| Lead Project: 008-02-0034 | |
| Parish: Pointe Coupee | |
| Routes: US 190 | |
| Description: LEFT TURN LANES AT LA 77 AND LA 78/411 | |
| Type Const: CLEARING AND GRUBBING, GRADING, COLD PLANING ASPHALTIC CONCRETE, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PRECAST PRESTRESSED CONCRETE GIRDER SPAN BRIDGE, TRAFFIC SIGNALIZATION, AND RELATED WORK. | |
| Estimated Construction Cost: $6,351,693.88 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $4,699,620.54 |
| 2 | 39462 | Jb James Construction Llc | $5,227,095.90 |
| 3 | 14422 | T. L. Wallace Construction, Inc. | $6,298,711.53 |
| 4 | 00481 | Coastal Bridge Co., L.L.C. | $7,238,738.93 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Jb James Construction Llc |
- 3 - T. L. Wallace Construction, Inc. |
- 4 - Coastal Bridge Co., L.L.C. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 65,000.00 | 65,000.00 | 200,000.00 | 200,000.00 | 300,000.00 | 300,000.00 | 80,000.00 | 80,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 20,000.00 | 20,000.00 | 1,500.00 | 1,500.00 | 30,000.00 | 30,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge Str No. 61390080300001 - 260' x 63'-4" Concrete Deck Girder and Steel Plate Girder Bridge | 1 | EACH | 150,000.00 | 150,000.00 | 120,000.00 | 120,000.00 | 333,000.00 | 333,000.00 | 300,000.00 | 300,000.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,762 | SQYD | 6.00 | 10,572.00 | 7.00 | 12,334.00 | 9.15 | 16,122.30 | 10.00 | 17,620.00 |
| 0005 | 202-02-14500 | Removal of Guard Rail | 250 | LNFT | 8.00 | 2,000.00 | 7.00 | 1,750.00 | 8.90 | 2,225.00 | 10.00 | 2,500.00 |
| 0006 | 202-02-26300 | Removal of Median / Island | 32 | SQYD | 4.00 | 128.00 | 8.00 | 256.00 | 12.00 | 384.00 | 15.00 | 480.00 |
| 0007 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 1,097.78 | SQYD | 7.00 | 7,684.46 | 11.00 | 12,075.58 | 17.00 | 18,662.26 | 15.00 | 16,466.70 |
| 0008 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 3,700.00 | 3,700.00 | 3,250.00 | 3,250.00 | 6,500.00 | 6,500.00 | 3,600.00 | 3,600.00 |
| 0009 | 203-02-00100 | Drainage Excavation | 4,060 | CUYD | 7.00 | 28,420.00 | 10.00 | 40,600.00 | 11.00 | 44,660.00 | 14.00 | 56,840.00 |
| 0010 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 45,000.00 | 45,000.00 | 200,000.00 | 200,000.00 | 75,000.00 | 75,000.00 | 65,000.00 | 65,000.00 |
| 0011 | 204-02-00100 | Temporary Hay or Straw Bales | 110 | EACH | 15.00 | 1,650.00 | 10.00 | 1,100.00 | 11.00 | 1,210.00 | 15.00 | 1,650.00 |
| 0012 | 204-06-00100 | Temporary Silt Fencing | 5,110 | LNFT | 1.30 | 6,643.00 | 1.50 | 7,665.00 | 1.50 | 7,665.00 | 4.00 | 20,440.00 |
| 0013 | 302-02-05000 | Class II Base Course (10" Thick) | 8,494.57 | SQYD | 43.00 | 365,266.51 | 30.00 | 254,837.10 | 50.00 | 424,728.50 | 100.00 | 849,457.00 |
| 0014 | 304-05-00100 | Lime Treatment (Type E) | 141.89 | TON | 250.00 | 35,472.50 | 150.00 | 21,283.50 | 390.00 | 55,337.10 | 200.00 | 28,378.00 |
| 0015 | 401-01-00100 | Aggregate Surface Course (Net Section) | 8.44 | CUYD | 100.00 | 844.00 | 100.00 | 844.00 | 75.00 | 633.00 | 600.00 | 5,064.00 |
