| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILBERT SOUTHERN CORP |
- 2 - APAC-TEXAS INC |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-C |
removal of portland cement concrete pavement
|
41,013   |
SQYD |
5.50 |
225,571.50 |
5.00 |
205,065.00 |
3.14 |
128,780.82 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
166,446.4 |
SQYD |
5.00 |
832,232.00 |
1.50 |
249,669.60 |
5.92 |
985,362.68 |
|
|
| 202-02-H |
removal of guard rail
|
12,438   |
LNFT |
3.00 |
37,314.00 |
3.00 |
37,314.00 |
3.03 |
37,687.14 |
|
|
| 202-02-I |
removal of existing sign
|
16   |
EACH |
80.00 |
1,280.00 |
84.00 |
1,344.00 |
80.89 |
1,294.24 |
|
|
| 202-02-J |
removal of existing sign support
|
18   |
EACH |
185.00 |
3,330.00 |
190.00 |
3,420.00 |
187.00 |
3,366.00 |
|
|
| 202-02-K |
removal of existing sign and u-channel post
|
18   |
EACH |
32.00 |
576.00 |
33.00 |
594.00 |
32.36 |
582.48 |
|
|
| 202-02-L |
removal of headwalls
|
8.0 |
EACH |
1,200.00 |
9,600.00 |
1,500.00 |
12,000.00 |
759.00 |
6,072.00 |
|
|
| 202-02-M |
removal of trees (live oaks)(18" to 30" diameter)
|
6   |
EACH |
2,100.00 |
12,600.00 |
400.00 |
2,400.00 |
1,215.00 |
7,290.00 |
|
|
| 202-02-N |
removal of trees (live oaks)(31" to 40" diameter)
|
10   |
EACH |
2,100.00 |
21,000.00 |
500.00 |
5,000.00 |
1,720.00 |
17,200.00 |
|
|
| 202-02-O |
removal of trees (live oaks)(41" to 50" diameter)
|
2   |
EACH |
2,100.00 |
4,200.00 |
600.00 |
1,200.00 |
2,125.00 |
4,250.00 |
|
|
| 202-02-P |
removal of trees (live oaks)(51" diameter and over)
|
3   |
EACH |
2,600.00 |
7,800.00 |
625.00 |
1,875.00 |
2,530.00 |
7,590.00 |
|
|
| 202-02-Q |
removal of trees (various sizes and species)
|
5   |
EACH |
2,100.00 |
10,500.00 |
500.00 |
2,500.00 |
1,010.00 |
5,050.00 |
|
|
| 202-02-R |
removal of portland cement concrete revetment
|
71   |
SQYD |
25.00 |
1,775.00 |
11.00 |
781.00 |
50.56 |
3,589.76 |
|
|
| 203-01 |
general excavation
|
169,408   |
CUYD |
7.00 |
1,185,856.00 |
3.50 |
592,928.00 |
7.00 |
1,185,856.00 |
|
|
| 203-04 |
embankment
|
378,706.0 |
CUYD |
4.00 |
1,514,824.00 |
7.00 |
2,650,942.00 |
11.25 |
4,260,442.50 |
|
|
| 204-02 |
temporary baled hay or straw
|
200   |
EACH |
3.00 |
600.00 |
4.00 |
800.00 |
5.00 |
1,000.00 |
|
|
| 302-01-A |
class ii base course (stone or recycled pccp)
|
126,095.6 |
CUYD |
57.50 |
7,250,497.00 |
49.00 |
6,178,684.40 |
47.59 |
6,000,889.60 |
|
|
| 303-01-B |
in-place cement stabilized base course (8.5" thick)
|
335,705   |
SQYD |
4.40 |
1,477,102.00 |
5.00 |
1,678,525.00 |
5.23 |
1,755,737.15 |
|
|
| 304-01 |
lime
|
643.48 |
TON |
110.00 |
70,782.80 |
115.00 |
74,000.20 |
112.00 |
72,069.76 |
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
33,571   |
SQYD |
1.50 |
50,356.50 |
1.80 |
60,427.80 |
3.67 |
123,205.57 |
|
|
| 305-01-D |
subgrade layer (12" thick)
|
302,135   |
SQYD |
6.00 |
1,812,810.00 |
6.00 |
1,812,810.00 |
5.85 |
1,767,489.75 |
|
|
| 502-01 |
superpave asphaltic concrete
|
295,841.1 |
TON |
46.00 |
13,608,690.60 |
45.00 |
13,312,849.50 |
40.86 |
12,088,067.34 |
|
|
