Bid Tabulations
Letting of
02/23/2011
LA DOTD Headquarters
| Lead Project: 008-01-0050 | |
| Parish: West Baton Rouge | |
| Routes: LA 415 | |
| Description: RIGHT TURN LANES AT LA 1145 & LA 987-3 | |
| Type Const: Reinforced Concrete Pavement | |
| Estimated Construction Cost: $400,684.03 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 52306 | Cecil Perry Improvements Llc | $371,081.28 |
| 2 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $465,533.97 |
| 3 | 05693 | Industrial Enterprises, Inc. | $474,104.98 |
| 4 | 14807 | Richard Price Contracting Co, Llc | $483,231.58 |
| 5 | 25088 | RCS Contractors, Inc. | $508,448.22 |
| 6 | 49356 | Kort's Trucking Inc. | $511,817.54 |
| 7 | 39462 | Jb James Construction Llc | $532,042.96 |
| 8 | 12198 | Byron E. Talbot Contractor, Inc. | $575,604.44 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Cecil Perry Improvements Llc |
- 2 - F.G. Sullivan, Jr. Contractor LLC |
- 3 - Industrial Enterprises, Inc. |
- 4 - Richard Price Contracting Co, Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 10 | SQYD | 7.00 | 70.00 | 20.00 | 200.00 | 11.20 | 112.00 | 115.00 | 1,150.00 |
| 0002 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 17 | SQYD | 40.00 | 680.00 | 20.00 | 340.00 | 22.40 | 380.80 | 70.00 | 1,190.00 |
| 0003 | 202-02-38500 | Removal of Surfacing and Stablized Base | 511.2 | SQYD | 5.55 | 2,837.16 | 10.00 | 5,112.00 | 7.28 | 3,721.54 | 7.50 | 3,834.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 3,805.00 | 3,805.00 | 34,950.00 | 34,950.00 | 71,311.00 | 71,311.00 | 12,200.00 | 12,200.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 4,068 | CUYD | 12.40 | 50,443.20 | 15.00 | 61,020.00 | 15.00 | 61,020.00 | 19.00 | 77,292.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 1,437 | EACH | 13.50 | 19,399.50 | 10.00 | 14,370.00 | 10.49 | 15,074.13 | 12.00 | 17,244.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 507 | LNFT | 1.61 | 816.27 | 2.00 | 1,014.00 | 2.23 | 1,130.61 | 2.50 | 1,267.50 |
| 0008 | 302-02-06080 | Class II Base Course (12" Thick) (Asphaltic Concrete Base on Embankment Layer) | 1,409.8 | SQYD | 43.00 | 60,621.40 | 40.00 | 56,392.00 | 70.20 | 98,967.96 | 51.20 | 72,181.76 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 144.2 | TON | 240.50 | 34,680.10 | 10.00 | 1,442.00 | 200.00 | 28,840.00 | 275.00 | 39,655.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 79.07 | 3,953.50 | 25.00 | 1,250.00 | 55.00 | 2,750.00 | 72.00 | 3,600.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 62.5 | TON | 280.00 | 17,500.00 | 270.00 | 16,875.00 | 203.50 | 12,718.75 | 341.00 | 21,312.50 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 2.3 | TON | 280.00 | 644.00 | 270.00 | 621.00 | 220.00 | 506.00 | 341.00 | 784.30 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 333 | SQYD | 16.50 | 5,494.50 | 15.00 | 4,995.00 | 16.50 | 5,494.50 | 6.82 | 2,271.06 |
| 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -113 | CUYD | 1.85 | -209.05 | 0.00 | 0.00 | 0.10 | -11.30 | 0.01 | -1.13 |
| 0015 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 1,334.8 | SQYD | 62.00 | 82,757.60 | 120.00 | 160,176.00 | 85.12 | 113,618.18 | 79.62 | 106,276.78 |
| 0016 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") FOR DRAINAGE WORK NEAR STATION 14+35 | 16 | LNFT | 85.91 | 1,374.56 | 200.00 | 3,200.00 | 82.01 | 1,312.16 | 148.00 | 2,368.00 |
| 0017 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") FOR DRAINAGE WORK NEAR STATION 14+09 | 48 | LNFT | 94.20 | 4,521.60 | 200.00 | 9,600.00 | 82.01 | 3,936.48 | 144.00 | 6,912.00 |
