Bid Tabulations
Letting of
12/16/2009
LA DOTD Headquarters
| Lead Project: 023-01-0063 | |
| Parish: Rapides | |
| Routes: US 167 | |
| Description: LA 107 / LA 28 BRIDGES GUARD RAIL RE-HAB | |
| Type Const: GUARD RAIL, AND RELATED WORK | |
| Estimated Construction Cost: $724,164.88 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 48896 | Command Construction Industries LLC | $484,467.75 |
| 2 | 34068 | Alpha Service and Products, Inc. | $499,982.60 |
| 3 | 38764 | Atwood Fence Company Inc. | $599,972.00 |
| 4 | 43371 | RMD Holdings Ltd | $757,090.21 |
| 41747 | Odum Services, L.P. | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Command Construction Industries LLC |
- 2 - Alpha Service and Products, Inc. |
- 3 - Atwood Fence Company Inc. |
- 4 - RMD Holdings Ltd |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-04024 | Removal of Bridge Components ALUMINUM RAIL, BRACKETS AND HARDWARE | 1 | LUMP | 50,000.00 | 50,000.00 | 5,000.00 | 5,000.00 | 8,572.50 | 8,572.50 | 70,420.39 | 70,420.39 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 3,280 | LNFT | 1.00 | 3,280.00 | 4.50 | 14,760.00 | 4.00 | 13,120.00 | 7.45 | 24,436.00 |
| 0003 | 202-02-38500 | Removal of Surfacing and Stablized Base | 13.3 | SQYD | 450.00 | 5,985.00 | 50.00 | 665.00 | 25.00 | 332.50 | 123.24 | 1,639.09 |
| 0004 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 12,276 | LNFT | 24.00 | 294,624.00 | 28.85 | 354,162.60 | 35.00 | 429,660.00 | 32.02 | 393,077.52 |
| 0005 | 704-03-00100 | Blocked Out Guard Rail | 2,425 | LNFT | 12.75 | 30,918.75 | 17.00 | 41,225.00 | 17.00 | 41,225.00 | 18.43 | 44,692.75 |
| 0006 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 18.8 | LNFT | 50.00 | 940.00 | 75.00 | 1,410.00 | 115.00 | 2,162.00 | 104.17 | 1,958.40 |
| 0007 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 55.00 | 16,500.00 | 53.00 | 15,900.00 | 60.00 | 18,000.00 | 45.26 | 13,578.00 |
| 0008 | 704-11-00100 | Guard Rail End Treatment (Flared) | 12 | EACH | 2,000.00 | 24,000.00 | 2,000.00 | 24,000.00 | 2,000.00 | 24,000.00 | 1,683.59 | 20,203.08 |
| 0009 | 707-01-00100 | Concrete Curb | 60 | LNFT | 50.00 | 3,000.00 | 40.00 | 2,400.00 | 25.00 | 1,500.00 | 105.74 | 6,344.40 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,500.00 | 2,500.00 | 10,000.00 | 10,000.00 | 30,000.00 | 30,000.00 | 81,530.10 | 81,530.10 |
| 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 76,761.23 | 76,761.23 |
| 0012 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 60.00 | 720.00 | 80.00 | 960.00 | 75.00 | 900.00 | 35.80 | 429.60 |
| 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 2,500.00 | 2,500.00 | 4,000.00 | 4,000.00 | 13,729.65 | 13,729.65 |
| 0014 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,000 | INLF | 1.00 | 1,000.00 | 2.00 | 2,000.00 | 1.50 | 1,500.00 | 8.29 | 8,290.00 |
| CONTRACTOR TOTAL | 484,467.75 | 499,982.60 | 599,972.00 | 757,090.21 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
Odum Services, L.P. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-04024 | Removal of Bridge Components ALUMINUM RAIL, BRACKETS AND HARDWARE | 1 | LUMP | 30,000.00 | 30,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 3,280 | LNFT | 2.00 | 6,560.00 |
| 0003 | 202-02-38500 | Removal of Surfacing and Stablized Base | 13.3 | SQYD | 250.00 | 3,325.00 |
| 0004 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 12,276 | LNFT | 20.00 | 245,520.00 |
| 0005 | 704-03-00100 | Blocked Out Guard Rail | 2,425 | LNFT | 19.00 | 46,075.00 |
| 0006 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 18.8 | LNFT | 125.00 | 2,350.00 |
| 0007 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 65.00 | 19,500.00 |
| 0008 | 704-11-00100 | Guard Rail End Treatment (Flared) | 12 | EACH | 1,785.00 | 21,420.00 |
| 0009 | 707-01-00100 | Concrete Curb | 60 | LNFT | 20.00 | 1,200.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,750.00 | 2,750.00 |
| 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 |
| 0012 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 110.00 | 1,320.00 |
| 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 |
| 0014 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,000 | INLF | 5.00 | 5,000.00 |
| CONTRACTOR TOTAL | IRREGULAR | |||||