| 508-01 |
asphaltic concrete (sma) wearing course
|
78,836.6 |
TON |
57.00 |
4,493,686.20 |
53.00 |
4,178,339.80 |
47.93 |
3,778,638.23 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
11,187   |
SQYD |
3.00 |
33,561.00 |
4.50 |
50,341.50 |
14.00 |
156,618.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 408   |
CUYD |
0.01 |
- 4.08 |
1.00 |
- 408.00 |
1.00 |
- 408.00 |
|
|
| 601-03-K |
portland cement concrete shoulder (10" thick)
|
160.0 |
SQYD |
89.00 |
14,240.00 |
70.00 |
11,200.00 |
45.00 |
7,200.00 |
|
|
| 601-04 |
portland cement concrete pavement coring
|
4   |
EACH |
200.00 |
800.00 |
105.00 |
420.00 |
101.00 |
404.00 |
|
|
| 701-10-I |
cross drain pipe (24"rcp)
|
2,760   |
LNFT |
60.00 |
165,600.00 |
85.00 |
234,600.00 |
83.00 |
229,080.00 |
|
|
| 701-10-M |
cross drain pipe (36"rcp)
|
256   |
LNFT |
84.00 |
21,504.00 |
145.00 |
37,120.00 |
142.00 |
36,352.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
4   |
EACH |
3,000.00 |
12,000.00 |
2,900.00 |
11,600.00 |
2,900.00 |
11,600.00 |
|
|
| 702-03-I |
catch basins (cb-62)
|
2   |
EACH |
3,500.00 |
7,000.00 |
4,600.00 |
9,200.00 |
4,600.00 |
9,200.00 |
|
|
| 702-04-B |
adjusting catch basins
|
2   |
EACH |
4,100.00 |
8,200.00 |
1,600.00 |
3,200.00 |
1,525.00 |
3,050.00 |
|
|
| 702-07-A |
cross drain safey end (type 1)
|
108   |
EACH |
1,600.00 |
172,800.00 |
1,500.00 |
162,000.00 |
1,450.00 |
156,600.00 |
|
|
| 703-01 |
shoulder underdrain systems
|
680   |
LNFT |
44.00 |
29,920.00 |
7.00 |
4,760.00 |
12.00 |
8,160.00 |
|
|
| 703-02 |
shoulder outlet underdrains
|
8   |
EACH |
1,400.00 |
11,200.00 |
415.00 |
3,320.00 |
350.00 |
2,800.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spa.)
|
406.4 |
LNFT |
27.30 |
11,094.72 |
28.00 |
11,379.20 |
27.60 |
11,216.64 |
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
325.3 |
LNFT |
36.00 |
11,710.80 |
37.00 |
12,036.10 |
36.40 |
11,840.92 |
|
|
| 704-01-D |
guard rail (double thrie beam)(6'-3" post spa.)
|
75.0 |
LNFT |
29.00 |
2,175.00 |
30.00 |
2,250.00 |
29.32 |
2,199.00 |
|
|
| 704-03 |
blocked out guard rail
|
2,581.8 |
LNFT |
13.75 |
35,499.75 |
14.00 |
36,145.20 |
13.90 |
35,887.02 |
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
81.9 |
LNFT |
72.00 |
5,896.80 |
75.00 |
6,142.50 |
72.80 |
5,962.32 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
350.0 |
LNFT |
38.00 |
13,300.00 |
39.00 |
13,650.00 |
38.42 |
13,447.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
31   |
EACH |
1,550.00 |
48,050.00 |
1,600.00 |
49,600.00 |
1,570.00 |
48,670.00 |
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
10,949.1 |
SQYD |
43.00 |
470,811.30 |
31.00 |
339,422.10 |
56.00 |
613,149.60 |
|
|
| 712-01-A |
concrete cast-in-place revetment (4" thick)
|
651   |
SQYD |
46.00 |
29,946.00 |
51.00 |
33,201.00 |
81.00 |
52,731.00 |
|
|
| 712-04 |
flexible revetment
|
2,266   |
SQYD |
36.00 |
81,576.00 |
55.00 |
124,630.00 |
75.00 |
169,950.00 |
|
|
| 713-01 |
temporary signs and barricades
|
lump |
LUMP |
200,000.00 |
200,000.00 |
170,000.00 |
170,000.00 |
