Bid Tabulations
Letting of
07/14/2010
LA DOTD Headquarters
| Lead Project: 008-07-0032 | |
| Parish: Avoyelles | |
| Routes: US 71 | |
| Description: S. BUNKIE CITY LIMITS - RR OVERPASS | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,081,475.74 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $851,776.26 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $1,098,651.97 |
| 3 | 05789 | D & J Construction Co., Inc. | $1,152,251.00 |
| 4 | 34356 | Prairie Contractors Inc. | $1,247,254.51 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - D & J Construction Co., Inc. |
- 4 - Prairie Contractors Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 23 | SQYD | 37.00 | 851.00 | 20.00 | 460.00 | 5.00 | 115.00 | 15.00 | 345.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 42 | LNFT | 21.00 | 882.00 | 15.00 | 630.00 | 5.00 | 210.00 | 15.00 | 630.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 150 | LNFT | 3.00 | 450.00 | 8.00 | 1,200.00 | 15.00 | 2,250.00 | 12.00 | 1,800.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 65 | CUYD | 52.00 | 3,380.00 | 30.00 | 1,950.00 | 65.00 | 4,225.00 | 40.00 | 2,600.00 |
| 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 112 | CUYD | 85.00 | 9,520.00 | 60.00 | 6,720.00 | 65.00 | 7,280.00 | 60.00 | 6,720.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 6,321.1 | TON | 67.50 | 426,674.25 | 75.00 | 474,082.50 | 88.00 | 556,256.80 | 100.80 | 637,166.88 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 2,159.1 | TON | 92.50 | 199,716.75 | 125.00 | 269,887.50 | 88.00 | 190,000.80 | 55.00 | 118,750.50 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 36,765 | SQYD | 1.00 | 36,765.00 | 1.00 | 36,765.00 | 1.75 | 64,338.75 | 2.50 | 91,912.50 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -546 | CUYD | 0.10 | -54.60 | 1.00 | -546.00 | 0.10 | -54.60 | 0.01 | -5.46 |
| 0010 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 100 | SQYD | 53.00 | 5,300.00 | 80.00 | 8,000.00 | 75.00 | 7,500.00 | 100.00 | 10,000.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 846 | SQYD | 64.00 | 54,144.00 | 125.00 | 105,750.00 | 125.00 | 105,750.00 | 125.00 | 105,750.00 |
| 0012 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 30 | EACH | 355.00 | 10,650.00 | 800.00 | 24,000.00 | 1,400.00 | 42,000.00 | 400.00 | 12,000.00 |
| 0013 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,400.00 | 9,600.00 | 2,400.00 | 9,600.00 | 2,200.00 | 8,800.00 | 2,500.00 | 10,000.00 |
| 0014 | 706-01-00100 | Concrete Walk (4" Thick) | 16 | SQYD | 95.00 | 1,520.00 | 75.00 | 1,200.00 | 50.00 | 800.00 | 60.00 | 960.00 |
| 0015 | 706-04-00100 | Handicapped Curb Ramps | 6 | EACH | 1,050.00 | 6,300.00 | 1,200.00 | 7,200.00 | 700.00 | 4,200.00 | 800.00 | 4,800.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,000.00 | 7,000.00 | 12,000.00 | 12,000.00 | 27,000.00 | 27,000.00 | 20,000.00 | 20,000.00 |
| 0017 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 96 | LNFT | 0.60 | 57.60 | 0.80 | 76.80 | 2.00 | 192.00 | 0.01 | 0.96 |
| 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.206 | MILE | 150.00 | 780.90 | 350.00 | 1,822.10 | 225.00 | 1,171.35 | 400.00 | 2,082.40 |
| 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.33 | MILE | 310.00 | 102.30 | 1.00 | 0.33 | 350.00 | 115.50 | 0.01 | 0.00 |
| 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 20.494 | MILE | 625.00 | 12,808.75 | 1.00 | 20.49 | 400.00 | 8,197.60 | 0.01 | 0.20 |
| 0021 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 3 | EACH | 100.00 | 300.00 | 100.00 | 300.00 | 100.00 | 300.00 | 0.01 | 0.03 |
| 0022 | 716-01-00100 | Mulch (Vegetative) | 1 | TON | 530.00 | 530.00 | 600.00 | 600.00 | 550.00 | 550.00 | 800.00 | 800.00 |
| 0023 | 717-01-00100 | Seeding | 15 | LB | 16.00 | 240.00 | 17.00 | 255.00 | 16.00 | 240.00 | 20.00 | 300.00 |
| 0024 | 718-01-00100 | Fertilizer | 500 | LB | 0.57 | 285.00 | 0.80 | 400.00 | 0.60 | 300.00 | 1.00 | 500.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 85,000.00 | 85,000.00 | 70,000.00 | 70,000.00 | 100,000.00 | 100,000.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 344 | EACH | 4.50 | 1,548.00 | 5.80 | 1,995.20 | 6.00 | 2,064.00 | 6.00 | 2,064.00 |
| 0027 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 96 | LNFT | 5.00 | 480.00 | 5.00 | 480.00 | 8.00 | 768.00 | 10.00 | 960.00 |
| 0028 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.247 | MILE | 2,300.00 | 23,568.10 | 2,700.00 | 27,666.90 | 2,000.00 | 20,494.00 | 2,300.00 | 23,568.10 |
| 0029 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.165 | MILE | 625.00 | 103.13 | 950.00 | 156.75 | 3,200.00 | 528.00 | 5,000.00 | 825.00 |
| 0030 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 3 | EACH | 425.00 | 1,275.00 | 450.00 | 1,350.00 | 1,000.00 | 3,000.00 | 1,200.00 | 3,600.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,400.00 | 2,400.00 | 3,500.00 | 3,500.00 | 5,000.00 | 5,000.00 | 1.00 | 1.00 |
| 0032 | 741-11-00100 | Adjusting Water Valve | 10 | EACH | 340.00 | 3,400.00 | 830.00 | 8,300.00 | 300.00 | 3,000.00 | 300.00 | 3,000.00 |
| 0033 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 42,654 | INLF | 0.02 | 853.08 | 0.10 | 4,265.40 | 0.20 | 8,530.80 | 1.10 | 46,919.40 |
| 0034 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 35,640 | INLF | 0.15 | 5,346.00 | 0.10 | 3,564.00 | 0.20 | 7,128.00 | 1.10 | 39,204.00 |
| CONTRACTOR TOTAL | 851,776.26 | 1,098,651.97 | 1,152,251.00 | 1,247,254.51 | ||||||||