.00 |
19,000.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
13.077 |
MILE |
165.00 |
2,157.70 |
380.00 |
4,969.26 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
13.002 |
MILE |
140.00 |
1,820.28 |
270.50 |
3,517.04 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
28.023 |
MILE |
1.00 |
28.02 |
541.03 |
15,161.28 |
|
|
|
|
| 724-01-C |
pavement patching (18" minimum thickness)
|
200   |
SQYD |
175.00 |
35,000.00 |
200.00 |
40,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
129,000.00 |
129,000.00 |
73,775.00 |
73,775.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
75.00 |
300.00 |
70.34 |
281.36 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
575   |
EACH |
7.50 |
4,312.50 |
4.87 |
2,800.25 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
9.341 |
MILE |
3,000.00 |
28,023.00 |
1,916.00 |
17,897.35 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.334 |
MILE |
1,200.00 |
5,200.80 |
649.00 |
2,812.76 |
|
|
|
|
| 735-01 |
mailboxes
|
55   |
EACH |
6.00 |
330.00 |
13.00 |
715.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
35   |
EACH |
145.00 |
5,075.00 |
175.00 |
6,125.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
5   |
EACH |
200.00 |
1,000.00 |
250.00 |
1,250.00 |
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
290.00 |
580.00 |
350.00 |
700.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
45,000.00 |
45,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,295,679.50 |
|
1,374,696.50 |
|
|
|
|
|