| 0016 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 350 | CUYD | 30.00 | 10,500.00 | 72.00 | 25,200.00 | 72.00 | 25,200.00 | 125.00 | 43,750.00 |
| 0017 | 502-01-00100 | Superpave Asphaltic Concrete | 6,825.1 | TON | 89.00 | 607,433.90 | 80.00 | 546,008.00 | 120.00 | 819,012.00 | 100.00 | 682,510.00 |
| 0018 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 740.94 | TON | 100.00 | 74,094.00 | 90.00 | 66,684.60 | 120.00 | 88,912.80 | 125.00 | 92,617.50 |
| 0019 | 509-01-00100 | Cold Planing Asphaltic Pavement | 15,706.05 | SQYD | 1.80 | 28,270.89 | 2.50 | 39,265.13 | 7.80 | 122,507.19 | 6.00 | 94,236.30 |
| 0020 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,636.05 | CUYD | 1.00 | -1,636.05 | 0.01 | -16.36 | 0.00 | 0.00 | 1.00 | -1,636.05 |
| 0021 | 704-03-00100 | Blocked Out Guard Rail | 299.2 | LNFT | 20.00 | 5,984.00 | 19.00 | 5,684.80 | 21.00 | 6,283.20 | 21.00 | 6,283.20 |
| 0022 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 97.9 | LNFT | 63.00 | 6,167.70 | 55.00 | 5,384.50 | 61.00 | 5,971.90 | 60.75 | 5,947.43 |
| 0023 | 706-02-00300 | Concrete Drive (8" Thick) | 980 | SQYD | 50.00 | 49,000.00 | 85.00 | 83,300.00 | 60.00 | 58,800.00 | 65.00 | 63,700.00 |
| 0024 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 706.55 | SQYD | 40.00 | 28,262.00 | 65.00 | 45,925.75 | 40.00 | 28,262.00 | 50.00 | 35,327.50 |
| 0025 | 707-01-00300 | Concrete Curb (Mountable) | 2,896.32 | LNFT | 12.00 | 34,755.84 | 25.00 | 72,408.00 | 15.00 | 43,444.80 | 20.00 | 57,926.40 |
| 0026 | 707-03-00100 | Combination Concrete Curb and Gutter | 812 | LNFT | 17.00 | 13,804.00 | 35.00 | 28,420.00 | 18.00 | 14,616.00 | 50.00 | 40,600.00 |
| 0027 | 712-04-00100 | Flexible Revetment | 945 | SQYD | 44.00 | 41,580.00 | 75.00 | 70,875.00 | 83.00 | 78,435.00 | 100.00 | 94,500.00 |
| 0028 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | 30,000.00 | 30,000.00 | 125,000.00 | 125,000.00 |
| 0029 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 650 | LNFT | 0.50 | 325.00 | 1.00 | 650.00 | 0.33 | 214.50 | 0.45 | 292.50 |
| 0030 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1.08 | MILE | 340.00 | 367.20 | 1,500.00 | 1,620.00 | 1,200.00 | 1,296.00 | 860.00 | 928.80 |
| 0031 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 5.4 | MILE | 850.00 | 4,590.00 | 750.00 | 4,050.00 | 780.00 | 4,212.00 | 860.00 | 4,644.00 |
| 0032 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 12 | EACH | 85.00 | 1,020.00 | 75.00 | 900.00 | 56.00 | 672.00 | 83.00 | 996.00 |
| 0033 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 6 | EACH | 85.00 | 510.00 | 75.00 | 450.00 | 56.00 | 336.00 | 83.00 | 498.00 |
| 0034 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 110.00 | 220.00 | 75.00 | 150.00 | 56.00 | 112.00 | 110.50 | 221.00 |
| 0035 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 350 | EACH | 5.20 | 1,820.00 | 4.50 | 1,575.00 | 0.39 | 136.50 | 5.00 | 1,750.00 |
