Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 012-07-0017 | |
| Parish: Jefferson Davis, Allen | |
| Routes: US 190 | |
| Description: US 165 - LA 99 and TURN LANE @ LA 99 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC PAVEMENT, PAVEMENT PATCHING AND WIDENING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $2,427,171.25 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34356 | Prairie Contractors Inc. | $2,039,242.75 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,100,689.12 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $2,273,781.74 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Prairie Contractors Inc. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 80 | SQYD | 7.00 | 560.00 | 10.00 | 800.00 | 20.00 | 1,600.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,897 | CUYD | 28.00 | 109,116.00 | 57.00 | 222,129.00 | 45.00 | 175,365.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 18,602.6 | TON | 76.75 | 1,427,749.55 | 75.00 | 1,395,195.00 | 75.00 | 1,395,195.00 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,166.8 | TON | 50.00 | 58,340.00 | 110.00 | 128,348.00 | 125.00 | 145,850.00 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 72,188 | SQYD | 4.03 | 290,917.64 | 1.10 | 79,406.80 | 1.00 | 72,188.00 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,055 | CUYD | 55.00 | -168,025.00 | 0.10 | -305.50 | 1.00 | -3,055.00 |
| 0007 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 300 | SQYD | 120.00 | 36,000.00 | 118.00 | 35,400.00 | 120.00 | 36,000.00 |
| 0008 | 510-02-00100 | Pavement Widening | 1,611.8 | SQYD | 39.00 | 62,860.20 | 38.00 | 61,248.40 | 55.00 | 88,649.00 |
| 0009 | 701-07-00600 | Yard Drain Pipe (15") | 24 | LNFT | 65.00 | 1,560.00 | 36.00 | 864.00 | 50.00 | 1,200.00 |
| 0010 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 3,000.00 | 6,000.00 | 2,600.00 | 5,200.00 | 2,400.00 | 4,800.00 |
| 0011 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 2,500.00 | 2,500.00 | 1,500.00 | 1,500.00 | 1,100.00 | 1,100.00 |
| 0012 | 702-07-00300 | Cross Drain Safety End (Type 3) | 4 | EACH | 2,500.00 | 10,000.00 | 6,000.00 | 24,000.00 | 3,900.00 | 15,600.00 |
| 0013 | 706-01-00100 | Concrete Walk (4" Thick) | 80 | SQYD | 60.00 | 4,800.00 | 50.00 | 4,000.00 | 70.00 | 5,600.00 |
| 0014 | 706-04-00100 | Handicapped Curb Ramps | 18 | EACH | 850.00 | 15,300.00 | 470.00 | 8,460.00 | 1,400.00 | 25,200.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 5,100.00 | 5,100.00 | 7,400.00 | 7,400.00 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 3,738 | LNFT | 0.01 | 37.38 | 0.60 | 2,242.80 | 0.90 | 3,364.20 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 14.016 | MILE | 0.01 | 0.14 | 150.00 | 2,102.40 | 1.00 | 14.02 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 10.167 | MILE | 400.00 | 4,066.80 | 315.00 | 3,202.61 | 1.00 | 10.17 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 37.959 | MILE | 0.01 | 0.38 | 400.00 | 15,183.60 | 610.00 | 23,154.99 |
| 0020 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 9 | EACH | 0.01 | 0.09 | 30.00 | 270.00 | 50.00 | 450.00 |
| 0021 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 9 | EACH | 0.01 | 0.09 | 30.00 | 270.00 | 50.00 | 450.00 |
| 0022 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 3 | EACH | 0.01 | 0.03 | 105.00 | 315.00 | 80.00 | 240.00 |
| 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 100,000.00 | 100,000.00 | 38,500.00 | 38,500.00 | 200,000.00 | 200,000.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,937 | EACH | 5.00 | 9,685.00 | 4.50 | 8,716.50 | 5.80 | 11,234.60 |
| 0025 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,246 | LNFT | 7.00 | 8,722.00 | 6.25 | 7,787.50 | 5.50 | 6,853.00 |
| 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.653 | MILE | 2,250.00 | 28,469.25 | 2,300.00 | 29,101.90 | 2,700.00 | 34,163.10 |
| 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.389 | MILE | 800.00 | 2,711.20 | 790.00 | 2,677.31 | 940.00 | 3,185.66 |
| 0028 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 225.00 | 675.00 | 210.00 | 630.00 | 230.00 | 690.00 |
| 0029 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 225.00 | 675.00 | 210.00 | 630.00 | 240.00 | 720.00 |
| 0030 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 400.00 | 400.00 | 390.00 | 390.00 | 440.00 | 440.00 |
| 0031 | 735-01-00100 | Mailboxes | 12 | EACH | 3.00 | 36.00 | 8.40 | 100.80 | 10.00 | 120.00 |
| 0032 | 735-02-00100 | Mailbox Supports (Single) | 12 | EACH | 175.00 | 2,100.00 | 180.00 | 2,160.00 | 165.00 | 1,980.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 5,200.00 | 5,200.00 | 6,000.00 | 6,000.00 |
| 0034 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 48,600 | INLF | 0.01 | 486.00 | 0.10 | 4,860.00 | 0.10 | 4,860.00 |
| 0035 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 3.9 | MILE | 2,000.00 | 7,800.00 | 770.00 | 3,003.00 | 400.00 | 1,560.00 |
| 0036 | NS-MSC-00280 | Adjusting Gas Valves and Valve Boxes | 2 | EACH | 300.00 | 600.00 | 1,000.00 | 2,000.00 | 800.00 | 1,600.00 |
| CONTRACTOR TOTAL | 2,039,242.75 | 2,100,689.12 | 2,273,781.74 | |||||||