Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 008-03-0056 | |
| Parish: Pointe Coupee | |
| Routes: US 190 | |
| Description: Morganza Floodway Bridge Repairs | |
| Type Const: PAVEMENT STRIPING AND PAVEMENT MARKERS, BRIDGE REPAIRS, (ADDITIVE ALTERNATE A1 -- EPOXY-URETHANE COPOLYMER OVERLAY SYSTEM), AND RELATED WORK. | |
| Estimated Construction Cost: $10,390,129.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 26435 | C.E.C., Inc. | $9,777,345.03 |
| 2 | 44133 | Gibson & Associates Inc | $11,405,533.76 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $13,195,123.69 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - C.E.C., Inc. |
- 2 - Gibson & Associates Inc |
- 3 - Coastal Bridge Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 1 | LUMP | 20,000.00 | 20,000.00 | 49,500.00 | 49,500.00 | 70,000.00 | 70,000.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 | 191,000.00 | 191,000.00 | 340,000.00 | 340,000.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 744,000.00 | 744,000.00 | 825,000.00 | 825,000.00 |
| 0004 | 731-02-00100 | Reflectorized Raised Pavement Markers | 7,664 | EACH | 5.25 | 40,236.00 | 5.34 | 40,925.76 | 5.35 | 41,002.40 |
| 0005 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.498 | MILE | 2,385.00 | 34,577.73 | 2,400.00 | 34,795.20 | 2,500.00 | 36,245.00 |
| 0006 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.249 | MILE | 890.00 | 6,451.61 | 900.00 | 6,524.10 | 910.00 | 6,596.59 |
| 0007 | 732-05-00100 | Removal of Existing Markings | 3.624 | MILE | 2,000.00 | 7,248.00 | 2,200.00 | 7,972.80 | 1,100.00 | 3,986.40 |
| 0008 | 740-01-00100 | Construction Layout | 1 | LUMP | 60,000.00 | 60,000.00 | 63,000.00 | 63,000.00 | 325,000.00 | 325,000.00 |
| 0009 | NS-202-00004 | Removal of Debris (Bridge Drainage System) | 1 | LUMP | 20,000.00 | 20,000.00 | 96,000.00 | 96,000.00 | 35,000.00 | 35,000.00 |
| 0010 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 1,000.00 | 3,000.00 | 20,000.00 | 60,000.00 | 30,000.00 | 90,000.00 |
| 0011 | NS-727-00002 | Temporary Construction Matting | 1 | LUMP | 950,000.00 | 950,000.00 | 54,000.00 | 54,000.00 | 1,250,000.00 | 1,250,000.00 |
| 0013 | NS-737-00001 | Traffic Paint Curbs and Traffic Islands | 5,731 | SQYD | 7.00 | 40,117.00 | 0.55 | 3,152.05 | 1.00 | 5,731.00 |
| 0014 | NS-800-00003 | Structure Jacking | 1 | LUMP | 560,000.00 | 560,000.00 | 1,635,000.00 | 1,635,000.00 | 1,500,000.00 | 1,500,000.00 |
| 0015 | NS-800-00241 | Bearing Pads (Elastomeric) | 2,968 | EACH | 35.00 | 103,880.00 | 50.00 | 148,400.00 | 115.00 | 341,320.00 |
| 0016 | NS-805-00007 | Concrete Pile Repairs | 15 | LNFT | 600.00 | 9,000.00 | 980.00 | 14,700.00 | 400.00 | 6,000.00 |
| 0017 | NS-805-00018 | Structural Polymer Concrete (Joint Repairs) | 95 | LNFT | 400.00 | 38,000.00 | 350.00 | 33,250.00 | 435.00 | 41,325.00 |
| 0018 | NS-805-00027 | Structural Concrete Patching | 104 | SQFT | 330.00 | 34,320.00 | 180.00 | 18,720.00 | 250.00 | 26,000.00 |
| 0019 | NS-807-00002 | Steel Bearing Assembly | 2,968 | EACH | 790.00 | 2,344,720.00 | 1,330.00 | 3,947,440.00 | 900.00 | 2,671,200.00 |
| 0020 | NS-810-00001 | Barrier Rail Rehabiltation | 165.32 | LNFT | 500.00 | 82,660.00 | 385.00 | 63,648.20 | 1,250.00 | 206,650.00 |
| 0027 | NS-737-00003 | Painted Pavement Vertical Striping (Solid Line) (6 inch Width) | 37,556 | LNFT | 2.50 | 93,890.00 | 0.55 | 20,655.80 | 0.55 | 20,655.80 |
| SUBTOTAL GENERAL | 4,928,100 | 7,232,684 | 7,841,712 | |||||||
| Alternate DA1 | ||||||||||
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 | 65,000.00 | 65,000.00 | 120,000.00 | 120,000.00 |
| 0022 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 7.112 | MILE | 1,935.00 | 13,761.72 | 2,000.00 | 14,224.00 | 2,000.00 | 14,224.00 |
| 0023 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 14.224 | MILE | 5,780.00 | 82,214.72 | 5,900.00 | 83,921.60 | 6,000.00 | 85,344.00 |
| 0024 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 940 | EACH | 5.00 | 4,700.00 | 5.00 | 4,700.00 | 5.00 | 4,700.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 75,000.00 | 75,000.00 | 125,000.00 | 125,000.00 | 45,000.00 | 45,000.00 |
| 0026 | NS-800-00002 | Epoxy-Urethane Copolymer Overlay System | 891,955 | SQFT | 5.15 | 4,593,568.25 | 4.35 | 3,880,004.25 | 5.70 | 5,084,143.50 |
| SUBTOTAL ALT DA1 | 4,849,244.69 | 4,172,849.85 | 5,353,411.50 | |||||||
| CONTRACTOR TOTAL | 9,777,345.03 | 11,405,533.76 | 13,195,123.69 | |||||||