Bid Tabulations
Letting of
06/16/2010
LA DOTD Headquarters
| Lead Project: 010-30-0032 | |
| Parish: Bossier | |
| Routes: LA 72 | |
| Description: OLD MINDEN ROAD INTERSECTION IMPROVEMENTS | |
| Type Const: BASE COURSE, P.C.C. PAVEMENT, INCIDENTAL, CONSTRUCTION, PAVEMENT MARKINGS AND RELATED WORK. | |
| Estimated Construction Cost: $205,052.90 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 28218 | F. J. Burnell, Inc. | $134,084.10 |
| 2 | 45004 | Bondco LLC | $202,987.80 |
| 3 | 18546 | C W & W Contractors, Inc. | $247,698.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F. J. Burnell, Inc. |
- 2 - Bondco LLC |
- 3 - C W & W Contractors, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 7.5 | SQYD | 100.00 | 750.00 | 70.00 | 525.00 | 20.00 | 150.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 1,493.5 | LNFT | 1.00 | 1,493.50 | 17.00 | 25,389.50 | 20.00 | 29,870.00 |
| 0003 | 202-02-26300 | Removal of Median / Island | 522 | SQYD | 10.00 | 5,220.00 | 40.00 | 20,880.00 | 10.00 | 5,220.00 |
| 0004 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 112.6 | SQYD | 10.00 | 1,126.00 | 44.00 | 4,954.40 | 10.00 | 1,126.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 39.9 | SQYD | 20.00 | 798.00 | 25.00 | 997.50 | 10.00 | 399.00 |
| 0006 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 882.9 | SQYD | 75.00 | 66,217.50 | 78.00 | 68,866.20 | 120.00 | 105,948.00 |
| 0007 | 706-01-00100 | Concrete Walk (4" Thick) | 3.2 | SQYD | 100.00 | 320.00 | 180.00 | 576.00 | 100.00 | 320.00 |
| 0008 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 333.3 | SQYD | 50.00 | 16,665.00 | 80.00 | 26,664.00 | 65.00 | 21,664.50 |
| 0009 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 8.2 | SQYD | 100.00 | 820.00 | 180.00 | 1,476.00 | 110.00 | 902.00 |
| 0010 | 707-01-00200 | Concrete Curb (Barrier) | 395.9 | LNFT | 10.00 | 3,959.00 | 20.00 | 7,918.00 | 10.00 | 3,959.00 |
| 0011 | 707-01-00300 | Concrete Curb (Mountable) | 798.5 | LNFT | 7.00 | 5,589.50 | 15.00 | 11,977.50 | 10.00 | 7,985.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 |
| 0013 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 3,255.6 | LNFT | 1.00 | 3,255.60 | 0.75 | 2,441.70 | 2.00 | 6,511.20 |
| 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 13,000.00 | 13,000.00 | 7,500.00 | 7,500.00 | 30,000.00 | 30,000.00 |
| 0015 | 730-15-01000 | Relocate Light Poles Relocate Light Pole | 1 | EACH | 3,000.00 | 3,000.00 | 4,500.00 | 4,500.00 | 10,000.00 | 10,000.00 |
| 0016 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 274 | LNFT | 5.00 | 1,370.00 | 3.00 | 822.00 | 6.00 | 1,644.00 |
| 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 7,500.00 | 7,500.00 | 7,000.00 | 7,000.00 |
| CONTRACTOR TOTAL | 134,084.10 | 202,987.80 | 247,698.70 | |||||||