| 0036 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 70 | EACH | 1,000.00 | 70,000.00 | 975.00 | 68,250.00 | 1,200.00 | 84,000.00 | 1,150.00 | 80,500.00 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 450,000.00 | 450,000.00 | 550,000.00 | 550,000.00 | 600,000.00 | 600,000.00 | 650,000.00 | 650,000.00 |
| 0038 | 729-01-00100 | Sign (Type A) | 20 | SQFT | 55.00 | 1,100.00 | 50.00 | 1,000.00 | 51.00 | 1,020.00 | 44.00 | 880.00 |
| 0039 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 85.00 | 680.00 | 75.00 | 600.00 | 83.00 | 664.00 | 85.00 | 680.00 |
| 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 906 | EACH | 5.75 | 5,209.50 | 5.00 | 4,530.00 | 1.65 | 1,494.90 | 5.50 | 4,983.00 |
| 0041 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 700 | LNFT | 3.45 | 2,415.00 | 3.00 | 2,100.00 | 3.35 | 2,345.00 | 3.30 | 2,310.00 |
| 0042 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.7 | MILE | 2,500.00 | 6,750.00 | 2,400.00 | 6,480.00 | 3,300.00 | 8,910.00 | 2,650.00 | 7,155.00 |
| 0043 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.13 | MILE | 6,500.00 | 845.00 | 6,000.00 | 780.00 | 6,700.00 | 871.00 | 6,630.00 | 861.90 |
| 0044 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.08 | MILE | 1,100.00 | 1,188.00 | 1,000.00 | 1,080.00 | 1,100.00 | 1,188.00 | 1,100.00 | 1,188.00 |
| 0045 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 12 | EACH | 175.00 | 2,100.00 | 200.00 | 2,400.00 | 280.00 | 3,360.00 | 185.00 | 2,220.00 |
| 0046 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 7 | EACH | 200.00 | 1,400.00 | 200.00 | 1,400.00 | 330.00 | 2,310.00 | 210.00 | 1,470.00 |
| 0047 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 200.00 | 1,200.00 | 200.00 | 1,200.00 | 330.00 | 1,980.00 | 200.00 | 1,200.00 |
| 0048 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 465.00 | 930.00 | 400.00 | 800.00 | 440.00 | 880.00 | 440.00 | 880.00 |
| 0049 | 732-05-00100 | Removal of Existing Markings | 1.076 | MILE | 3,000.00 | 3,228.00 | 5,000.00 | 5,380.00 | 5,600.00 | 6,025.60 | 2,750.00 | 2,959.00 |
| 0050 | 736-01-00100 | Trenching and Backfilling | 950 | LNFT | 4.45 | 4,227.50 | 4.00 | 3,800.00 | 3.00 | 2,850.00 | 4.25 | 4,037.50 |
| 0051 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 880 | LNFT | 12.00 | 10,560.00 | 11.00 | 9,680.00 | 15.00 | 13,200.00 | 12.10 | 10,648.00 |
| 0052 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 1 | EACH | 7,600.00 | 7,600.00 | 6,700.00 | 6,700.00 | 7,100.00 | 7,100.00 | 7,400.00 | 7,400.00 |
| 0053 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 2 | EACH | 8,600.00 | 17,200.00 | 7,600.00 | 15,200.00 | 7,500.00 | 15,000.00 | 8,400.00 | 16,800.00 |
| 0054 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 2 | EACH | 10,000.00 | 20,000.00 | 9,000.00 | 18,000.00 | 9,500.00 | 19,000.00 | 9,800.00 | 19,600.00 |
| 0055 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 3 | EACH | 11,000.00 | 33,000.00 | 10,000.00 | 30,000.00 | 10,000.00 | 30,000.00 | 10,950.00 | 32,850.00 |
| 0056 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 16 | EACH | 920.00 | 14,720.00 | 800.00 | 12,800.00 | 1,100.00 | 17,600.00 | 880.00 | 14,080.00 |
