Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 014-04-0052 | |
| Parish: Allen | |
| Routes: US 165 | |
| Description: US 165 @ BOISE-CASCADE INTERSECTION | |
| Type Const: GRADING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $564,028.15 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 52306 | Cecil Perry Improvements Llc | $698,243.20 |
| 2 | 39580 | Gerace Construction Llc | $698,559.10 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $726,062.64 |
| 4 | 00568 | Merrick Construction Co. | $756,312.03 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Cecil Perry Improvements Llc |
- 2 - Gerace Construction Llc |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Merrick Construction Co. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | lump | 14,312.00 | 14,312.00 | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,540.2 | sq m | 19.20 | 29,571.84 | 6.75 | 10,396.35 | 13.00 | 20,022.60 | 4.00 | 6,160.80 |
| 0003 | 203-01-00100 | General Excavation | 912 | cu m | 15.24 | 13,898.88 | 10.00 | 9,120.00 | 6.00 | 5,472.00 | 2.00 | 1,824.00 |
| 0004 | 203-03-00100 | Embankment | 951 | cu m | 30.17 | 28,691.67 | 10.00 | 9,510.00 | 23.00 | 21,873.00 | 6.00 | 5,706.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 10 | each | 22.10 | 221.00 | 40.00 | 400.00 | 18.00 | 180.00 | 3.00 | 30.00 |
| 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | each | 60.02 | 240.08 | 125.00 | 500.00 | 300.00 | 1,200.00 | 20.00 | 80.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 860 | ln m | 1.87 | 1,608.20 | 7.00 | 6,020.00 | 4.00 | 3,440.00 | 2.00 | 1,720.00 |
| 0008 | 302-02-05120 | Class II Base Course (250 mm Thick) (Stone or Recycled Portland Cement Concrete) | 3,061.5 | sq m | 28.48 | 87,191.52 | 30.00 | 91,845.00 | 31.50 | 96,437.25 | 30.00 | 91,845.00 |
| 0009 | 302-02-11000 | Class II Base Course (425 mm Thick) (Stone or Recycled Portland Cement Concrete) | 1,264.4 | sq m | 47.75 | 60,375.10 | 50.00 | 63,220.00 | 51.00 | 64,484.40 | 38.00 | 48,047.20 |
| 0010 | 304-05-00100 | Lime Treatment (Type E) | 27 | Mg | 476.94 | 12,877.38 | 400.00 | 10,800.00 | 700.00 | 18,900.00 | 200.00 | 5,400.00 |
| 0011 | 305-01-04020 | Subgrade Layer (300 mm Thick) (Treated) | 4,334 | sq m | 8.16 | 35,365.44 | 9.75 | 42,256.50 | 11.00 | 47,674.00 | 10.00 | 43,340.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 428.8 | Mg | 211.35 | 90,626.88 | 160.00 | 68,608.00 | 135.00 | 57,888.00 | 195.00 | 83,616.00 |
| 0013 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 309.3 | Mg | 211.35 | 65,370.56 | 210.00 | 64,953.00 | 165.00 | 51,034.50 | 195.00 | 60,313.50 |
| 0014 | 601-02-00900 | Portland Cement Concrete Pavement (225 mm Thick) (Crossovers & Turnouts) | 1,917 | sq m | 78.13 | 149,775.21 | 90.00 | 172,530.00 | 99.50 | 190,741.50 | 100.00 | 191,700.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | lump | 42,297.91 | 42,297.91 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 | 50,000.00 | 50,000.00 |
| 0016 | 716-01-00100 | Mulch (Vegetative) | 1 | Mg | 1,708.37 | 1,708.37 | 700.00 | 700.00 | 700.00 | 700.00 | 1,160.00 | 1,160.00 |
| 0017 | 717-01-00100 | Seeding | 33 | kg | 24.28 | 801.24 | 15.00 | 495.00 | 16.00 | 528.00 | 8.00 | 264.00 |
| 0018 | 718-01-00100 | Fertilizer | 1,123 | kg | 1.44 | 1,617.12 | 0.55 | 617.65 | 0.60 | 673.80 | 1.00 | 1,123.00 |
| 0019 | 727-01-00100 | Mobilization | 1 | lump | 10,469.87 | 10,469.87 | 65,000.00 | 65,000.00 | 77,000.00 | 77,000.00 | 75,000.00 | 75,000.00 |
| 0020 | 731-02-00100 | Reflectorized Raised Pavement Markers | 63 | each | 8.54 | 538.02 | 5.50 | 346.50 | 6.25 | 393.75 | 5.00 | 315.00 |
| 0021 | 732-01-02040 | Plastic Pavement Striping (200 mm Width) (Thermoplastic 125 mil) | 76 | ln m | 8.03 | 610.28 | 3.50 | 266.00 | 5.25 | 399.00 | 3.00 | 228.00 |
| 0022 | 732-01-02080 | Plastic Pavement Striping (600 mm Width) (Thermoplastic 125 mil) | 34 | ln m | 20.11 | 683.74 | 13.00 | 442.00 | 17.80 | 605.20 | 11.50 | 391.00 |
| 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (100 mm Width) (Thermoplastic 90 mil) | 0.83 | km | 4,003.67 | 3,323.05 | 1,700.00 | 1,411.00 | 2,000.00 | 1,660.00 | 1,500.00 | 1,245.00 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (100 mm Width) (Thermoplastic 90 mil) | 0.238 | km | 3,869.71 | 920.99 | 450.00 | 107.10 | 780.00 | 185.64 | 435.00 | 103.53 |
| 0025 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | each | 134.23 | 268.46 | 200.00 | 400.00 | 255.00 | 510.00 | 175.00 | 350.00 |
| 0026 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | each | 292.87 | 585.74 | 225.00 | 450.00 | 300.00 | 600.00 | 200.00 | 400.00 |
| 0027 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | each | 183.04 | 183.04 | 200.00 | 200.00 | 300.00 | 300.00 | 200.00 | 200.00 |
| 0028 | 732-05-00100 | Removal of Existing Markings | 0.6 | km | 1,801.93 | 1,081.16 | 3,000.00 | 1,800.00 | 6,000.00 | 3,600.00 | 2,800.00 | 1,680.00 |
| 0029 | 740-01-00100 | Construction Layout | 1 | lump | 7,175.52 | 7,175.52 | 12,000.00 | 12,000.00 | 5,000.00 | 5,000.00 | 65,000.00 | 65,000.00 |
| 0030 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 43,100 | mmlm | 0.25 | 10,775.00 | 0.15 | 6,465.00 | 0.10 | 4,310.00 | 0.10 | 4,310.00 |
| 0031 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 0.7 | km | 9,588.81 | 6,712.17 | 11,000.00 | 7,700.00 | 7,500.00 | 5,250.00 | 6,800.00 | 4,760.00 |
| 0032 | 722-01-00100 | Project Site Laboratory | 1 | each | 18,365.76 | 18,365.76 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 698,243.20 | 698,559.10 | 726,062.64 | 756,312.03 | ||||||||