| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - HUEY STOCKSTILL, INC. |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
- 3 - BARRIERE CONSTRUCTION CO., LLC. |
- 4 - DIAMOND B CONSTRUCTION CO., L.L.C. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks and drives
|
1,556   |
SQYD |
9.00 |
14,004.00 |
10.00 |
15,560.00 |
9.00 |
14,004.00 |
7.70 |
11,981.20 |
| 202-02-H |
removal of guard rail
|
1,340   |
LNFT |
4.00 |
5,360.00 |
3.60 |
4,824.00 |
7.00 |
9,380.00 |
3.30 |
4,422.00 |
| 202-02-I |
removal of shoulder surfacing
|
15,370.7 |
SQYD |
1.00 |
15,370.70 |
1.60 |
24,593.12 |
2.00 |
30,741.40 |
1.44 |
22,133.80 |
| 202-02-J |
removal of surfacing
|
967   |
SQYD |
9.00 |
8,703.00 |
7.00 |
6,769.00 |
4.00 |
3,868.00 |
2.41 |
2,330.47 |
| 203-08 |
borrow (vehicular measurement)
|
4,545   |
CUYD |
10.00 |
45,450.00 |
8.50 |
38,632.50 |
10.00 |
45,450.00 |
14.00 |
63,630.00 |
| 203-08-A |
borrow (vehicular meas.)(selected soils)
|
1,520   |
CUYD |
10.00 |
15,200.00 |
9.00 |
13,680.00 |
11.00 |
16,720.00 |
15.00 |
22,800.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,870   |
CUYD |
40.00 |
74,800.00 |
48.00 |
89,760.00 |
42.00 |
78,540.00 |
37.00 |
69,190.00 |
| 502-01-B |
superpave asphaltic concrete (level 2)
|
8,943.8 |
TON |
42.00 |
375,639.60 |
45.00 |
402,471.00 |
49.00 |
438,246.20 |
60.77 |
543,514.72 |
| 502-01-B-01 |
superpave asphaltic conc wearing course (level 2f)
|
10,333.5 |
TON |
44.00 |
454,674.00 |
48.00 |
496,008.00 |
53.00 |
547,675.50 |
53.80 |
555,942.30 |
| 502-01-D |
superpave asphaltic concrete, incidental paving (level
a) |
1,563.2 |
TON |
80.00 |
125,056.00 |
80.00 |
125,056.00 |
53.00 |
82,849.60 |
91.27 |
142,673.26 |
| 507-01-B |
asphaltic surface treatment (2 applications)
|
52,883   |
SQYD |
3.00 |
158,649.00 |
2.15 |
113,698.45 |
2.40 |
126,919.20 |
2.31 |
122,159.73 |
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
6,917   |
LNFT |
1.00 |
6,917.00 |
1.05 |
7,262.85 |
1.40 |
9,683.80 |
1.10 |
7,608.70 |
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
9,178   |
LNFT |
1.25 |
11,472.50 |
1.35 |
12,390.30 |
1.60 |
14,684.80 |
1.50 |
13,767.00 |
| 602-03 |
cleaning and sealing random cracks
|
4,600   |
LNFT |
3.00 |
13,800.00 |
3.15 |
14,490.00 |
3.50 |
16,100.00 |
3.30 |
15,180.00 |
| 602-05-G-01 |
full depth patching of jointed conc pvmt (8" thick)
(16.0 sq yds & under) |
98.2 |
SQYD |
130.00 |
12,766.00 |
160.00 |
15,712.00 |
105.00 |
10,311.00 |
162.00 |
15,908.40 |
| 602-05-G-02 |
full depth patching of jointed conc pvmt (8" thick)
(16.1-48.0 sq yds) |
272.8 |
SQYD |
120.00 |
32,736.00 |
145.00 |
39,556.00 |
90.00 |
24,552.00 |
151.00 |
41,192.80 |
| 602-05-G-03 |
full depth patching of jointed conc pvmt (8" thick)
(48.1 sq yds & over) |
1,214.1 |
SQYD |
110.00 |
133,551.00 |
135.00 |
163,903.50 |
85.00 |
103,198.50 |
140.00 |
169,974.00 |
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
16   |
LNFT |
35.00 |
560.00 |
100.00 |
1,600.00 |
70.00 |
1,120.00 |
55.00 |
880.00 |
| 701-04-E |
storm drain pipe arch (30" equiv. rcpa)
|
138   |
LNFT |
60.00 |
8,280.00 |
110.00 |
15,180.00 |
130.00 |
17,940.00 |
100.00 |
13,800.00 |
| 702-03-B |
catch basins (cb-02)
|
2   |
EACH |
2,000.00 |
4,000.00 |
2,000.00 |
4,000.00 |
4,000.00 |
8,000.00 |
3,100.00 |
6,200.00 |
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
360.0 |
LNFT |
23.00 |
8,280.00 |
23.00 |
8,280.00 |
28.00 |
10,080.00 |
25.00 |
9,000.00 |
| 704-03 |
blocked out guard rail
|
500.0 |
LNFT |
14.00 |
7,000.00 |
14.50 |
7,250.00 |
15.00 |
7,500.00 |
15.00 |