| 0018 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,900.00 | 2,900.00 | 2,500.00 | 2,500.00 | 2,912.00 | 2,912.00 | 2,950.00 | 2,950.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 24,141.53 | 24,141.53 | 43,500.00 | 43,500.00 | 19,008.00 | 19,008.00 | 27,500.00 | 27,500.00 |
| 0020 | 726-01-00100 | Bedding Material | 4 | CUYD | 102.74 | 410.96 | 50.00 | 200.00 | 93.50 | 374.00 | 279.00 | 1,116.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 37,765.00 | 37,765.00 | 25,000.00 | 25,000.00 | 12,656.00 | 12,656.00 | 45,000.00 | 45,000.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 76 | EACH | 5.70 | 433.20 | 5.25 | 399.00 | 5.30 | 402.80 | 6.00 | 456.00 |
| 0023 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 352.9 | LNFT | 1.60 | 564.64 | 1.35 | 476.42 | 1.48 | 522.29 | 1.54 | 543.47 |
| 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 33 | LNFT | 11.39 | 375.87 | 4.50 | 148.50 | 10.60 | 349.80 | 5.12 | 168.96 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.271 | MILE | 3,987.64 | 1,080.65 | 2,750.00 | 745.25 | 3,710.00 | 1,005.41 | 3,116.38 | 844.54 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.116 | MILE | 3,190.09 | 370.05 | 850.00 | 98.60 | 2,968.00 | 344.29 | 916.81 | 106.35 |
| 0027 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 8 | EACH | 199.38 | 1,595.04 | 215.00 | 1,720.00 | 185.50 | 1,484.00 | 244.55 | 1,956.40 |
| 0028 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 222.17 | 888.68 | 225.00 | 900.00 | 206.70 | 826.80 | 255.92 | 1,023.68 |
| 0029 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 455.73 | 455.73 | 400.00 | 400.00 | 424.00 | 424.00 | 454.97 | 454.97 |
| 0030 | 732-05-00100 | Removal of Existing Markings | 0.09 | MILE | 11,409.00 | 1,026.81 | 5,000.00 | 450.00 | 10,600.00 | 954.00 | 5,687.22 | 511.85 |
| 0031 | 739-01-00100 | Hydro-Seeding | 1.05 | ACRE | 1,361.50 | 1,429.58 | 1,200.00 | 1,260.00 | 1,266.70 | 1,330.04 | 1,359.23 | 1,427.19 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,075.00 | 2,075.00 | 10,000.00 | 10,000.00 | 5,500.00 | 5,500.00 | 25,000.00 | 25,000.00 |
| 0033 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 6,179.2 | INLF | 1.00 | 6,179.20 | 1.00 | 6,179.20 | 0.83 | 5,128.74 | 0.75 | 4,634.40 |
| CONTRACTOR TOTAL | 371,081.28 | 465,533.97 | 474,104.98 | 483,231.58 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - RCS Contractors, Inc. |
- 6 - Kort's Trucking Inc. |
- 7 - Jb James Construction Llc |
- 8 - Byron E. Talbot Contractor, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02000 | Removal of Asphalt Drives | 10 | SQYD | 30.00 | 300.00 | 12.00 | 120.00 | 50.00 | 500.00 | 7.75 | 77.50 |
| 0002 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 17 | SQYD | 30.00 | 510.00 | 15.00 | 255.00 | 50.00 | 850.00 | 7.50 | 127.50 |
| 0003 | 202-02-38500 | Removal of Surfacing and Stablized Base | 511.2 | SQYD | 5.00 | 2,556.00 | 13.00 | 6,645.60 | 8.00 | 4,089.60 | 10.70 | 5,469.84 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | 46,000.00 | 46,000.00 | 60,000.00 | 60,000.00 | 30,000.00 | 30,000.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 4,068 | CUYD | 22.00 | 89,496.00 | 12.00 | 48,816.00 | 9.00 | 36,612.00 | 12.05 | 49,019.40 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 1,437 | EACH | 5.00 | 7,185.00 | 12.50 | 17,962.50 | 12.00 | 17,244.00 | 11.00 | 15,807.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 507 | LNFT | 3.00 | 1,521.00 | 2.50 | 1,267.50 | 3.00 | 1,521.00 | 2.25 | 1,140.75 |