| 0057 | 736-05-04000 | Signal Heads (5 Section, 12" Led Lens, R, LT. Y, Y, LT. G, G) | 4 | EACH | 1,300.00 | 5,200.00 | 1,300.00 | 5,200.00 | 1,600.00 | 6,400.00 | 1,350.00 | 5,400.00 |
| 0058 | 736-06-00600 | Signal Service (Existing Pole) | 2 | EACH | 900.00 | 1,800.00 | 900.00 | 1,800.00 | 1,300.00 | 2,600.00 | 940.00 | 1,880.00 |
| 0059 | 736-08-00070 | Sig Cntrlr (TS-2, Type 2, w/Eth cap)(Type 6 Cabinet) (F&I) | 2 | EACH | 24,000.00 | 48,000.00 | 23,000.00 | 46,000.00 | 27,000.00 | 54,000.00 | 25,000.00 | 50,000.00 |
| 0060 | 736-09-00100 | Loop Detector | 300 | LNFT | 11.50 | 3,450.00 | 10.00 | 3,000.00 | 12.00 | 3,600.00 | 11.10 | 3,330.00 |
| 0061 | 736-10-00200 | Underground Junction Box (Type E) | 6 | EACH | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 480.00 | 2,880.00 | 400.00 | 2,400.00 |
| 0062 | 736-10-00300 | Underground Junction Box (Type F) | 6 | EACH | 425.00 | 2,550.00 | 400.00 | 2,400.00 | 550.00 | 3,300.00 | 420.00 | 2,520.00 |
| 0063 | 736-10-00500 | Underground Junction Box (Type H) | 2 | EACH | 900.00 | 1,800.00 | 800.00 | 1,600.00 | 960.00 | 1,920.00 | 875.00 | 1,750.00 |
| 0064 | 736-11-00100 | Conduit (1/2" HDPE, Schedule 80) | 160 | LNFT | 6.25 | 1,000.00 | 6.00 | 960.00 | 0.72 | 115.20 | 6.00 | 960.00 |
| 0065 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 1,560 | LNFT | 1.70 | 2,652.00 | 1.50 | 2,340.00 | 1.45 | 2,262.00 | 1.65 | 2,574.00 |
| 0066 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 60 | LNFT | 11.00 | 660.00 | 10.00 | 600.00 | 2.70 | 162.00 | 10.60 | 636.00 |
| 0067 | 736-12-01000 | Conductor (2c, Loop Lead in, imsa 50-2, #19 awg, Twisted Pair) | 2,080 | LNFT | 1.25 | 2,600.00 | 1.25 | 2,600.00 | 1.05 | 2,184.00 | 1.25 | 2,600.00 |
| 0068 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 60 | LNFT | 6.00 | 360.00 | 6.00 | 360.00 | 2.85 | 171.00 | 5.90 | 354.00 |
| 0069 | 736-12-06000 | Conductor (10c, #14 awg) | 1,100 | LNFT | 2.00 | 2,200.00 | 2.00 | 2,200.00 | 2.00 | 2,200.00 | 2.00 | 2,200.00 |
| 0070 | 739-01-00100 | Hydro-Seeding | 2.35 | ACRE | 1,000.00 | 2,350.00 | 900.00 | 2,115.00 | 1,000.00 | 2,350.00 | 1,000.00 | 2,350.00 |
| 0071 | 740-01-00100 | Construction Layout | 1 | LUMP | 80,000.00 | 80,000.00 | 50,000.00 | 50,000.00 | 54,000.00 | 54,000.00 | 110,000.00 | 110,000.00 |
| 0072 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 35,000.00 | 35,000.00 | 40,000.00 | 40,000.00 | 80,000.00 | 80,000.00 | 110,000.00 | 110,000.00 |
| 0073 | 804-01-00200 | Precast Concrete Piles (14") | 100 | LNFT | 87.00 | 8,700.00 | 120.00 | 12,000.00 | 100.00 | 10,000.00 | 100.00 | 10,000.00 |
| 0074 | 804-01-00300 | Precast Concrete Piles (16") | 3,674 | LNFT | 61.00 | 224,114.00 | 63.00 | 231,462.00 | 58.00 | 213,092.00 | 85.00 | 312,290.00 |
| 0075 | 804-01-00700 | Precast Concrete Piles (30") | 1,890 | LNFT | 130.00 | 245,700.00 | 120.00 | 226,800.00 | 290.00 | 548,100.00 | 165.00 | 311,850.00 |
| 0076 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 6,000.00 | 6,000.00 | 2,000.00 | 2,000.00 | 34,000.00 | 34,000.00 | 500.00 | 500.00 |