7,500.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
37.00 |
7,400.00 |
40.00 |
8,000.00 |
36.00 |
7,200.00 |
40.00 |
8,000.00 |
| 704-11-A |
guard rail end treatment (flared)
|
8   |
EACH |
1,500.00 |
12,000.00 |
1,530.00 |
12,240.00 |
1,800.00 |
14,400.00 |
1,600.00 |
12,800.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
100,000.00 |
100,000.00 |
25,000.00 |
25,000.00 |
30,000.00 |
30,000.00 |
53,000.00 |
53,000.00 |
| 713-03-C |
temporary pavement markings (8" width)
|
150   |
LNFT |
0.10 |
15.00 |
0.21 |
31.50 |
0.25 |
37.50 |
0.22 |
33.00 |
| 713-03-E |
temporary pavement markings (24" width)
|
52   |
LNFT |
0.30 |
15.60 |
0.63 |
32.76 |
0.75 |
39.00 |
0.66 |
34.32 |
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
7.550 |
MILE |
200.00 |
1,510.00 |
115.00 |
868.25 |
160.00 |
1,208.00 |
330.00 |
2,491.50 |
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
6.110 |
MILE |
100.00 |
611.00 |
260.00 |
1,588.60 |
50.00 |
305.50 |
280.00 |
1,710.80 |
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
20.900 |
MILE |
200.00 |
4,180.00 |
530.00 |
11,077.00 |
100.00 |
2,090.00 |
560.00 |
11,704.00 |
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
10.00 |
20.00 |
43.00 |
86.00 |
40.00 |
80.00 |
45.00 |
90.00 |
| 713-06-B |
temporary pavement legends and symbols (double arrow)
|
2   |
EACH |
10.00 |
20.00 |
48.00 |
96.00 |
45.00 |
90.00 |
51.00 |
102.00 |
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
1   |
EACH |
20.00 |
20.00 |
135.00 |
135.00 |
125.00 |
125.00 |
140.00 |
140.00 |
| 713-06-E |
temporary pavement legends and symbols (school
crossing) |
12   |
EACH |
20.00 |
240.00 |
185.00 |
2,220.00 |
175.00 |
2,100.00 |
196.00 |
2,352.00 |
| 713-07-A |
temporary reflectorized raised pavement markers (tabs)
|
1,000   |
EACH |
1.50 |
1,500.00 |
3.16 |
3,160.00 |
2.00 |
2,000.00 |
2.00 |
2,000.00 |
| 714-02 |
water
|
40.0 |
MGAL |
FREE |
FREE |
10.00 |
400.00 |
1.00 |
40.00 |
0.01 |
0.40 |
| 716-01-A |
mulch (vegetative)
|
4.00 |
ACRE |
600.00 |
2,400.00 |
660.00 |
2,640.00 |
800.00 |
3,200.00 |
672.00 |
2,688.00 |
| 717-01 |
seeding
|
120   |
LB |
7.00 |
840.00 |
7.50 |
900.00 |
8.00 |
960.00 |
7.50 |
900.00 |
| 718-01 |
fertilizer
|
4,000   |
LB |
0.20 |
800.00 |
0.20 |
800.00 |
0.60 |
2,400.00 |
0.22 |
880.00 |
| 722-01 |
project site laboratory
|
1   |
EACH |
1,000.00 |
1,000.00 |
2,000.00 |
2,000.00 |
2,000.00 |
2,000.00 |
23,200.00 |
23,200.00 |
| 724-01-B |
pavement patching (12" minimum thickness)
|
600   |
SQYD |
50.00 |
30,000.00 |
80.00 |
48,000.00 |
50.00 |
30,000.00 |
92.00 |
55,200.00 |
| 726-01 |
bedding material
|
56.0 |
CUYD |
25.00 |
1,400.00 |
70.00 |
3,920.00 |
35.00 |
1,960.00 |
56.00 |
3,136.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
196,000.00 |
196,000.00 |
92,000.00 |
92,000.00 |
139,000.00 |
139,000.00 |
139,000.00 |
139,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
60.00 |
480.00 |
60.00 |
480.00 |
100.00 |
800.00 |
72.00 |
576.00 |
| 731-02 |
reflectorized raised pavement markers
|
700   |
EACH |
6.00 |
4,200.00 |
5.15 |
3,605.00 |
6.00 |
4,200.00 |
6.00 |
4,200.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
150   |
LNFT |
1.00 |
150.00 |
0.66 |
99.00 |
1.00 |
150.00 |
0.75 |
112.50 |
| 732-01-E |
plastic pavement striping (24" width)
|
52   |
LNFT |
3.00 |
156.00 |
2.65 |
137.80 |
4.00 |
208.00 |
3.00 |
156.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.760 |
MILE |
2,000.00 |
31,520.00 |
1,800.00 |
28,368.00 |
1,900.00 |
29,944.00 |
2,000.00 |
31,520.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.050 |