| 0008 | 302-02-06080 | Class II Base Course (12" Thick) (Asphaltic Concrete Base on Embankment Layer) | 1,409.8 | SQYD | 44.00 | 62,031.20 | 70.00 | 98,686.00 | 58.00 | 81,768.40 | 64.00 | 90,227.20 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 144.2 | TON | 250.00 | 36,050.00 | 250.00 | 36,050.00 | 240.00 | 34,608.00 | 295.00 | 42,539.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 100.00 | 5,000.00 | 65.00 | 3,250.00 | 100.00 | 5,000.00 | 100.00 | 5,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 62.5 | TON | 290.00 | 18,125.00 | 160.00 | 10,000.00 | 310.00 | 19,375.00 | 162.00 | 10,125.00 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 2.3 | TON | 290.00 | 667.00 | 160.00 | 368.00 | 310.00 | 713.00 | 210.00 | 483.00 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 333 | SQYD | 16.00 | 5,328.00 | 29.00 | 9,657.00 | 8.00 | 2,664.00 | 15.90 | 5,294.70 |
| 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -113 | CUYD | 0.01 | -1.13 | 0.50 | -56.50 | 1.00 | -113.00 | 0.65 | -73.45 |
| 0015 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 1,334.8 | SQYD | 87.00 | 116,127.60 | 96.00 | 128,140.80 | 85.00 | 113,458.00 | 119.50 | 159,508.60 |
| 0016 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") FOR DRAINAGE WORK NEAR STATION 14+35 | 16 | LNFT | 80.00 | 1,280.00 | 110.00 | 1,760.00 | 130.00 | 2,080.00 | 80.00 | 1,280.00 |
| 0017 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") FOR DRAINAGE WORK NEAR STATION 14+09 | 48 | LNFT | 80.00 | 3,840.00 | 110.00 | 5,280.00 | 130.00 | 6,240.00 | 80.00 | 3,840.00 |
| 0018 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,200.00 | 2,200.00 | 2,200.00 | 2,200.00 | 3,000.00 | 3,000.00 | 3,425.00 | 3,425.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 |
| 0020 | 726-01-00100 | Bedding Material | 4 | CUYD | 100.00 | 400.00 | 85.00 | 340.00 | 75.00 | 300.00 | 200.00 | 800.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 49,000.00 | 49,000.00 | 45,000.00 | 45,000.00 | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 76 | EACH | 5.25 | 399.00 | 5.50 | 418.00 | 5.50 | 418.00 | 5.30 | 402.80 |
| 0023 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 352.9 | LNFT | 1.50 | 529.35 | 1.60 | 564.64 | 1.40 | 494.06 | 1.50 | 529.35 |
| 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 33 | LNFT | 11.00 | 363.00 | 11.00 | 363.00 | 10.00 | 330.00 | 10.60 | 349.80 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.271 | MILE | 4,000.00 | 1,084.00 | 3,600.00 | 975.60 | 3,500.00 | 948.50 | 3,710.00 | 1,005.41 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.116 | MILE | 3,000.00 | 348.00 | 3,000.00 | 348.00 | 3,000.00 | 348.00 | 3,000.00 | 348.00 |
| 0027 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 8 | EACH | 180.00 | 1,440.00 | 194.00 | 1,552.00 | 200.00 | 1,600.00 | 185.50 | 1,484.00 |
| 0028 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 200.00 | 800.00 | 199.00 | 796.00 | 200.00 | 800.00 | 210.00 | 840.00 |
| 0029 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 500.00 | 500.00 | 450.00 | 450.00 | 400.00 | 400.00 | 425.00 | 425.00 |
| 0030 | 732-05-00100 | Removal of Existing Markings | 0.09 | MILE | 11,000.00 | 990.00 | 11,000.00 | 990.00 | 10,000.00 | 900.00 | 10,600.00 | 954.00 |
| 0031 | 739-01-00100 | Hydro-Seeding | 1.05 | ACRE | 4,000.00 | 4,200.00 | 1,200.00 | 1,260.00 | 1,200.00 | 1,260.00 | 1,200.00 | 1,260.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 35,000.00 | 35,000.00 | 5,000.00 | 5,000.00 | 30,000.00 | 30,000.00 | 6,500.00 | 6,500.00 |
| 0033 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 6,179.2 | INLF | 1.00 | 6,179.20 | 2.00 | 12,358.40 | 0.75 | 4,634.40 | 1.20 | 7,415.04 |
| CONTRACTOR TOTAL | 508,448.22 | 511,817.54 | 532,042.96 | 575,604.44 | ||||||||