Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 030-04-0029 | |
| Parish: Washington | |
| Routes: LA 21 | |
| Description: JCT. LA 10 - N. JCT. LA 436 | |
| Type Const: DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, ASPHALTIC SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $3,424,038.78 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $2,754,964.81 |
| 2 | 06276 | Barriere Construction Co., LLC. | $2,852,182.12 |
| 3 | 06487 | Huey Stockstill, Inc. | $3,170,779.95 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $3,643,582.78 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - Barriere Construction Co., LLC. |
- 3 - Huey Stockstill, Inc. |
- 4 - Boh Bros. Construction Co., LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 2,120 | LNFT | 2.00 | 4,240.00 | 3.00 | 6,360.00 | 2.00 | 4,240.00 | 7.00 | 14,840.00 |
| 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 16 | EACH | 66.00 | 1,056.00 | 11.00 | 176.00 | 10.00 | 160.00 | 11.00 | 176.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,376 | CUYD | 15.00 | 35,640.00 | 6.00 | 14,256.00 | 12.00 | 28,512.00 | 10.00 | 23,760.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 2,930 | LNFT | 1.50 | 4,395.00 | 1.50 | 4,395.00 | 1.40 | 4,102.00 | 1.40 | 4,102.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 30,962.2 | TON | 57.75 | 1,788,067.05 | 65.00 | 2,012,543.00 | 68.00 | 2,105,429.60 | 80.00 | 2,476,976.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,300.8 | TON | 95.00 | 123,576.00 | 1.00 | 1,300.80 | 68.00 | 88,454.40 | 100.00 | 130,080.00 |
| 0007 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 47,494 | GAL | 3.15 | 149,606.10 | 3.00 | 142,482.00 | 3.20 | 151,980.80 | 3.20 | 151,980.80 |
| 0008 | 507-02-00200 | Aggregate (S2) | 69,844 | SQYD | 0.95 | 66,351.80 | 1.00 | 69,844.00 | 1.00 | 69,844.00 | 1.00 | 69,844.00 |
| 0009 | 507-02-00300 | Aggregate (S3) | 69,844 | SQYD | 0.80 | 55,875.20 | 0.50 | 34,922.00 | 0.80 | 55,875.20 | 0.80 | 55,875.20 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 84,960 | SQYD | 1.40 | 118,944.00 | 1.20 | 101,952.00 | 1.10 | 93,456.00 | 2.00 | 169,920.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,425 | CUYD | 0.10 | -442.50 | 1.00 | -4,425.00 | 0.00 | 0.00 | 10.00 | -44,250.00 |
| 0012 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,500 | SQYD | 69.00 | 103,500.00 | 50.00 | 75,000.00 | 100.00 | 150,000.00 | 85.00 | 127,500.00 |
| 0013 | 602-05-01160 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9" Thick) | 6 | SQYD | 1,000.00 | 6,000.00 | 500.00 | 3,000.00 | 250.00 | 1,500.00 | 1,000.00 | 6,000.00 |
| 0014 | 702-04-00100 | Adjusting Manholes | 8 | EACH | 1,500.00 | 12,000.00 | 500.00 | 4,000.00 | 150.00 | 1,200.00 | 250.00 | 2,000.00 |
| 0015 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 1,120 | LNFT | 31.00 | 34,720.00 | 30.00 | 33,600.00 | 30.00 | 33,600.00 | 30.00 | 33,600.00 |
| 0016 | 704-03-00100 | Blocked Out Guard Rail | 700 | LNFT | 22.00 | 15,400.00 | 21.00 | 14,700.00 | 21.00 | 14,700.00 | 19.00 | 13,300.00 |
| 0017 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 400 | LNFT | 71.00 | 28,400.00 | 70.00 | 28,000.00 | 65.00 | 26,000.00 | 60.00 | 24,000.00 |
| 0018 | 704-11-00100 | Guard Rail End Treatment (Flared) | 16 | EACH | 2,100.00 | 33,600.00 | 2,150.00 | 34,400.00 | 2,000.00 | 32,000.00 | 2,300.00 | 36,800.00 |