122,000.00 |
122,000.00 |
|
|
| 713-04-B-02 |
temporary pavement markings (broken line)(4"width)
(10'length) (thermoplastic) |
31.205 |
MILE |
660.00 |
20,595.30 |
670.00 |
20,907.35 |
585.00 |
18,254.92 |
|
|
| 713-05-A-01 |
temporary pavement markings (solid line)(4"width)(type
1 removable) |
2.864 |
MILE |
11,880.00 |
34,024.32 |
12,000.00 |
34,368.00 |
21,026.00 |
60,218.46 |
|
|
| 713-05-A-02 |
temporary pavement markings (solid line)(4"width)
(thermoplastic) |
71.000 |
MILE |
1,960.00 |
139,160.00 |
2,000.00 |
142,000.00 |
983.00 |
69,793.00 |
|
|
| 713-08 |
temporary precast concrete barrier (contractor
furnished) |
1,100   |
EACH |
750.00 |
825,000.00 |
625.00 |
687,500.00 |
610.00 |
671,000.00 |
|
|
| 716-01-B |
mulch (fiber)
|
197.87 |
ACRE |
580.00 |
114,764.60 |
460.00 |
91,020.20 |
632.00 |
125,053.84 |
|
|
| 717-01 |
seeding
|
11,872   |
LB |
5.50 |
65,296.00 |
6.15 |
73,012.80 |
3.29 |
39,058.88 |
|
|
| 718-01 |
fertilizer
|
197,873   |
LB |
0.18 |
35,617.14 |
0.21 |
41,553.33 |
0.20 |
39,574.60 |
|
|
| 719-01 |
plants (live oak (quercus virginiana))(15 gallon)
|
44   |
EACH |
125.00 |
5,500.00 |
130.00 |
5,720.00 |
112.00 |
4,928.00 |
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
200   |
SQYD |
2.00 |
400.00 |
1.00 |
200.00 |
1.00 |
200.00 |
|
|
| 720-01-B |
erosion control system, slope protection (type b)
|
250   |
SQYD |
4.00 |
1,000.00 |
1.00 |
250.00 |
1.00 |
250.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
200,000.00 |
200,000.00 |
28,000.00 |
28,000.00 |
25,000.00 |
25,000.00 |
|
|
| 726-01 |
bedding material
|
446.7 |
CUYD |
64.00 |
28,588.80 |
77.00 |
34,395.90 |
76.00 |
33,949.20 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
4,210,000.00 |
4,210,000.00 |
3,405,000.00 |
3,405,000.00 |
4,122,000.00 |
4,122,000.00 |
|
|
| 729-01 |
sign (type a)
|
224.0 |
SQFT |
23.40 |
5,241.60 |
24.00 |
5,376.00 |
23.66 |
5,299.84 |
|
|
| 729-04 |
sign (type d)
|
600.0 |
SQFT |
23.00 |
13,800.00 |
24.00 |
14,400.00 |
23.26 |
13,956.00 |
|
|
| 729-05 |
sign (type e)
|
31.0 |
SQFT |
29.00 |
899.00 |
30.00 |
930.00 |
29.32 |
908.92 |
|
|
| 729-08-B |
mounting (3 1/2" post)
|
15   |
EACH |
680.00 |
10,200.00 |
700.00 |
10,500.00 |
688.00 |
10,320.00 |
|
|
| 729-08-F |
mounting (w6 x 12)
|
2   |
EACH |
800.00 |
1,600.00 |
820.00 |
1,640.00 |
810.00 |
1,620.00 |
|
|
| 729-08-G |
mounting (w8 x 18)
|
2   |
EACH |
1,200.00 |
2,400.00 |
1,200.00 |
2,400.00 |
1,214.00 |
2,428.00 |
|
|
| 729-08-H |
mounting (w8 x 24)
|
4   |
EACH |
1,338.00 |
5,352.00 |
1,400.00 |
5,600.00 |
1,353.00 |
5,412.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
58   |
EACH |
50.00 |
2,900.00 |
51.00 |
2,958.00 |
51.00 |
2,958.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
19   |
EACH |
60.00 |
1,140.00 |
61.00 |
1,159.00 |
61.00 |
1,159.00 |
|
|
| 729-17 |
milepost assembly (ground mounted)
|
20   |
EACH |
215.00 |
4,300.00 |
220.00 |
4,400.00 |
218.00 |
4,360.00 |
|
|
| 731-01 |
non-reflectorized raised pavement markers
|
8   |
EACH |
15.00 |
120.00 |
15.00 |
120.00 |
10.11 |