MILE |
700.00 |
2,135.00 |
610.00 |
1,860.50 |
700.00 |
2,135.00 |
685.00 |
2,089.25 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
130.00 |
260.00 |
125.00 |
250.00 |
150.00 |
300.00 |
140.00 |
280.00 |
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
200.00 |
400.00 |
175.00 |
350.00 |
200.00 |
400.00 |
196.00 |
392.00 |
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
1   |
EACH |
300.00 |
300.00 |
300.00 |
300.00 |
340.00 |
340.00 |
336.00 |
336.00 |
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
6   |
EACH |
400.00 |
2,400.00 |
400.00 |
2,400.00 |
500.00 |
3,000.00 |
448.00 |
2,688.00 |
| 736-09 |
loop detector
|
650   |
LNFT |
10.00 |
6,500.00 |
10.00 |
6,500.00 |
11.00 |
7,150.00 |
12.00 |
7,800.00 |
| 736-10 |
underground junction box
|
1   |
EACH |
300.00 |
300.00 |
630.00 |
630.00 |
300.00 |
300.00 |
672.00 |
672.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
15,000.00 |
15,000.00 |
20,000.00 |
20,000.00 |
22,000.00 |
22,000.00 |
| S-001 |
cement treated base course (12 in depth)
|
33,583   |
SQYD |
3.00 |
100,749.00 |
5.30 |
177,989.90 |
5.00 |
167,915.00 |
4.50 |
151,123.50 |
| S-002 |
u-channel post installation
|
144   |
each |
34.00 |
4,896.00 |
35.00 |
5,040.00 |
40.00 |
5,760.00 |
68.00 |
9,792.00 |
| S-004 |
milling concrete pavement
|
533   |
SQYD |
13.00 |
6,929.00 |
15.00 |
7,995.00 |
14.00 |
7,462.00 |
17.00 |
9,061.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,058,615.40 |
|
2,086,877.03 |
|
2,106,863.00 |
|
2,424,048.65 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - COVINGTON PAVING CO. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks and drives
|
1,556   |
SQYD |
7.15 |
11,125.40 |
|
|
|
|
|
|
| 202-02-H |
removal of guard rail
|
1,340   |
LNFT |
6.00 |
8,040.00 |
|
|
|
|
|
|
| 202-02-I |
removal of shoulder surfacing
|
15,370.7 |
SQYD |
0.08 |
1,229.65 |
|
|
|
|
|
|
| 202-02-J |
removal of surfacing
|
967   |
SQYD |
3.25 |
3,142.75 |
|
|
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
4,545   |
CUYD |
11.00 |
49,995.00 |
|
|
|
|
|
|
| 203-08-A |
borrow (vehicular meas.)(selected soils)
|
1,520   |
CUYD |
23.50 |
35,720.00 |
|
|
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,870   |
CUYD |
36.57 |
68,385.90 |
|
|
|
|
|
|
| 502-01-B |
superpave asphaltic concrete (level 2)
|
8,943.8 |
TON |
54.50 |
487,437.10 |
|
|
|
|
|
|
| 502-01-B-01 |
superpave asphaltic conc wearing course (level 2f)
|
10,333.5 |
TON |
55.50 |
573,509.25 |
|
|
|
|
|
|
| 502-01-D |
superpave asphaltic concrete, incidental paving (level
a) |
1,563.2 |
TON |
60.00 |
93,792.00 |
|
|
|
|
|
|
| 507-01-B |
asphaltic surface treatment (2 applications)
|
52,883   |
SQYD |
2.31 |
122,159.73 |
|
|
|
|
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
6,917   |
LNFT |
1.10 |
7,608.70 |
|
|
|
|
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
9,178   |
LNFT |
1.38 |
12,665.64 |
|
|
|
|
|
|
| 602-03 |
cleaning and sealing random cracks
|
4,600   |
LNFT |
3.30 |
15,180.00 |
|
|
|
|
|
|
| 602-05-G-01 |
full depth patching of jointed conc pvmt (8" thick)
(16.0 sq yds & under) |
98.2 |
SQYD |
143.00 |
14,042.60 |
|
|
|
|
|
|
| 602-05-G-02 |
full depth patching of jointed conc pvmt (8" thick)
(16.1-48.0 sq yds) |
272.8 |
SQYD |
132.00 |
36,009.60 |
|
|
|
|
|
|
| 602-05-G-03 |
full depth patching of jointed conc pvmt (8" thick)
(48.1 sq yds & over) |
1,214.1 |
SQYD |
121.00 |
146,906.10 |
|
|
|
|
|
|
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
16   |
LNFT |
61.00 |
976.00 |
|
|
|
|
|
|
| 701-04-E |
storm drain pipe arch (30" equiv. rcpa)
