Bid Tabulations
Letting of
04/27/2011
LA DOTD Headquarters
| Lead Project: 007-02-0102 | |
| Parish: Jefferson | |
| Routes: US 61 | |
| Description: IMPROVE / REPAVE WEST TURNAROUND ROADWAY KENNER OVERPASS | |
| Type Const: PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE, PAVEMENT STRIPING AND RELATED WORK. | |
| Estimated Construction Cost: $194,578.88 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $185,161.06 |
| 2 | 06276 | Barriere Construction Co., LLC | $188,165.24 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $369,914.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - Barriere Construction Co., LLC |
- 3 - Coastal Bridge Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 50 | CUYD | 50.00 | 2,500.00 | 15.00 | 750.00 | 50.00 | 2,500.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 622 | TON | 130.00 | 80,860.00 | 112.00 | 69,664.00 | 170.00 | 105,740.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 72.1 | TON | 125.00 | 9,012.50 | 112.00 | 8,075.20 | 200.00 | 14,420.00 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 30 | SQYD | 120.00 | 3,600.00 | 150.00 | 4,500.00 | 150.00 | 4,500.00 |
| 0005 | 510-02-00100 | Pavement Widening | 505 | SQYD | 80.00 | 40,400.00 | 65.00 | 32,825.00 | 80.00 | 40,400.00 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 14,000.00 | 14,000.00 | 18,000.00 | 18,000.00 | 20,000.00 | 20,000.00 |
| 0007 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 32 | LNFT | 0.75 | 24.00 | 1.25 | 40.00 | 0.75 | 24.00 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.656 | MILE | 10.00 | 26.56 | 675.00 | 1,792.80 | 550.00 | 1,460.80 |
| 0009 | 717-01-00100 | Seeding | 15 | LB | 30.00 | 450.00 | 40.00 | 600.00 | 25.00 | 375.00 |
| 0010 | 718-01-00100 | Fertilizer | 500 | LB | 1.00 | 500.00 | 3.00 | 1,500.00 | 1.00 | 500.00 |
| 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 18,000.00 | 18,000.00 | 18,000.00 | 18,000.00 | 125,000.00 | 125,000.00 |
| 0012 | 731-02-00100 | Reflectorized Raised Pavement Markers | 44 | EACH | 6.00 | 264.00 | 8.00 | 352.00 | 5.50 | 242.00 |
| 0013 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 16 | LNFT | 6.00 | 96.00 | 5.50 | 88.00 | 5.00 | 80.00 |
| 0014 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.328 | MILE | 3,000.00 | 3,984.00 | 3,080.00 | 4,090.24 | 2,850.00 | 3,784.80 |
| 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 |
| 0016 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 17,000.00 | 17,000.00 | 35,000.00 | 35,000.00 |
| 0017 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 888 | INLF | 0.50 | 444.00 | 1.00 | 888.00 | 1.00 | 888.00 |
| CONTRACTOR TOTAL | 185,161.06 | 188,165.24 | 369,914.60 | |||||||