80.88 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
2,573   |
EACH |
5.20 |
13,379.60 |
5.30 |
13,636.90 |
6.07 |
15,618.11 |
|
|
| 732-02-A |
plastic pavement striping (solid line)(4" width)
|
61.838 |
MILE |
1,960.00 |
121,202.48 |
2,000.00 |
123,676.00 |
1,910.00 |
118,110.58 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
19.494 |
MILE |
830.00 |
16,180.02 |
850.00 |
16,569.90 |
1,300.00 |
25,342.20 |
|
|
| 732-05-A |
removal of existing markings (blast cleaning)
|
38.978 |
MILE |
0.01 |
0.38 |
2,200.00 |
85,751.60 |
979.00 |
38,159.46 |
|
|
| 732-05-B |
removal of temporary pavement markings
|
139.981 |
MILE |
0.01 |
1.39 |
2,200.00 |
307,958.20 |
351.00 |
49,133.33 |
|
|
| 733-01-A |
concrete roadway barrier (double faced,"f"shaped)
|
4,640.0 |
LNFT |
110.00 |
510,400.00 |
78.00 |
361,920.00 |
122.00 |
566,080.00 |
|
|
| 733-01-B |
concrete roadway barrier (double faced,"special"shaped)
|
3,986.0 |
LNFT |
100.00 |
398,600.00 |
78.00 |
310,908.00 |
151.00 |
601,886.00 |
|
|
| 734-01 |
rubblizing portland cement concrete pavement
|
233,737   |
SQYD |
2.50 |
584,342.50 |
2.65 |
619,403.05 |
2.85 |
666,150.45 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
200,000.00 |
200,000.00 |
430,000.00 |
430,000.00 |
400,000.00 |
400,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
75,000.00 |
75,000.00 |
140,000.00 |
140,000.00 |
500,000.00 |
500,000.00 |
|
|
| 804-01-B |
precast concrete piles (14")
|
6,364   |
LNFT |
54.00 |
343,656.00 |
34.00 |
216,376.00 |
36.00 |
229,104.00 |
|
|
| 804-05 |
precast concrete test piles
|
2   |
EACH |
12,000.00 |
24,000.00 |
9,000.00 |
18,000.00 |
10,000.00 |
20,000.00 |
|
|
| 804-09 |
loading test piles
|
2   |
EACH |
6,000.00 |
12,000.00 |
10,000.00 |
20,000.00 |
1.00 |
2.00 |
|
|
| 804-10 |
reloading test piles
|
2   |
EACH |
1,400.00 |
2,800.00 |
1,400.00 |
2,800.00 |
1.00 |
2.00 |
|
|
| 804-11 |
redriving test piles
|
2   |
EACH |
1,200.00 |
2,400.00 |
500.00 |
1,000.00 |
1.00 |
2.00 |
|
|
| 804-12 |
loading permanent piles
|
2   |
EACH |
4,300.00 |
8,600.00 |
500.00 |
1,000.00 |
1.00 |
2.00 |
|
|
| 804-17 |
dynamic monitoring
|
6   |
EACH |
1,200.00 |
7,200.00 |
1,000.00 |
6,000.00 |
1,000.00 |
6,000.00 |
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
93.09 |
CUYD |
1,200.00 |
111,708.00 |
800.00 |
74,472.00 |
688.00 |
64,045.92 |
|
|
| 805-01-F |
class a concrete (bents)
|
205.08 |
CUYD |
1,400.00 |
287,112.00 |
600.00 |
123,048.00 |
600.00 |
123,048.00 |
|
|
| 805-03 |
class aa concrete
|
814.08 |
CUYD |
800.00 |
651,264.00 |
350.00 |
284,928.00 |
500.00 |
407,040.00 |
|
|
| 805-12-A-01 |
reinforced concrete box culverts (3x3)
|
66.2 |
LNFT |
170.00 |
11,254.00 |
360.00 |
23,832.00 |
455.00 |
30,121.00 |
|
|
| 805-12-E |
reinforced concrete box culverts (4x4)
|
148.0 |
LNFT |
260.00 |
38,480.00 |
380.00 |
56,240.00 |
516.00 |
76,368.00 |
|
|
| 805-12-M |
reinforced concrete box culverts (6x6)
|
192.0 |
LNFT |
370.00 |
71,040.00 |
460.00 |
88,320.00 |
660.00 |
126,720.00 |
|
|
| 805-12-S |
reinforced concrete box culverts (8x8)