| 0019 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 5 | SQYD | 350.00 | 1,750.00 | 200.00 | 1,000.00 | 210.00 | 1,050.00 | 250.00 | 1,250.00 |
| 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 80,000.00 | 80,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 |
| 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 48 | LNFT | 0.65 | 31.20 | 1.00 | 48.00 | 0.30 | 14.40 | 0.10 | 4.80 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 19.503 | MILE | 150.00 | 2,925.45 | 1.00 | 19.50 | 50.00 | 975.15 | 10.00 | 195.03 |
| 0023 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.532 | MILE | 380.00 | 2,862.16 | 1.00 | 7.53 | 100.00 | 753.20 | 15.00 | 112.98 |
| 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 31.586 | MILE | 650.00 | 20,530.90 | 1.00 | 31.59 | 200.00 | 6,317.20 | 20.00 | 631.72 |
| 0025 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 210.00 | 840.00 | 1.00 | 4.00 | 50.00 | 200.00 | 10.00 | 40.00 |
| 0026 | 717-01-00100 | Seeding | 217 | LB | 8.50 | 1,844.50 | 8.00 | 1,736.00 | 8.00 | 1,736.00 | 8.00 | 1,736.00 |
| 0027 | 718-01-00100 | Fertilizer | 7,220 | LB | 0.50 | 3,610.00 | 0.45 | 3,249.00 | 0.45 | 3,249.00 | 0.45 | 3,249.00 |
| 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 2,350 | SQYD | 1.25 | 2,937.50 | 1.30 | 3,055.00 | 1.20 | 2,820.00 | 1.20 | 2,820.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 73,500.00 | 73,500.00 | 115,000.00 | 115,000.00 | 220,000.00 | 220,000.00 | 250,000.00 | 250,000.00 |
| 0030 | 729-01-00100 | Sign (Type A) (W11-1 "Bicycle Traffic" & W16-1P "Share The Road") | 74 | SQFT | 22.00 | 1,628.00 | 20.00 | 1,480.00 | 20.00 | 1,480.00 | 17.00 | 1,258.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 71.00 | 1,136.00 | 70.00 | 1,120.00 | 70.00 | 1,120.00 | 85.00 | 1,360.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,772 | EACH | 4.75 | 8,417.00 | 5.50 | 9,746.00 | 5.00 | 8,860.00 | 5.50 | 9,746.00 |
| 0033 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 24 | LNFT | 3.25 | 78.00 | 5.00 | 120.00 | 3.00 | 72.00 | 4.50 | 108.00 |
| 0034 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 15.793 | MILE | 1,100.00 | 17,372.30 | 2,000.00 | 31,586.00 | 1,000.00 | 15,793.00 | 1,950.00 | 30,796.35 |
| 0035 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 3.766 | MILE | 525.00 | 1,977.15 | 700.00 | 2,636.20 | 500.00 | 1,883.00 | 650.00 | 2,447.90 |
| 0036 | 732-03-04000 | Plastic Pavement Striping (Broken Line) (7" Width) (Preformed Tape) (Retroreflectivity Level I) Contrast | 0.86 | MILE | 4,100.00 | 3,526.00 | 6,400.00 | 5,504.00 | 4,000.00 | 3,440.00 | 6,000.00 | 5,160.00 |
| 0037 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 400.00 | 800.00 | 400.00 | 800.00 | 400.00 | 800.00 | 400.00 | 800.00 |
| 0038 | 732-05-00100 | Removal of Existing Markings | 0.535 | MILE | 5,200.00 | 2,782.00 | 5,300.00 | 2,835.50 | 5,000.00 | 2,675.00 | 5,000.00 | 2,675.00 |
| 0039 | 735-01-00100 | Mailboxes | 48 | EACH | 1.00 | 48.00 | 1.00 | 48.00 | 1.00 | 48.00 | 6.00 | 288.00 |
| 0040 | 735-02-00100 | Mailbox Supports (Single) | 42 | EACH | 120.00 | 5,040.00 | 125.00 | 5,250.00 | 120.00 | 5,040.00 | 120.00 | 5,040.00 |
| 0041 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 200.00 | 400.00 | 200.00 | 400.00 | 200.00 | 400.00 | 180.00 | 360.00 |
| 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 6,000.00 | 6,000.00 | 2,000.00 | 2,000.00 |
| CONTRACTOR TOTAL | 2,754,964.81 | 2,852,182.12 | 3,170,779.95 | 3,643,582.78 | ||||||||