Bid Tabulations
Letting of
07/27/2011
LA DOTD Headquarters
| Lead Project: 006-05-0087-R1 | |
| Parish: Orleans | |
| Routes: US 165 (S) | |
| Description: CHEF MENTEUR BRIDGE FENDER SYSTEM REPAIRS | |
| Type Const: FENDER SYSTEM REPAIRS AND RELATED WORK. | |
| Estimated Construction Cost: $2,972,605.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 25747 | Kostmayer Construction, Llc | $2,783,075.00 |
| 2 | 48087 | Silverton Construction Company LLC | $3,490,135.00 |
| 3 | 00060 | F. Miller Construction Llc | $3,512,530.00 |
| 4 | 00271 | Massman Construction Co. | $3,585,500.00 |
| 5 | 20168 | Bo-Mac Contractors Ltd | $3,645,632.55 |
| 6 | 33056 | Manson Construction Co. | $3,761,265.00 |
| 7 | 37302 | Double Aught Construction LLC | $3,869,056.00 |
| 8 | 00481 | Coastal Bridge Co., L.L.C. | $3,938,440.00 |
| 9 | 30077 | Gill's Crane & Dozer Service, Inc. | $4,221,580.00 |
| 10 | 49002 | Aquaterra Contracting, LP | $4,474,395.00 |
| 11 | 01012 | Cecil D. Gassiott, LLC | $4,554,450.00 |
| 12 | 07740 | Cajun Constructors, Inc. | $5,978,579.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Kostmayer Construction, Llc |
- 2 - Silverton Construction Company LLC |
- 3 - F. Miller Construction Llc |
- 4 - Massman Construction Co. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 175,000.00 | 175,000.00 | 246,000.00 | 246,000.00 | 454,000.00 | 454,000.00 | 117,000.00 | 117,000.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 3,700.00 | 3,700.00 | 5,000.00 | 5,000.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 271,000.00 | 271,000.00 | 350,000.00 | 350,000.00 | 320,000.00 | 320,000.00 |
| 0004 | 730-09-00100 | Electrical System | 1 | LUMP | 375,000.00 | 375,000.00 | 670,000.00 | 670,000.00 | 580,000.00 | 580,000.00 | 520,000.00 | 520,000.00 |
| 0005 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | 37,000.00 | 37,000.00 | 10,000.00 | 10,000.00 |
| 0007 | 804-03-02120 | Steel Piles (24" Pipe) | 6,060 | LNFT | 135.00 | 818,100.00 | 153.00 | 927,180.00 | 120.00 | 727,200.00 | 178.00 | 1,078,680.00 |
| 0008 | 804-03-02160 | Steel Piles (36" Pipe) | 2,450 | LNFT | 230.00 | 563,500.00 | 232.00 | 568,400.00 | 182.00 | 445,900.00 | 240.00 | 588,000.00 |
| 0009 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 400,000.00 | 400,000.00 | 491,000.00 | 491,000.00 | 607,500.00 | 607,500.00 | 533,000.00 | 533,000.00 |
| 0010 | NS-804-00007 | Ultra-High Molecular Weight Polyethylene (UHMW-PE) Panels | 3,135 | SQFT | 85.00 | 266,475.00 | 93.00 | 291,555.00 | 98.00 | 307,230.00 | 132.00 | 413,820.00 |
| CONTRACTOR TOTAL | 2,783,075.00 | 3,490,135.00 | 3,512,530.00 | 3,585,500.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Bo-Mac Contractors Ltd |
- 6 - Manson Construction Co. |
- 7 - Double Aught Construction LLC |
- 8 - Coastal Bridge Co., L.L.C. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 288,149.00 | 288,149.00 | 442,000.00 | 442,000.00 | 346,320.00 | 346,320.00 | 370,000.00 | 370,000.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 13,747.00 | 13,747.00 | 5,000.00 | 5,000.00 | 23,125.00 | 23,125.00 | 5,000.00 | 5,000.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 323,014.00 | 323,014.00 | 380,000.00 | 380,000.00 | 258,250.00 | 258,250.00 | 245,000.00 | 245,000.00 |
| 0004 | 730-09-00100 | Electrical System | 1 | LUMP | 638,787.00 | 638,787.00 | 585,000.00 | 585,000.00 | 780,220.00 | 780,220.00 | 580,000.00 | 580,000.00 |
| 0005 | 740-01-00100 | Construction Layout | 1 | LUMP | 75,000.00 | 75,000.00 | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | 20,000.00 | 20,000.00 |
| 0007 | 804-03-02120 | Steel Piles (24" Pipe) | 6,060 | LNFT | 140.92 | 853,975.20 | 175.00 | 1,060,500.00 | 155.85 | 944,451.00 | 184.00 | 1,115,040.00 |
| 0008 | 804-03-02160 | Steel Piles (36" Pipe) | 2,450 | LNFT | 175.55 | 430,097.50 | 255.00 | 624,750.00 | 230.30 | 564,235.00 | 233.00 | 570,850.00 |
| 0009 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 841,315.00 | 841,315.00 | 345,000.00 | 345,000.00 | 623,440.00 | 623,440.00 | 625,000.00 | 625,000.00 |
| 0010 | NS-804-00007 | Ultra-High Molecular Weight Polyethylene (UHMW-PE) Panels | 3,135 | SQFT | 57.91 | 181,547.85 | 89.00 | 279,015.00 | 89.00 | 279,015.00 | 130.00 | 407,550.00 |
| CONTRACTOR TOTAL | 3,645,632.55 | 3,761,265.00 | 3,869,056.00 | 3,938,440.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - Gill's Crane & Dozer Service, Inc. |
- 10 - Aquaterra Contracting, LP |
- 11 - Cecil D. Gassiott, LLC |
- 12 - Cajun Constructors, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 500,000.00 | 500,000.00 | 469,000.00 | 469,000.00 | 110,000.00 | 110,000.00 | 312,654.00 | 312,654.00 |
| 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 9,500.00 | 9,500.00 | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 200,000.00 | 200,000.00 | 122,000.00 | 122,000.00 | 110,000.00 | 110,000.00 | 125,000.00 | 125,000.00 |
| 0004 | 730-09-00100 | Electrical System | 1 | LUMP | 700,000.00 | 700,000.00 | 679,000.00 | 679,000.00 | 500,000.00 | 500,000.00 | 800,000.00 | 800,000.00 |
| 0005 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 27,000.00 | 27,000.00 | 20,000.00 | 20,000.00 | 10,900.00 | 10,900.00 |
| 0007 | 804-03-02120 | Steel Piles (24" Pipe) | 6,060 | LNFT | 263.00 | 1,593,780.00 | 179.00 | 1,084,740.00 | 330.00 | 1,999,800.00 | 265.00 | 1,605,900.00 |
| 0008 | 804-03-02160 | Steel Piles (36" Pipe) | 2,450 | LNFT | 260.00 | 637,000.00 | 262.00 | 641,900.00 | 450.00 | 1,102,500.00 | 375.00 | 918,750.00 |
| 0009 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 300,000.00 | 300,000.00 | 1,087,000.00 | 1,087,000.00 | 420,000.00 | 420,000.00 | 1,495,000.00 | 1,495,000.00 |
| 0010 | NS-804-00007 | Ultra-High Molecular Weight Polyethylene (UHMW-PE) Panels | 3,135 | SQFT | 80.00 | 250,800.00 | 113.00 | 354,255.00 | 90.00 | 282,150.00 | 225.00 | 705,375.00 |
| CONTRACTOR TOTAL | 4,221,580.00 | 4,474,395.00 | 4,554,450.00 | 5,978,579.00 | ||||||||