Bid Tabulations
Letting of
04/27/2011
LA DOTD Headquarters
| Lead Project: 010-05-0033 | |
| Parish: Bossier, Desoto, Red River | |
| Routes: US 84, US 71, LA 483 | |
| Description: Asphalt Surface Treatment Projects | |
| Type Const: Asphalt Surface Treatment, Pavement Markings and related work | |
| Estimated Construction Cost: $361,857.31 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 35378 | P.R. Parker Company Inc | $379,072.25 |
| 2 | 14422 | T. L. Wallace Construction, Inc. | $379,946.40 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - P.R. Parker Company Inc |
- 2 - T. L. Wallace Construction, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 53,612 | GAL | 3.49 | 187,105.88 | 3.30 | 176,919.60 |
| 0002 | 507-02-00200 | Aggregate (S2) | 111,080 | SQYD | 0.63 | 69,980.40 | 0.85 | 94,418.00 |
| 0003 | 507-02-00300 | Aggregate (S3) | 26,029 | SQYD | 0.43 | 11,192.47 | 0.70 | 18,220.30 |
| 0004 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 200 | SQYD | 68.00 | 13,600.00 | 80.00 | 16,000.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 16,500.00 | 16,500.00 | 15,500.00 | 15,500.00 |
| 0006 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 2,540 | EACH | 2.00 | 5,080.00 | 1.25 | 3,175.00 |
| 0007 | 727-01-00100 | Mobilization | 1 | LUMP | 37,900.00 | 37,900.00 | 18,000.00 | 18,000.00 |
| 0008 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,270 | EACH | 6.75 | 8,572.50 | 6.75 | 8,572.50 |
| 0009 | 737-01-00100 | Painted Traffic Striping (Solid Line) (4" Width) | 45.6 | MILE | 525.00 | 23,940.00 | 525.00 | 23,940.00 |
| 0010 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 13.35 | MILE | 300.00 | 4,005.00 | 300.00 | 4,005.00 |
| 0011 | 737-03-00500 | Painted Traffic Striping (Solid Line) (24" Width) | 132 | LNFT | 3.00 | 396.00 | 3.00 | 396.00 |
| 0012 | NS-737-00006 | Painted Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 400.00 | 800.00 | 400.00 | 800.00 |
| CONTRACTOR TOTAL | 379,072.25 | 379,946.40 | ||||||