|
198.6 |
LNFT |
570.00 |
113,202.00 |
600.00 |
119,160.00 |
810.00 |
160,866.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
187,274   |
LB |
1.00 |
187,274.00 |
0.60 |
112,364.40 |
1.50 |
280,911.00 |
|
|
| 810-01 |
concrete railing (barrier)
|
1,120.00 |
LNFT |
40.00 |
44,800.00 |
45.00 |
50,400.00 |
40.00 |
44,800.00 |
|
|
| 813-01 |
concrete approach slabs
|
1,084.38 |
SQYD |
222.00 |
240,732.36 |
133.00 |
144,222.54 |
125.00 |
135,547.50 |
|
|
| S-001 |
variable message sign unit
|
8   |
EACH |
15,000.00 |
120,000.00 |
15,000.00 |
120,000.00 |
16,000.00 |
128,000.00 |
|
|
| S-002 |
stone drainage outlet
|
318   |
EACH |
480.00 |
152,640.00 |
300.00 |
95,400.00 |
344.00 |
109,392.00 |
|
|
| S-003 |
aggregate drains
|
156   |
EACH |
210.00 |
32,760.00 |
225.00 |
35,100.00 |
223.00 |
34,788.00 |
|
|
| S-004 |
retaining wall
|
563   |
LNFT |
150.00 |
84,450.00 |
31.00 |
17,453.00 |
172.00 |
96,836.00 |
|
|
| S-005 |
patching rubblized p.c.c. pavement (stone)
|
5,000.0 |
SQYD |
30.00 |
150,000.00 |
19.00 |
95,000.00 |
22.81 |
114,050.00 |
|
|
| S-006 |
selective pruning of existing live oak trees
|
38   |
EACH |
525.00 |
19,950.00 |
800.00 |
30,400.00 |
506.00 |
19,228.00 |
|
|
| S-007 |
cleaning existing ditches
|
2,000   |
LNFT |
2.00 |
4,000.00 |
6.50 |
13,000.00 |
5.06 |
10,120.00 |
|
|
| S-008 |
geotextile fabric
|
16,349   |
SQYD |
3.00 |
49,047.00 |
2.00 |
32,698.00 |
2.00 |
32,698.00 |
|
|
| S-009 |
rumble strips (ground in)
|
38.8 |
MILE |
430.00 |
16,684.00 |
440.00 |
17,072.00 |
435.00 |
16,878.00 |
|
|
| S-012 |
motor assistance patrol
|
4,000   |
HOUR |
30.00 |
120,000.00 |
53.00 |
212,000.00 |
52.74 |
210,960.00 |
|
|
| S-013 |
impact attenuators (construction zone)
|
2   |
EACH |
34,000.00 |
68,000.00 |
25,000.00 |
50,000.00 |
17,200.00 |
34,400.00 |
|
|
| S-014 |
pier protection system
|
4   |
EACH |
16,000.00 |
64,000.00 |
23,000.00 |
92,000.00 |
30,400.00 |
121,600.00 |
|
|
| S-025 |
remove and remount existing sign logos
|
10   |
EACH |
40.00 |
400.00 |
41.00 |
410.00 |
40.45 |
404.50 |
|
|
| S-101 |
removal of concrete deck, bent cap & wingwall
|
lump |
LUMP |
100,000.00 |
100,000.00 |
120,000.00 |
120,000.00 |
84,000.00 |
84,000.00 |
|
|
| S-102 |
removal of concrete & pipe railings
|
1,120   |
LNFT |
16.00 |
17,920.00 |
26.00 |
29,120.00 |
166.84 |
186,860.80 |
|
|
| S-103 |
dynamic analysis
|
6   |
EACH |
450.00 |
2,700.00 |
1,200.00 |
7,200.00 |
500.00 |
3,000.00 |
|
|
| S-104 |
existing deck slab patch repair
|
34   |
SQYD |
148.00 |
5,032.00 |
300.00 |
10,200.00 |
404.46 |
13,751.64 |
|
|
| S-105 |
removal of existing guard rail
|
lump |
LUMP |
1.00 |
1.00 |
1.00 |
1.00 |
1.01 |
1.01 |
|
|
| S-712-1 |
paved slope drain (4" minimum thickness)
|
1,700.0 |
LNFT |
18.00 |
30,600.00 |
15.00 |
25,500.00 |
15.17 |
25,789.00 |
|
|
| S-712-2 |
paved slope drain (4" thick)
|
1,100.0 |
LNFT |
14.00 |
15,400.00 |
12.00 |
13,200.00 |
12.13 |
13,343.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
44,877,976.38 |
|
41,770,430.07 |
|
45,148,163.56 |
|
|
|