Bid Tabulations
Letting of
04/27/2011
LA DOTD Headquarters
| Lead Project: 025-08-0066 | |
| Parish: Caddo | |
| Routes: US 171 | |
| Description: LA 3132 TO LA 511 | |
| Type Const: Asphaltic Concrete Pavement Resurfacing, Guard Rail, Pavement Markings | |
| Estimated Construction Cost: $1,141,657.44 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, Llc | $1,280,594.10 |
| 2 | 17464 | Benton & Brown, LLC. | $1,649,193.11 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, Llc |
- 2 - Benton & Brown, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 1,612 | LNFT | 3.00 | 4,836.00 | 3.30 | 5,319.60 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 8,939.2 | TON | 96.25 | 860,398.00 | 110.00 | 983,312.00 |
| 0003 | 509-01-00100 | Cold Planing Asphaltic Pavement | 68,121 | SQYD | 2.00 | 136,242.00 | 3.00 | 204,363.00 |
| 0004 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,129 | CUYD | 0.10 | -212.90 | 0.01 | -21.29 |
| 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 448 | SQYD | 99.00 | 44,352.00 | 100.00 | 44,800.00 |
| 0006 | 510-03-00100 | Pavement Joint Repair | 360 | TON | 200.00 | 72,000.00 | 300.00 | 108,000.00 |
| 0007 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 637.5 | LNFT | 33.00 | 21,037.50 | 36.00 | 22,950.00 |
| 0008 | 704-03-00100 | Blocked Out Guard Rail | 487.6 | LNFT | 22.00 | 10,727.20 | 24.00 | 11,702.40 |
| 0009 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 12.6 | LNFT | 125.00 | 1,575.00 | 135.00 | 1,701.00 |
| 0010 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 6.3 | LNFT | 135.00 | 850.50 | 150.00 | 945.00 |
| 0011 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 37.5 | LNFT | 60.00 | 2,250.00 | 65.00 | 2,437.50 |
| 0012 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 75 | LNFT | 65.00 | 4,875.00 | 70.00 | 5,250.00 |
| 0013 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 6 | EACH | 2,500.00 | 15,000.00 | 2,750.00 | 16,500.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 75,000.00 | 75,000.00 |
| 0015 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 5,612 | LNFT | 0.15 | 841.80 | 0.15 | 841.80 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 912 | LNFT | 0.80 | 729.60 | 0.90 | 820.80 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.14 | MILE | 800.00 | 8,112.00 | 350.00 | 3,549.00 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 10.14 | MILE | 250.00 | 2,535.00 | 275.00 | 2,788.50 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 20.282 | MILE | 350.00 | 7,098.70 | 400.00 | 8,112.80 |
| 0020 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 36 | EACH | 10.00 | 360.00 | 11.00 | 396.00 |
| 0021 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 36 | EACH | 10.00 | 360.00 | 11.00 | 396.00 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000.00 | 15,000.00 | 75,000.00 | 75,000.00 |
| 0023 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 100.00 | 600.00 | 110.00 | 660.00 |
| 0024 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 674 | EACH | 9.00 | 6,066.00 | 10.00 | 6,740.00 |
| 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,169 | EACH | 4.50 | 5,260.50 | 5.00 | 5,845.00 |
| 0026 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,806 | LNFT | 0.90 | 2,525.40 | 1.00 | 2,806.00 |
| 0027 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 456 | LNFT | 4.00 | 1,824.00 | 4.50 | 2,052.00 |
| 0028 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.141 | MILE | 2,800.00 | 28,394.80 | 3,000.00 | 30,423.00 |
| 0029 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.07 | MILE | 800.00 | 4,056.00 | 900.00 | 4,563.00 |
| 0030 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 10 | EACH | 150.00 | 1,500.00 | 165.00 | 1,650.00 |
| 0031 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 8 | EACH | 150.00 | 1,200.00 | 165.00 | 1,320.00 |
| 0032 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 18 | EACH | 150.00 | 2,700.00 | 165.00 | 2,970.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 16,000.00 | 16,000.00 |
| CONTRACTOR TOTAL | 1,280,594.10 | 1,649,193.11 | ||||||