| 0077 | 804-17-00100 | Dynamic Monitoring | 4 | EACH | 1,200.00 | 4,800.00 | 1,800.00 | 7,200.00 | 2,900.00 | 11,600.00 | 1,500.00 | 6,000.00 |
| 0078 | 805-01-00700 | Class A Concrete (Bents) | 238.88 | CUYD | 1,000.00 | 238,880.00 | 1,200.00 | 286,656.00 | 750.00 | 179,160.00 | 1,650.00 | 394,152.00 |
| 0079 | 805-04-00100 | Class AA(M) Concrete | 683.6 | CUYD | 700.00 | 478,520.00 | 660.00 | 451,176.00 | 700.00 | 478,520.00 | 1,100.00 | 751,960.00 |
| 0080 | 805-08-00400 | Precast-Prestressed Concrete Girder (Type IV) | 3,118.5 | LNFT | 110.00 | 343,035.00 | 125.00 | 389,812.50 | 120.00 | 374,220.00 | 135.00 | 420,997.50 |
| 0081 | 805-11-00100 | Strip Seal Joints | 168.5 | LNFT | 190.00 | 32,015.00 | 175.00 | 29,487.50 | 210.00 | 35,385.00 | 225.00 | 37,912.50 |
| 0082 | 806-01-00100 | Deformed Reinforcing Steel | 247,014 | LB | 0.65 | 160,559.10 | 0.85 | 209,961.90 | 0.98 | 242,073.72 | 1.25 | 308,767.50 |
| 0083 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 6,000.00 | 6,000.00 | 25,000.00 | 25,000.00 | 5,200.00 | 5,200.00 | 65,000.00 | 65,000.00 |
| 0084 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 650 | LNFT | 60.00 | 39,000.00 | 55.00 | 35,750.00 | 72.00 | 46,800.00 | 100.00 | 65,000.00 |
| 0085 | 813-01-00100 | Concrete Approach Slabs | 748.88 | SQYD | 200.00 | 149,776.00 | 220.00 | 164,753.60 | 220.00 | 164,753.60 | 300.00 | 224,664.00 |
| 0086 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 350 | TON | 95.00 | 33,250.00 | 125.00 | 43,750.00 | 140.00 | 49,000.00 | 250.00 | 87,500.00 |
| 0087 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 28,680 | INLF | 0.55 | 15,774.00 | 1.50 | 43,020.00 | 1.00 | 28,680.00 | 1.65 | 47,322.00 |
| 0088 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,005 | INLF | 1.75 | 1,758.75 | 1.50 | 1,507.50 | 1.40 | 1,407.00 | 1.65 | 1,658.25 |
| 0089 | NS-700-00180 | Impact Attenuator (Construction Zone) | 6 | EACH | 15,000.00 | 90,000.00 | 10,000.00 | 60,000.00 | 19,000.00 | 114,000.00 | 15,500.00 | 93,000.00 |
| 0090 | NS-700-00220 | Impact Attenuator (Kinetic) | 2 | EACH | 14,000.00 | 28,000.00 | 20,000.00 | 40,000.00 | 19,000.00 | 38,000.00 | 15,500.00 | 31,000.00 |
| 0091 | NS-700-00240 | Special Guard Rail Anchor Section | 4 | EACH | 1,200.00 | 4,800.00 | 1,100.00 | 4,400.00 | 1,200.00 | 4,800.00 | 1,250.00 | 5,000.00 |
| 0092 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 12,000.00 | 24,000.00 | 15,200.00 | 30,400.00 | 16,000.00 | 32,000.00 | 16,000.00 | 32,000.00 |
| 0093 | NS-736-00005 | Video Detection Cabinet Components | 2 | EACH | 9,000.00 | 18,000.00 | 8,000.00 | 16,000.00 | 8,300.00 | 16,600.00 | 8,800.00 | 17,600.00 |
| 0094 | NS-736-00006 | Video Detection Camera | 8 | EACH | 2,000.00 | 16,000.00 | 1,900.00 | 15,200.00 | 2,100.00 | 16,800.00 | 2,100.00 | 16,800.00 |
| 0095 | NS-736-00007 | Video Detection Training | 1 | LUMP | 1.15 | 1.15 | 1.00 | 1.00 | 1.10 | 1.10 | 1.10 | 1.10 |
| 0097 | 737-04-00001 | Painted Curbs and Islands | 94.66 | SQYD | 1.20 | 113.59 | 5.00 | 473.30 | 5.55 | 525.36 | 90.00 | 8,519.40 |
| CONTRACTOR TOTAL | 4,699,620.54 | 5,227,095.90 | 6,298,711.53 | 7,238,738.93 | ||||||||