|
138   |
LNFT |
94.00 |
12,972.00 |
|
|
|
|
|
|
| 702-03-B |
catch basins (cb-02)
|
2   |
EACH |
3,900.00 |
7,800.00 |
|
|
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
360.0 |
LNFT |
24.75 |
8,910.00 |
|
|
|
|
|
|
| 704-03 |
blocked out guard rail
|
500.0 |
LNFT |
15.00 |
7,500.00 |
|
|
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
40.00 |
8,000.00 |
|
|
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
8   |
EACH |
1,600.00 |
12,800.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
191,000.00 |
191,000.00 |
|
|
|
|
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
150   |
LNFT |
0.20 |
30.00 |
|
|
|
|
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
52   |
LNFT |
0.66 |
34.32 |
|
|
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
7.550 |
MILE |
300.00 |
2,265.00 |
|
|
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
6.110 |
MILE |
280.00 |
1,710.80 |
|
|
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
20.900 |
MILE |
560.00 |
11,704.00 |
|
|
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
45.00 |
90.00 |
|
|
|
|
|
|
| 713-06-B |
temporary pavement legends and symbols (double arrow)
|
2   |
EACH |
50.00 |
100.00 |
|
|
|
|
|
|
| 713-06-D |
temporary pavement legends and symbols (rr crossing)
|
1   |
EACH |
138.00 |
138.00 |
|
|
|
|
|
|
| 713-06-E |
temporary pavement legends and symbols (school
crossing) |
12   |
EACH |
195.00 |
2,340.00 |
|
|
|
|
|
|
| 713-07-A |
temporary reflectorized raised pavement markers (tabs)
|
1,000   |
EACH |
1.65 |
1,650.00 |
|
|
|
|
|
|
| 714-02 |
water
|
40.0 |
MGAL |
0.01 |
0.40 |
|
|
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
4.00 |
ACRE |
660.00 |
2,640.00 |
|
|
|
|
|
|
| 717-01 |
seeding
|
120   |
LB |
7.00 |
840.00 |
|
|
|
|
|
|
| 718-01 |
fertilizer
|
4,000   |
LB |
0.22 |
880.00 |
|
|
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
14,000.00 |
14,000.00 |
|
|
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
600   |
SQYD |
69.00 |
41,400.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
56.0 |
CUYD |
39.00 |
2,184.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
385,000.00 |
385,000.00 |
|
|
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
66.00 |
528.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
700   |
EACH |
5.65 |
3,955.00 |
|
|
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
150   |
LNFT |
0.75 |
112.50 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
52   |
LNFT |
2.90 |
150.80 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.760 |
MILE |
1,950.00 |
30,732.00 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.050 |
MILE |
670.00 |
2,043.50 |
|
|
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
138.00 |
276.00 |
|
|
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
195.00 |
390.00 |
|
|
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
1   |
EACH |
330.00 |
330.00 |
|
|
|
|
|
|
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
6   |
EACH |
440.00 |
2,640.00 |
|
|
|
|
|
|
| 736-09 |
loop detector
|
650   |
LNFT |
11.00 |
7,150.00 |
|
|
|
|
|
|
| 736-10 |
underground junction box
|
1   |
EACH |
300.00 |
300.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
60,000.00 |
60,000.00 |
|
|
|
|
|
|
| S-001 |
cement treated base course (12 in depth)
|
33,583   |
SQYD |
3.33 |
111,831.39 |
|
|
|
|
|
|
| S-002 |
u-channel post installation
|
144   |
each |
45.00 |
6,480.00 |
|
|
|
|
|
|
| S-004 |
milling concrete pavement
|
533   |
SQYD |
6.50 |
3,464.50 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|